Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

16 U.S.C. § 824a Interconnection and coordination of facilities; emergencies; transmission to foreign countries

+38 −4Shown
More for 16 U.S.C. § 824a
Read § 824aOnly this section
14 changes the bill asks for here, 14 carried out
  1. Carried out:

    by striking Commission after During the continuance of any war in which the United States is engaged, or whenever the and inserting Secretary of Energy (referred to in this subsection as the Secretary);

  2. Carried out:

    by striking or other causes, the Commission and inserting the Secretary;

  3. Carried out:

    by striking its own motion and inserting the Secretary’s motion;

  4. Carried out:

    by striking its judgment and inserting the Secretary’s judgment;

  5. Carried out:

    by inserting As part of the order, the Secretary shall explain why such order, including the requirements under such order, will best meet the emergency and serve the public interest. after serve the public interest.; and

  6. Carried out:

    by striking Commission after carrying out such order, the and inserting Federal Energy Regulatory Commission (referred to in this subsection as the Commission);

  7. Carried out:

    by striking Commission after law or regulation, the and inserting Secretary; and

  8. Carried out:

    by adding at the end the following:(A) that is in effect for 96 or fewer hours, the specific hours that are necessary to meet the emergency and serve the public interest; or (B) that is in effect for more than 96 hours, the specific methodology by which such hours that are necessary to meet the emergency and …

  9. Carried out:

    by striking Commission each place it appears and inserting Secretary;

  10. Carried out:

    in subparagraph (A), by striking that may result in a conflict with a requirement of any Federal, State, or local environmental law or regulation;

  11. Carried out:

    by inserting that may result in a conflict with a requirement of any Federal, State, or local environmental law or regulation after In renewing or reissuing an order under subparagraph (A); and

  12. Carried out:

    by inserting The Secretary shall publicly identify the primary Federal agency consulted. after practicable.; and

  13. Carried out:

    by adding at the end the following:(C) Before renewing or reissuing an order under subparagraph (A), the Secretary shall undertake a robust study of available alternatives that would reduce the net costs as compared to renewing or reissuing the order. (D) In the event the Secretary issues a renewed or reissued …

  14. Carried out:

    by adding at the end the following:(6) (A) Not later than 30 days after the date on which the Secretary issues an order under this subsection (including any renewal or reissuance of an order under this subsection), the Commission shall publish, including on a publicly accessible website, a report on— (i) the …

§ 824a(a)–(e)

§ 824a. Interconnection and coordination of facilities; emergencies; transmission to foreign countries

(a) Regional districts; establishment; notice to State commissions For the purpose of assuring an abundant supply of electric energy throughout the United States with the greatest possible economy and with regard to the proper utilization and conservation of natural resources, the Commission is empowered and directed to divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy, and it may at any time thereafter, upon its own motion or upon application, make such modifications thereof as in its judgment will promote the public interest. Each such district shall embrace an area which, in the judgment of the Commission, can economically be served by such interconnection and coordinated electric facilities. It shall be the duty of the Commission to promote and encourage such interconnection and coordination within each such district and between such districts. Before establishing any such district and fixing or modifying the boundaries thereof the Commission shall give notice to the State commission of each State situated wholly or in part within such district, and shall afford each such State commission reasonable opportunity to present its views and recommendations, and shall receive and consider such views and recommendations.

(b) Sale or exchange of energy; establishing physical connections Whenever the Commission, upon application of any State commission or of any person engaged in the transmission or sale of electric energy, and after notice to each State commission and public utility affected and after opportunity for hearing, finds such action necessary or appropriate in the public interest it may by order direct a public utility (if the Commission finds that no undue burden will be placed upon such public utility thereby) to establish physical connection of its transmission facilities with the facilities of one or more other persons engaged in the transmission or sale of electric energy, to sell energy to or exchange energy with such persons: Provided, That the Commission shall have no authority to compel the enlargement of generating facilities for such purposes, nor to compel such public utility to sell or exchange energy when to do so would impair its ability to render adequate service to its customers. The Commission may prescribe the terms and conditions of the arrangement to be made between the persons affected by any such order, including the apportionment of cost between them and the compensation or reimbursement reasonably due to any of them.

