H.R. 3059 · Streamlining Critical Mineral Permitting Act ·

In committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

42 U.S.C. § 6925 Permits for treatment, storage, or disposal of hazardous waste

+14 −2Shown
More for 42 U.S.C. § 6925
Read § 6925Only this section
4 changes the bill asks for here, 4 carried out
  1. Carried out:

    in clause (i), by striking or at the end;

  2. Carried out:

    in clause (ii), by inserting or after this section,; and

  3. Carried out:

    by adding at the end the following:(iii) is a critical energy resource facility,; and

  4. Carried out:

    by adding at the end the following:(4) Definitions.— For the purposes of this subsection: (A) Critical energy resource.— The term “critical energy resource” means, as determined by the Secretary of Energy, any energy resource— (i) that is essential to the energy sector and energy systems of the United States; and …

§ 6925(e)(1)Any person who—(A)–(C)

Start of § 6925 to (e)(1) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(A)(A) (A)
owns or operates a facility required to have a permit under this section which facility—owns or operates a facility required to have a permit under this section which facility—
(A)(i)(i) (i)
was in existence on November 19, 1980,[struck: or]was in existence on November 19, 1980,
(A)(ii)(ii) (ii)
is in existence on the effective date of statutory or regulatory changes under this chapter that render the facility subject to the requirement to have a permit under this section,is in existence on the effective date of statutory or regulatory changes under this chapter that render the facility subject to the requirement to have a permit under this section,[inserted: or]
(A)(iii)(iii) [inserted: ]
[inserted: is a critical energy resource facility,]
(B)(B) (B)
has complied with the requirements of section 6930(a) of this title, andhas complied with the requirements of section 6930(a) of this title, and
(C)(C) (C)
has made an application for a permit under this section,has made an application for a permit under this section,

§ 6925(e)–(g)

(e)(1)–(3) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(e)(3)(A)(A) (A)
applies for a final determination regarding the issuance of a permit under subsection (c) for such facility before the date twelve months after the date on which the facility first becomes subject to such permit requirement; andapplies for a final determination regarding the issuance of a permit under subsection (c) for such facility before the date twelve months after the date on which the facility first becomes subject to such permit requirement; and
(e)(3)(B)(B) (B)
certifies that such facility is in compliance with all applicable groundwater monitoring and financial responsibility requirements.certifies that such facility is in compliance with all applicable groundwater monitoring and financial responsibility requirements.
(e)(4)(4) [inserted: Definitions.—]
[inserted: For the purposes of this subsection:]
(e)(4)(A)(A) [inserted: Critical energy resource.—]
[inserted: The term “critical energy resource” means, as determined by the Secretary of Energy, any energy resource—]
(e)(4)(A)(i)(i) [inserted: ]
[inserted: that is essential to the energy sector and energy systems of the United States; and]
(e)(4)(A)(ii)(ii) [inserted: ]
[inserted: the supply chain of which is vulnerable to disruption.]
(e)(4)(B)(B) [inserted: Critical energy resource facility.—]
[inserted: The term “critical energy resource facility” means a facility that processes or refines a critical energy resource.]
(f)(f) Coal mining wastes and reclamation permits(f) Coal mining wastes and reclamation permits
Notwithstanding subsection (a) through (e) of this section, any surface coal mining and reclamation permit covering any coal mining wastes or overburden which has been issued or approved under the Surface Mining Control and Reclamation Act of 1977 [30 U.S.C. 1201 et seq.] shall be deemed to be a permit issued pursuant to this section with respect to the treatment, storage, or disposal of such wastes or overburden. Regulations promulgated by the Administrator under this subchapter shall not be applicable to treatment, storage, or disposal of coal mining wastes and overburden which are covered by such a permit.Notwithstanding subsection (a) through (e) of this section, any surface coal mining and reclamation permit covering any coal mining wastes or overburden which has been issued or approved under the Surface Mining Control and Reclamation Act of 1977 [30 U.S.C. 1201 et seq.] shall be deemed to be a permit issued pursuant to this section with respect to the treatment, storage, or disposal of such wastes or overburden. Regulations promulgated by the Administrator under this subchapter shall not be applicable to treatment, storage, or disposal of coal mining wastes and overburden which are covered by such a permit.
(g)(g) Research, development, and demonstration permits(g) Research, development, and demonstration permits

Rest of § 6925 unchanged

Step through the changes