H.R. 10989 · Smart Transmission Line Placement Act ·

In committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

Federal Power Act § 216A Grid capacity expansion in existing rights-of-way New section

+54 −0Shown
More for Federal Power Act § 216A
1 change the bill asks for here, 1 carried out
  1. Carried out:

    The Federal Power Act is amended by inserting after section 216 (16 U.S.C. 824p) the following:216A. Grid capacity expansion in existing rights-of-way (a) Definitions.— In this section: (1) Applicable electrical standard.— The term applicable electrical standard includes— (A) a reliability standard (as defined in section 215(a)); and (B) an applicable standard of the National Electrical Safety Code published by the Institute of Electrical and Electronics Engineers Standards Association. (2) Covered area.— The term covered area means an area— (A) within an existing right-of-way; or (B) within the minimum additional area adjacent to an existing right-of-way that is necessary— (i) to comply with applicable electrical standards; or (ii) to complete an activity described in subsection (b). (3) Covered facility.— The term covered facility means an existing electric transmission or distribution facility or associated infrastructure (including an electrical substation) that is located within a covered area. (b) Exemptions.— (1) In general.— Activities to maintain or increase the capacity of the electric grid within a covered area, and any Federal agency action authorizing such activities— (A) are a category of actions designated as being categorically excluded from the preparation of an environmental assessment or an environmental impact statement under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and (B) shall not be considered to be— (i) a major Federal action for purposes of that Act; or (ii) an undertaking for purposes of section 306108 of title 54, United States Code. (2) Inclusions.— The activities described in paragraph (1) include— (A) any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation of, or addition to, a covered facility, including— (i) reconductoring; (ii) an increase in operating voltage; (iii) a circuit addition or adjustment; and (iv) installation of advanced transmission technologies (as defined in section 1223(a) of the Energy Policy Act of 2005 (42 U.S.C. 16422(a))); (B) any minimum widening of an existing right-of-way associated with an activity described in subparagraph (A) that— (i) is necessary to comply with applicable electrical standards; or (ii) remains within a covered area; (C) an addition of energy storage at or near a covered facility; and (D) the addition of a parallel circuit within an existing right-of-way..

§ 216A(a)–(b)

WhereMarkText
§ 216A. [inserted: Grid capacity expansion in existing rights-of-way]
(a)(a) [inserted: Definitions.—]
[inserted: In this section:]
(a)(1)(1) [inserted: Applicable electrical standard.—]
[inserted: The term “applicable electrical standard” includes—]
(a)(1)(A)(A) [inserted: ]
[inserted: a reliability standard (as defined in section 215(a)); and]
(a)(1)(B)(B) [inserted: ]
[inserted: an applicable standard of the National Electrical Safety Code published by the Institute of Electrical and Electronics Engineers Standards Association.]
(a)(2)(2) [inserted: Covered area.—]
[inserted: The term “covered area” means an area—]
(a)(2)(A)(A) [inserted: ]
[inserted: within an existing right-of-way; or]
(a)(2)(B)(B) [inserted: ]
[inserted: within the minimum additional area adjacent to an existing right-of-way that is necessary—]
(a)(2)(B)(i)(i) [inserted: ]
[inserted: to comply with applicable electrical standards; or]
(a)(2)(B)(ii)(ii) [inserted: ]
[inserted: to complete an activity described in subsection (b).]
(a)(3)(3) [inserted: Covered facility.—]
[inserted: The term “covered facility” means an existing electric transmission or distribution facility or associated infrastructure (including an electrical substation) that is located within a covered area.]
(b)(b) [inserted: Exemptions.—]
(b)(1)(1) [inserted: In general.—]
[inserted: Activities to maintain or increase the capacity of the electric grid within a covered area, and any Federal agency action authorizing such activities—]
(b)(1)(A)(A) [inserted: ]
[inserted: are a category of actions designated as being categorically excluded from the preparation of an environmental assessment or an environmental impact statement under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and]
(b)(1)(B)(B) [inserted: ]
[inserted: shall not be considered to be—]
(b)(1)(B)(i)(i) [inserted: ]
[inserted: a major Federal action for purposes of that Act; or]
(b)(1)(B)(ii)(ii) [inserted: ]
[inserted: an undertaking for purposes of section 306108 of title 54, United States Code.]
(b)(2)(2) [inserted: Inclusions.—]
[inserted: The activities described in paragraph (1) include—]
(b)(2)(A)(A) [inserted: ]
[inserted: any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation of, or addition to, a covered facility, including—]
(b)(2)(A)(i)(i) [inserted: ]
[inserted: reconductoring;]
(b)(2)(A)(ii)(ii) [inserted: ]
[inserted: an increase in operating voltage;]
(b)(2)(A)(iii)(iii) [inserted: ]
[inserted: a circuit addition or adjustment; and]
(b)(2)(A)(iv)(iv) [inserted: ]
[inserted: installation of advanced transmission technologies (as defined in section 1223(a) of the Energy Policy Act of 2005 (42 U.S.C. 16422(a)));]
(b)(2)(B)(B) [inserted: ]
[inserted: any minimum widening of an existing right-of-way associated with an activity described in subparagraph (A) that—]
(b)(2)(B)(i)(i) [inserted: ]
[inserted: is necessary to comply with applicable electrical standards; or]
(b)(2)(B)(ii)(ii) [inserted: ]
[inserted: remains within a covered area;]
(b)(2)(C)(C) [inserted: ]
[inserted: an addition of energy storage at or near a covered facility; and]
(b)(2)(D)(D) [inserted: ]
[inserted: the addition of a parallel circuit within an existing right-of-way.]