(c) Temporary connection and exchange of facilities during emergency

(1) During the continuance of any war in which the United States is engaged, or whenever the [struck: Commission][inserted: Secretary] [inserted: of Energy (referred to in this subsection as the “Secretary”) ]determines that an emergency exists by reason of a sudden increase in the demand for electric energy, or a shortage of electric energy or of facilities for the generation or transmission of electric energy, or of fuel or water for generating facilities, [struck: or other causes, ]the [struck: Commission][inserted: Secretary] shall have authority, either upon [struck: its][inserted: the] [struck: own][inserted: Secretary’s] motion or upon complaint, with or without notice, hearing, or report, to require by order such temporary connections of facilities and such generation, delivery, interchange, or transmission of electric energy as in [struck: its][inserted: the] [inserted: Secretary’s ]judgment will best meet the emergency and serve the public interest. [inserted: As part of the order, the Secretary shall explain why such order, including the requirements under such order, will best meet the emergency and serve the public interest. ]If the parties affected by such order fail to agree upon the terms of any arrangement between them in carrying out such order, the [inserted: Federal Energy Regulatory ]Commission[inserted: (referred to in this subsection as the “Commission”)], after hearing held either before or after such order takes effect, may prescribe by supplemental order such terms as it finds to be just and reasonable, including the compensation or reimbursement which should be paid to or by any such party.

(2) With respect to an order issued under this subsection that may result in a conflict with a requirement of any Federal, State, or local environmental law or regulation, the [struck: Commission][inserted: Secretary] shall ensure that such order requires generation, delivery, interchange, or transmission of electric energy only during hours necessary to meet the emergency and serve the public interest, and, to the maximum extent practicable, is consistent with any applicable Federal, State, or local environmental law or regulation and minimizes any adverse environmental impacts.

(A) [inserted: that is in effect for 96 or fewer hours, the specific hours that are necessary to meet the emergency and serve the public interest; or]

(B) [inserted: that is in effect for more than 96 hours, the specific methodology by which such hours that are necessary to meet the emergency and serve the public interest were determined.]

(3) To the extent any omission or action taken by a party, that is necessary to comply with an order issued under this subsection, including any omission or action taken to voluntarily comply with such order, results in noncompliance with, or causes such party to not comply with, any Federal, State, or local environmental law or regulation, such omission or action shall not be considered a violation of such environmental law or regulation, or subject such party to any requirement, civil or criminal liability, or a citizen suit under such environmental law or regulation.

(4)

(A) An order issued under this subsection [struck: that may result in a conflict with a requirement of any Federal, State, or local environmental law or regulation ]shall expire not later than 90 days after it is issued. The [struck: Commission][inserted: Secretary] may renew or reissue such order pursuant to paragraphs (1) and (2) for subsequent periods, not to exceed 90 days for each period, as the [struck: Commission][inserted: Secretary] determines necessary to meet the emergency and serve the public interest.

(B) In renewing or reissuing an order under subparagraph (A)[inserted: that may result in a conflict with a requirement of any Federal], [inserted: State, or local environmental law or regulation, ]the [struck: Commission][inserted: Secretary] shall consult with the primary Federal agency with expertise in the environmental interest protected by such law or regulation, and shall include in any such renewed or reissued order such conditions as such Federal agency determines necessary to minimize any adverse environmental impacts to the extent practicable. The [inserted: Secretary shall publicly identify the primary Federal agency consulted. The ]conditions, if any, submitted by such Federal agency shall be made available to the public. The [struck: Commission][inserted: Secretary] may exclude such a condition from the renewed or reissued order if it determines that such condition would prevent the order from adequately addressing the emergency necessitating such order and provides in the order, or otherwise makes publicly available, an explanation of such determination.

