H.R. 3059
Streamlining Critical Mineral Permitting Act
The bill's own words, as Congress.gov publishes them, without its long title and table of contents.
Sec. 1. Short title This Act may be cited as the Streamlining Critical Mineral Permitting Act.
Sec. 2. Interim hazardous waste permits Section 3005(e) of the Solid Waste Disposal Act (42 U.S.C. 6925(e)) is amended—
(1) in paragraph (1)(A)—
(A) in clause (i), by striking or at the end;
(B) in clause (ii), by inserting or after this section,; and
(C) by adding at the end the following:
(iii) is a critical energy resource facility,
; and
(2) by adding at the end the following:
(4) Definitions.— For the purposes of this subsection:
(A) Critical energy resource.— The term “critical energy resource” means, as determined by the Secretary of Energy, any energy resource—
(i) that is essential to the energy sector and energy systems of the United States; and
(ii) the supply chain of which is vulnerable to disruption.
(B) Critical energy resource facility.— The term “critical energy resource facility” means a facility that processes or refines a critical energy resource.
.