Title 33 · Navigation and Navigable Waters
Changes to 33 U.S.C. § 1342
H.R. 3898 · PERMIT Act · Referred The text sent to a committee of the other chamber after one chamber passed it.
Passed the House · step 3 of 5
33 U.S.C. § 1342 National pollutant discharge elimination system
10 changes the bill asks for here, 9 carried out
- Carried out:
Section 402(a) of the Federal Water Pollution Control Act (33 U.S.C. 1342(a)) is amended by adding at the end the following:
(6) General permits.— (A) Permits authorized.— The Administrator may issue general permits under this section on a State, regional, or nationwide basis, or for a delineated area, for discharges associated with any category of activities, which discharges are of similar types and …
- Carried out:
Section 402(b)(1)(B) of the Federal Water Pollution Control Act (33 U.S.C. 1342(b)(1)(B)) is amended by striking
five years
and insertingten years
. - Not carried out:
by striking (k) Compliance with and inserting the following:(k) Compliance with permits.— (1) In general.— Subject to paragraph (2), compliance with; and
The bill gives this provision a heading and rewords it at the same time, a kind of change we can't show yet.
Technical detail
the provision inserted says more than a heading and the words struck - Carried out:
by adding at the end the following:
(2) Scope.— For purposes of paragraph (1), compliance with the conditions of a permit issued under this section shall be considered compliance with respect to a discharge of— (A) any pollutant for which an effluent limitation is included in the permit; and (B) any pollutant for …
- Carried out:
Section 402 of the Federal Water Pollution Control Act (33 U.S.C. 1342) is amended by adding at the end the following:
(t) Expression of water quality-Based effluent limitations.— If the Administrator (or a State, in the case of a permit program approved by the Administrator) determines that a water quality-based limitation on a discharge of a pollutant is necessary to include in a permit under …
- Carried out:
by striking for a discharge from and inserting the following:(i) a discharge from for—;
- Carried out:
in clause (i) (as so designated), by striking the period at the end and inserting
; or
; and - Carried out:
by adding at the end the following:
(ii) a discharge resulting from the aerial application of a product used for fire control and suppression purposes that appears on the most current Forest Service Qualified Products List (or any successor list)..
- Carried out:
Section 402(l) of the Federal Water Pollution Control Act (33 U.S.C. 1342(l)) is amended by adding at the end the following:
(4) Agricultural stormwater discharge.— (A) In general.— The Administrator shall not require a permit, nor directly or indirectly require any State to require a permit, under this section for discharges of stormwater, including from subsurface drainage, from agricultural land …
- Carried out:
Section 402 of the Federal Water Pollution Control Act (33 U.S.C. 1342) is further amended by adding at the end the following:
(u) Discharges of pesticides.— (1) No permit requirement.— Except as provided in paragraph (2), a permit shall not be required by the Administrator or a State under this Act for a discharge from a point source into navigable waters of a pesticide authorized for sale, …
§ 1342(a)–(b)
Start of § 1342 to (a)(3) unchanged ·
(4) All permits for discharges into the navigable waters issued pursuant to section 407 of this title shall be deemed to be permits issued under this subchapter, and permits issued under this subchapter shall be deemed to be permits issued under section 407 of this title, and shall continue in force and effect for their term unless revoked, modified, or suspended in accordance with the provisions of this chapter.
(5) No permit for a discharge into the navigable waters shall be issued under section 407 of this title after October 18, 1972. Each application for a permit under section 407 of this title, pending on October 18, 1972, shall be deemed to be an application for a permit under this section. The Administrator shall authorize a State, which he determines has the capability of administering a permit program which will carry out the objectives of this chapter to issue permits for discharges into the navigable waters within the jurisdiction of such State. The Administrator may exercise the authority granted him by the preceding sentence only during the period which begins on October 18, 1972, and ends either on the ninetieth day after the date of the first promulgation of guidelines required by section 1314(i)(2) of this title, or the date of approval by the Administrator of a permit program for such State under subsection (b) of this section, whichever date first occurs, and no such authorization to a State shall extend beyond the last day of such period. Each such permit shall be subject to such conditions as the Administrator determines are necessary to carry out the provisions of this chapter. No such permit shall issue if the Administrator objects to such issuance.