(C) [inserted: Before renewing or reissuing an order under subparagraph (A), the Secretary shall undertake a robust study of available alternatives that would reduce the net costs as compared to renewing or reissuing the order.]

(D) [inserted: In the event the Secretary issues a renewed or reissued order under this paragraph, a petition for judicial review of such renewed or reissued order may be filed under section 313(b) without filing a request for rehearing or otherwise complying with any requirements of section 313(a).]

(5) If an order issued under this subsection is subsequently stayed, modified, or set aside by a court pursuant to section 825l of this title or any other provision of law, any omission or action previously taken by a party that was necessary to comply with the order while the order was in effect, including any omission or action taken to voluntarily comply with the order, shall remain subject to paragraph (3).

(6)

(A) [inserted: Not later than 30 days after the date on which the Secretary issues an order under this subsection (including any renewal or reissuance of an order under this subsection), the Commission shall publish, including on a publicly accessible website, a report on—]

(i) [inserted: the results of the study of alternatives under paragraph (4), if applicable;]

(ii) [inserted: the causes of the applicable emergency;]

(iii) [inserted: estimates of the costs that are expected to be incurred by any electric utility and customers of such electric utility as a result of the order; and]

(iv) [inserted: other expected impacts of the order.]

(B) [inserted: Not later than 60 days after the date on which the Secretary issues an order under this subsection (including any renewal or reissuance of an order under this subsection), an electric utility that has been, or is expected to be, affected as a result of the order, including any electric utility described in subparagraph (A)(iii), shall provide in writing to customers of the electric utility a description of the costs incurred due to the order, or costs expected to be incurred as a result of the order, including any information relevant to the electric utility and the customers of the electric utility published in the applicable report under subparagraph (A).]

(7)

(A) [inserted: Except as provided in subparagraph (B), the Commission may not issue an order under this subsection (including any renewal or reissuance of an order under this subsection) that would—]

(i) [inserted: prevent or delay the retirement or other permanent closure of a facility for the generation of electric energy; or]

(ii) [inserted: require the generation of electric energy at a facility that has retired or otherwise permanently closed.]

(B) [inserted: Subparagraph (A) shall not apply to a particular facility if—]

(i) [inserted: an emergency exists that cannot be met in any manner other than the delay of the retirement or other permanent closure of the facility; and]

(ii) [inserted: the applicable Transmission Organization requests in writing to the Secretary to delay the retirement or other permanent closure of the facility.]

(d) Temporary connection during emergency by persons without jurisdiction of Commission During the continuance of any emergency requiring immediate action, any person or municipality engaged in the transmission or sale of electric energy and not otherwise subject to the jurisdiction of the Commission may make such temporary connections with any public utility subject to the jurisdiction of the Commission or may construct such temporary facilities for the transmission of electric energy in interstate commerce as may be necessary or appropriate to meet such emergency, and shall not become subject to the jurisdiction of the Commission by reason of such temporary connection or temporary construction: Provided, That such temporary connection shall be discontinued or such temporary construction removed or otherwise disposed of upon the termination of such emergency: Provided further, That upon approval of the Commission permanent connections for emergency use only may be made hereunder.

(e) Transmission of electric energy to foreign country After six months from August 26, 1935, no person shall transmit any electric energy from the United States to a foreign country without first having secured an order of the Commission authorizing it to do so. The Commission shall issue such order upon application unless, after opportunity for hearing, it finds that the proposed transmission would impair the sufficiency of electric supply within the United States or would impede or tend to impede the coordination in the public interest of facilities subject to the jurisdiction of the Commission. The Commission may by its order grant such application in whole or in part, with such modifications and upon such terms and conditions as the Commission may find necessary or appropriate, and may from time to time, after opportunity for hearing and for good cause shown, make such supplemental orders in the premises as it may find necessary or appropriate.

Rest of § 824a unchanged ·