Skip to content
The People's CodeSearch
Menu

Title 10 · Armed ForcesThe military

Changes to 10 U.S.C. § 3702

H.R. 3838 · Streamlining Procurement for Effective Execution and Delivery and National Defense Authorization Act for Fiscal Year 2026 ·

Passed the House · step 3 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

10 U.S.C. § 3702 Required cost or pricing data and certification

Couldn't place 5 changes
More for 10 U.S.C. § 3702
Read § 3702

3 of the 5 changes this bill asks for here are already in the law as it stands, and were not made a second time. The bill, or another making the same changes, has probably become law since.

1 of the 5 changes this bill asks for here names words or provisions the section had before but doesn't now: the law has changed since the bill was written, so it is not marked.

The bill's words for this section

  1. Not carried out:

    by striking 2018 each place it appears and inserting 2026;

    “2018” isn't in § 3702(a)(1) in the Code as we have it. It was there before, as of Public Law 119-36: the law has changed since the bill was written.

    Technical detail“2018” not found in /us/usc/t10/s3702/a/1
  2. Not carried out:

    in subparagraph (A), by striking $2,000,000 and inserting $10,000,000; and

    The law already reads this way: § 3702(a)(1)(A) already has “$10,000,000”.

    Technical detailalready reads “$10,000,000” in /us/usc/t10/s3702/a/1/A
  3. Not carried out:

    in subparagraph (B), by striking $750,000 and inserting $2,000,000;

    The law already reads this way: § 3702(a)(1)(B) already has “$2,000,000”.

    Technical detailalready reads “$2,000,000” in /us/usc/t10/s3702/a/1/B
  4. Not carried out:

    in paragraph (2), by striking $2,000,000 and inserting $10,000,000; and

    The law already reads this way: § 3702(a)(2) already has “$10,000,000”.

    Technical detailalready reads “$10,000,000” in /us/usc/t10/s3702/a/2
  5. Not carried out:

    in subparagraph (3)(A), by striking chapter and the price of the subcontract is expected to exceed $2,000,000 and inserting the following:(i) in the case of a prime contract entered into after June 30, 2026, the price of the subcontract is expected to exceed $10,000,000; or (ii) in the case of a prime contract entered into on or before June 30, 2026, the price of the subcontract is expected to exceed $2,000,000. chapter and—.

    The bill points to subparagraph (3) of § 3702(a), which isn't there in the Code as we have it. It may have been renumbered or removed since the bill was drafted.

    Technical detailtarget not found: no subparagraph (3) in /us/usc/t10/s3702/a

Step through the changes