(6) [inserted: General permits.—]
(A) [inserted: Permits authorized.—] [inserted: The Administrator may issue general permits under this section on a State, regional, or nationwide basis, or for a delineated area, for discharges associated with any category of activities, which discharges are of similar types and from similar sources.]
(B) [inserted: Permit expiration notification requirement.—] [inserted: If a general permit issued under this section will expire and the Administrator decides not to issue a new general permit for discharges similar to those covered by the expiring general permit, the Administrator shall publish in the Federal Register a notice of such decision at least two years prior to the expiration of the general permit.]
(C) [inserted: Application of permit terms of an expired permit.—]
(i) [inserted: In general.—] [inserted: If a general permit issued under this section expires and the Administrator has not published a notice in accordance with subparagraph (B), the Administrator shall, until the date described in clause (ii)—]
(I) [inserted: continue to apply the terms, conditions, and requirements of the expired general permit to any discharge that was covered by the expired general permit; and]
(II) [inserted: apply such terms, conditions, and requirements to any discharge that would have been covered by the expired general permit (in accordance with any relevant requirements for such coverage) if the discharge had occurred before such expiration.]
(ii) [inserted: Date described.—] [inserted: The date described in this clause is the earlier of—]
(I) [inserted: the date on which the Administrator issues a new general permit for discharges similar to those covered by the expired general permit; or]
(II) [inserted: the date that is two years after the date on which the Administrator publishes in the Federal Register a notice of a decision not to issue a new general permit for discharges similar to those covered by the expired general permit.]
(b) State permit programs At any time after the promulgation of the guidelines required by subsection (i)(2) of section 1314 of this title, the Governor of each State desiring to administer its own permit program for discharges into navigable waters within its jurisdiction may submit to the Administrator a full and complete description of the program it proposes to establish and administer under State law or under an interstate compact. In addition, such State shall submit a statement from the attorney general (or the attorney for those State water pollution control agencies which have independent legal counsel), or from the chief legal officer in the case of an interstate agency, that the laws of such State, or the interstate compact, as the case may be, provide adequate authority to carry out the described program. The Administrator shall approve each submitted program unless he determines that adequate authority does not exist:
(1) To issue permits which—
(A) apply, and insure compliance with, any applicable requirements of sections 1311, 1312, 1316, 1317, and 1343 of this title;
(B) are for fixed terms not exceeding [struck: five][inserted: ten] years; and
(C) can be terminated or modified for cause including, but not limited to, the following:
(i) violation of any condition of the permit;
§ 1342(j)–(n)
(b)(1)(C)(ii)–(i) unchanged ·
(j) Public information A copy of each permit application and each permit issued under this section shall be available to the public. Such permit application or permit, or portion thereof, shall further be available on request for the purpose of reproduction.
(k) Compliance with permits Compliance with a permit issued pursuant to this section shall be deemed compliance, for purposes of sections 1319 and 1365 of this title, with sections 1311, 1312, 1316, 1317, and 1343 of this title, except any standard imposed under section 1317 of this title for a toxic pollutant injurious to human health. Until December 31, 1974, in any case where a permit for discharge has been applied for pursuant to this section, but final administrative disposition of such application has not been made, such discharge shall not be a violation of (1) section 1311, 1316, or 1342 of this title, or (2) section 407 of this title, unless the Administrator or other plaintiff proves that final administrative disposition of such application has not been made because of the failure of the applicant to furnish information reasonably required or requested in order to process the application. For the 180-day period beginning on October 18, 1972, in the case of any point source discharging any pollutant or combination of pollutants immediately prior to such date which source is not subject to section 407 of this title, the discharge by such source shall not be a violation of this chapter if such a source applies for a permit for discharge pursuant to this section within such 180-day period.
