26 U.S.C. § 48 Energy credit

+23 −46 of 7 shown
More for 26 U.S.C. § 48
Read § 48
7 changes the bill asks for here, 6 carried out
  1. Carried out:

    in subclause (VIII), by striking and, and

  2. Carried out:

    by adding at the end the following new subclause:(X) sustainable aviation fuel production property, and,

  3. Carried out:

    in paragraph (3)(A), by striking or at the end of clause (x), inserting or at the end of clause (xi), and by adding at the end the following new clause: (xii) sustainable aviation fuel production property,, and

  4. Not carried out:

    in paragraph (3)(A), by striking or at the end of clause (x), inserting or at the end of clause (xi), and by adding at the end the following new clause:(xii) sustainable aviation fuel production property,, and

    We can't read how this instruction is worded yet, so it isn't shown in the text.

    Technical detailno-pattern: inserting QTEXT at the end of clause (X), and by adding at the end the following new clause: QCONTENT, and
  5. Carried out:

    by redesignating paragraph (16) as paragraph (17) and by inserting after paragraph (15) the following new paragraph: (16) Phaseout for sustainable aviation fuel production property.— In the case of any energy property described in paragraph (3)(A)(xii) the construction of which begins before January 1, 2039, the energy percentage determined under paragraph (2) shall be equal to— (A) in the case of any property the construction of which begins after December 31, 2030, and before January 1, 2032, 24 percent, (B) in the case of any property the construction of which begins after December 31, 2031, and before January 1, 2033, 18 percent, and (C) in the case of any property the construction of which begins after December 31, 2032, and before January 1, 2039, 12 percent., and

  6. Carried out:

    by redesignating paragraph (16) as paragraph (17) and by inserting after paragraph (15) the following new paragraph:(16) Phaseout for sustainable aviation fuel production property.— In the case of any energy property described in paragraph (3)(A)(xii) the construction of which begins before January 1, 2039, the energy percentage determined under paragraph (2) shall be equal to— (A) in the …

  7. Carried out:

    in subsection (c), by adding at the end the following new paragraph:(9) Sustainable aviation fuel production property.— (A) In general.— The term “sustainable aviation fuel production property” means— (i) property which produces sustainable aviation fuel (as defined in section 40B(d)), or (ii) property directly related to enabling the production …

§ 48(a)(2)Energy percentage(A)–(B)

Start of § 48 to (a)(2)(A)(i)(VI) unchanged ·

(VII) qualified biogas property,

(VIII) microgrid controllers,[struck: and]

(IX) energy property described in clauses (v) and (vii) of paragraph (3)(A), and

(X) [inserted: sustainable aviation fuel production property, and]

(ii) in the case of any energy property to which clause (i) does not apply, 0 percent.

(B) Coordination with rehabilitation credit The energy percentage shall not apply to that portion of the basis of any property which is attributable to qualified rehabilitation expenditures.

§ 48(a)(3)Energy property(A)–(B)

(a)(2)(C)–(3)(A) unchanged ·

(ix) energy storage technology,

(x) qualified biogas property,[struck: or]

(xi) microgrid controllers,

(B)

§ 48(a)–(c)

(a)(3)(B)(i)–(15)(C)(iii) unchanged ·

(D) Qualified clean hydrogen For purposes of this paragraph, the term “qualified clean hydrogen” has the meaning given such term by section 45V(c)(2).

(E) Regulations The Secretary shall issue such regulations or other guidance as the Secretary determines necessary to carry out the purposes of this section, including regulations or other guidance which recaptures so much of any credit allowed under this section as exceeds the amount of the credit which would have been allowed if the expected production were consistent with the actual verified production (or all of the credit so allowed in the absence of such verification).

(16) [inserted: Phaseout for sustainable aviation fuel production property.—] [inserted: In the case of any energy property described in paragraph (3)(A)(xii) the construction of which begins before January 1, 2039, the energy percentage determined under paragraph (2) shall be equal to—]

(A) [inserted: in the case of any property the construction of which begins after December 31, 2030, and before January 1, 2032, 24 percent,]

(B) [inserted: in the case of any property the construction of which begins after December 31, 2031, and before January 1, 2033, 18 percent, and]

(C) [inserted: in the case of any property the construction of which begins after December 31, 2032, and before January 1, 2039, 12 percent.]

[struck: (16)] [inserted: (17)] Regulations and guidance The Secretary shall issue such regulations or other guidance as the Secretary determines necessary to carry out the purposes of this subsection, including regulations or other guidance which provides for requirements for recordkeeping or information reporting for purposes of administering the requirements of this subsection.

(b) Certain progress expenditure rules made applicable Rules similar to the rules of subsections (c)(4) and (d) of section 46 (as in effect on the day before the date of the enactment of the Revenue Reconciliation Act of 1990) shall apply for purposes of subsection (a).

(c) Definitions For purposes of this section—

§ 48(c)–(d)

(c)(1)–(8) unchanged ·

(iii) is not part of a bulk-power system (as defined in section 215 of the Federal Power Act (16 U.S.C. 824o)).

(C) Termination The term “microgrid controller” shall not include any property the construction of which begins after December 31, 2024.

(9) [inserted: Sustainable aviation fuel production property.—]

(A) [inserted: In general.—] [inserted: The term “sustainable aviation fuel production property” means—]

(i) [inserted: property which produces sustainable aviation fuel (as defined in section 40B(d)), or]

(ii) [inserted: property directly related to enabling the production or distribution of sustainable aviation fuel.]

(B) [inserted: Recapture of credit.—] [inserted: The Secretary shall, by regulations, provide for recapturing the benefit of any credit allowable under subsection (a)(3)(A)(xii) with respect to any sustainable aviation fuel production property if the sustainable aviation fuel production of such property comprises less than 80 percent of the total fuel production of such property in any of the 5 taxable years immediately following the taxable year in which such property was placed in service.]

(d) Coordination with Department of Treasury grants In the case of any property with respect to which the Secretary makes a grant under section 1603 of the American Recovery and Reinvestment Tax Act of 2009—

(1) Denial of production and investment credits No credit shall be determined under this section or section 45 with respect to such property for the taxable year in which such grant is made or any subsequent taxable year.

Rest of § 48 unchanged ·

Step through the changes