10 U.S.C. § 3204 Use of procedures other than competitive procedures
7 changes the bill asks for here, 7 carried out
- Carried out:
in subparagraph (E), by striking
and
; - Carried out:
in subparagraph (F), by striking the period and inserting a semicolon
;
and - Carried out:
by adding at the end the following new subparagraphs:
(G) whether or not a subcontracting plan was made for this contract; and (H) a statement that the justification was coordinated with the Office of Small Business Programs.;
- Carried out:
in clause (i), by striking
; or
and inserting a semicolon;
- Carried out:
in clause (ii), by striking the period and inserting
; or
; and - Carried out:
by adding at the end the following new clause:
(iii) maintain a contracting relationship with the prime contractor.; and
- Carried out:
by adding at the end the following new paragraph:
(8) For each contract entered into pursuant to subsection (a) for which a justification and approval is required by paragraph (1), the Secretary of Defense shall provide written notification to the Committees on Armed Services and Small Business of the House of Representatives …
§ 3204(e)Justification for Use of Procedures Other Than Competitive Procedures.—(2)–(4)
Start of § 3204 to (e)(2)(C) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (2)(D) | (D) | (D) | ||
| a description of the market survey conducted or a statement of the reasons a market survey was not conducted; | a description of the market survey conducted or a statement of the reasons a market survey was not conducted; | |||
| (2)(E) | (E) | (E) | ||
| a listing of the sources, if any, that expressed in writing an interest in the procurement; | a listing of the sources, if any, that expressed in writing an interest in the procurement; | |||
| (2)(F) | (F) | (F) | ||
| a statement of the actions, if any, the agency may take to remove or overcome any barrier to competition before a subsequent procurement for such needs | a statement of the actions, if any, the agency may take to remove or overcome any barrier to competition before a subsequent procurement for such needs[inserted: ;] | |||
| (2)(G) | (G) [inserted: ] | |||
| [inserted: whether or not a subcontracting plan was made for this contract; and] | ||||
| (2)(H) | (H) [inserted: ] | |||
| [inserted: a statement that the justification was coordinated with the Office of Small Business Programs.] | ||||
| (3) | (3) Justification and approval allowed after contract awarded.— | (3) Justification and approval allowed after contract awarded.— | ||
| In the case of a procurement permitted by subsection (a)(2), the justification and approval required by paragraph (1) may be made after the contract is awarded. | In the case of a procurement permitted by subsection (a)(2), the justification and approval required by paragraph (1) may be made after the contract is awarded. | |||
| (4) | (4) Justification and approval not required.— | (4) Justification and approval not required.— | ||
| The justification and approval required by paragraph (1) is not required— | The justification and approval required by paragraph (1) is not required— | |||
§ 3204(e)Justification for Use of Procedures Other Than Competitive Procedures.—(5)–(6)
(e)(4)(A)–(5) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (5)(A) | (A) | (A) | ||
| In no case may the head of an agency— | In no case may the head of an agency— | |||
| (5)(A)(i) | (i) | (i) | ||
| enter into a contract for property or services using procedures other than competitive procedures on the basis of the lack of advance planning or concerns related to the amount of funds available to the agency for procurement functions; | enter into a contract for property or services using procedures other than competitive procedures on the basis of the lack of advance planning or concerns related to the amount of funds available to the agency for procurement functions; | |||
| (5)(A)(ii) | (ii) | (ii) | ||
| procure property or services from another agency unless such other agency complies fully with the requirements of chapter 137 legacy provisions in its procurement of such property or services | procure property or services from another agency unless such other agency complies fully with the requirements of chapter 137 legacy provisions in its procurement of such property or services[inserted: ; or] | |||
| (5)(A)(iii) | (iii) [inserted: ] | |||
| [inserted: maintain a contracting relationship with the prime contractor.] | ||||
| (5)(B) | (B) | (B) | ||
| The restriction contained in subparagraph (A)(ii) is in addition to, and not in lieu of, any other restriction provided by law. | The restriction contained in subparagraph (A)(ii) is in addition to, and not in lieu of, any other restriction provided by law. | |||
| (6) | (6) Limitation on Delegations of Authority Under Paragraph (1)(B).— | (6) Limitation on Delegations of Authority Under Paragraph (1)(B).— | ||
§ 3204(e)–(f)
(e)(6)(A)–(B) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (e)(6)(B)(ii)(II) | (II) | (II) | ||
| if a civilian, is serving in a position with a grade under the General Schedule (or any other schedule for civilian officers or employees) that is comparable to or higher than the grade of major general or rear admiral. | if a civilian, is serving in a position with a grade under the General Schedule (or any other schedule for civilian officers or employees) that is comparable to or higher than the grade of major general or rear admiral. | |||
| (e)(7) | (7) Justification and approval not required for phase iii sbir award.— | (7) Justification and approval not required for phase iii sbir award.— | ||
| The justification and approval required by paragraph (1) is not required in the case of a Phase III award made pursuant to section 9(r)(4) of the Small Business Act (15 U.S.C. 638(r)(4)). | The justification and approval required by paragraph (1) is not required in the case of a Phase III award made pursuant to section 9(r)(4) of the Small Business Act (15 U.S.C. 638(r)(4)). | |||
| (e)(8) | (8) [inserted: ] | |||
| [inserted: For each contract entered into pursuant to subsection (a) for which a justification and approval is required by paragraph (1), the Secretary of Defense shall provide written notification to the Committees on Armed Services and Small Business of the House of Representatives and the Committees on Armed Services and Small Business and Entrepreneurship of the Senate that the contract did not result in a bundling of contract requirements (as defined in section 3(o) of the Small Business Act (15 U.S.C. 632(o))).] | ||||
| (f) | (f) Public Availability of Justification and Approval Required for Using Procedures Other Than Competitive Procedures.— | (f) Public Availability of Justification and Approval Required for Using Procedures Other Than Competitive Procedures.— | ||
| (f)(1) | (1) Time requirement.— | (1) Time requirement.— | ||
| (f)(1)(A) | (A) Within 14 days after contract award.— | (A) Within 14 days after contract award.— | ||
| Except as provided in subparagraph (B), in the case of a procurement permitted by subsection (a), the head of an agency shall make publicly available, within 14 days after the award of the contract, the documents containing the justification and approval required by subsection (e)(1) with respect to the procurement. | Except as provided in subparagraph (B), in the case of a procurement permitted by subsection (a), the head of an agency shall make publicly available, within 14 days after the award of the contract, the documents containing the justification and approval required by subsection (e)(1) with respect to the procurement. | |||
Rest of § 3204 unchanged