(2) [inserted: Scope.—] [inserted: For purposes of paragraph (1), compliance with the conditions of a permit issued under this section shall be considered compliance with respect to a discharge of—]
(A) [inserted: any pollutant for which an effluent limitation is included in the permit; and]
(B) [inserted: any pollutant for which an effluent limitation is not included in the permit that is—]
(i) [inserted: specifically identified as controlled or monitored through indicator parameters in the permit, the fact sheet for the permit, or the administrative record relating to the permit;]
(ii) [inserted: specifically identified during the permit application process as present in discharges to which the permit will apply; or]
(iii) [inserted: whether or not specifically identified in the permit or during the permit application process—]
(I) [inserted: present in any waste streams or processes of the point source to which the permit applies, which waste streams or processes are specifically identified during the permit application process; or]
(II) [inserted: otherwise within the scope of any operations of the point source to which the permit applies, which scope of operations is specifically identified during the permit application process.]
(l) Limitation on permit requirement
(1) Agricultural return flows The Administrator shall not require a permit under this section for discharges composed entirely of return flows from irrigated agriculture, nor shall the Administrator directly or indirectly, require any State to require such a permit.
(2) Stormwater runoff from oil, gas, and mining operations The Administrator shall not require a permit under this section, nor shall the Administrator directly or indirectly require any State to require a permit, for discharges of stormwater runoff from mining operations or oil and gas exploration, production, processing, or treatment operations or transmission facilities, composed entirely of flows which are from conveyances or systems of conveyances (including but not limited to pipes, conduits, ditches, and channels) used for collecting and conveying precipitation runoff and which are not contaminated by contact with, or do not come into contact with, any overburden, raw material, intermediate products, finished product, byproduct, or waste products located on the site of such operations.
(3) Silvicultural activities
(A) NPDES permit requirements for silvicultural activities.— [inserted: The Administrator shall not require a permit under this section nor directly or indirectly require any State to require a permit under this section for—]
(i) [inserted: a discharge from runoff resulting from the conduct of the following silviculture activities conducted in accordance with standard industry practice: nursery operations, site preparation, reforestation and subsequent cultural treatment, thinning, prescribed burning, pest and fire control, harvesting operations, surface drainage, or road construction and maintenance; or]
(ii) [inserted: a discharge resulting from the aerial application of a product used for fire control and suppression purposes that appears on the most current Forest Service Qualified Products List (or any successor list).]
[struck: The Administrator shall not require a permit under this section nor directly or indirectly require any State to require a permit under this section for a discharge from runoff resulting from the conduct of the following silviculture activities conducted in accordance with standard industry practice: nursery operations, site preparation, reforestation and subsequent cultural treatment, thinning, prescribed burning, pest and fire control, harvesting operations, surface drainage, or road construction and maintenance.]
(B) Other requirements.— Nothing in this paragraph exempts a discharge from silvicultural activity from any permitting requirement under section 1344 of this title, existing permitting requirements under section 1342 of this title, or from any other federal law.
(C) The authorization provided in Section1 1365(a) of this title does not apply to any non-permitting program established under 1342(p)(6)2 of this title for the silviculture activities listed in 1342(l)(3)(A)2 of this title, or to any other limitations that might be deemed to apply to the silviculture activities listed in 1342(l)(3)(A)2 of this title.
(4) [inserted: Agricultural stormwater discharge.—]
(A) [inserted: In general.—] [inserted: The Administrator shall not require a permit, nor directly or indirectly require any State to require a permit, under this section for discharges of stormwater, including from subsurface drainage, from agricultural land that occur in direct response to a precipitation event.]
(B) [inserted: Agricultural land defined.—] [inserted: In this paragraph, the term “agricultural land” includes—]
(i) [inserted: land on which an agricultural input (such as manure and other crop nutrients, crop protection, or seed) is applied;]
(ii) [inserted: land on which animals (including fish and shellfish), crops (including fruit and nut trees), crop residue, plants, seed, or vegetation are present for purposes of farming or ranching; and]
(iii) [inserted: land that is—]
(I) [inserted: immediately adjacent to, and functionally related to, land described in clause (i) or (ii); and]
(II) [inserted: necessary to support agricultural production, soil conservation, flood control, or water quality.]
(m) Additional pretreatment of conventional pollutants not required To the extent a treatment works (as defined in section 1292 of this title) which is publicly owned is not meeting the requirements of a permit issued under this section for such treatment works as a result of inadequate design or operation of such treatment works, the Administrator, in issuing a permit under this section, shall not require pretreatment by a person introducing conventional pollutants identified pursuant to section 1314(a)(4) of this title into such treatment works other than pretreatment required to assure compliance with pretreatment standards under subsection (b)(8) of this section and section 1317(b)(1) of this title. Nothing in this subsection shall affect the Administrator’s authority under sections 1317 and 1319 of this title, affect State and local authority under sections 1317(b)(4) and 1370 of this title, relieve such treatment works of its obligations to meet requirements established under this chapter, or otherwise preclude such works from pursuing whatever feasible options are available to meet its responsibility to comply with its permit under this section.
(n) Partial permit program
§ 1342(s)–(u)
(n)(1)–(s)(6) unchanged ·
(A) In general Nothing in section 1311(b)(1)(C) of this title precludes a State from authorizing in the water quality standards of the State the issuance of a schedule of compliance to meet water quality-based effluent limitations in permits that incorporate provisions of an integrated plan.
(B) Transition rule In any case in which a discharge is subject to a judicial order or consent decree, as of January 14, 2019, resolving an enforcement action under this chapter, any schedule of compliance issued pursuant to an authorization in a State water quality standard may not revise a schedule of compliance in that order or decree to be less stringent, unless the order or decree is modified by agreement of the parties and the court.
(t) [inserted: Expression of water quality-Based effluent limitations.—] [inserted: If the Administrator (or a State, in the case of a permit program approved by the Administrator) determines that a water quality-based limitation on a discharge of a pollutant is necessary to include in a permit under this section in addition to any appropriate technology-based effluent limitations included in such permit, the Administrator (or the State) may include such water quality-based limitation in such permit only in the form of a limitation that—]
(1) [inserted: specifies the pollutant to which it applies; and]
(2) [inserted: clearly describes the manner in which compliance with the limitation may be achieved, which shall include—]
(A) [inserted: a numerical limit on the discharge of such pollutant;]
(B) [inserted: a narrative description of required actions to be applied to the discharge (including any measures or practices required to be applied); or]
(C) [inserted: a narrative description of a limitation on the discharge that specifies the level of control to be applied.]
(u) [inserted: Discharges of pesticides.—]
(1) [inserted: No permit requirement.—] [inserted: Except as provided in paragraph (2), a permit shall not be required by the Administrator or a State under this Act for a discharge from a point source into navigable waters of a pesticide authorized for sale, distribution, or use under the Federal Insecticide, Fungicide, and Rodenticide Act, or the residue of such a pesticide, resulting from the application of such pesticide.]
(2) [inserted: Exceptions.—] [inserted: Paragraph (1) shall not apply to the following discharges of a pesticide or pesticide residue:]
(A) [inserted: A discharge resulting from the application of a pesticide in violation of a provision of the Federal Insecticide, Fungicide, and Rodenticide Act that is relevant to protecting water quality, if—]
(i) [inserted: the discharge would not have occurred but for the violation; or]
(ii) [inserted: the amount of pesticide or pesticide residue in the discharge is greater than would have occurred without the violation.]
(B) [inserted: Stormwater discharges subject to regulation under subsection (p).]
(C) [inserted: The following discharges subject to regulation under this section:]
(i) [inserted: Manufacturing or industrial effluent.]
(ii) [inserted: Treatment works effluent.]
(iii) [inserted: Discharges incidental to the normal operation of a vessel, including a discharge resulting from ballasting operations or vessel biofouling prevention.]