Skip to content
The People's CodeSearch
Menu

Changes to the Code

H.R. 3905 · Judicial Review Timeline Clarity Act ·

In committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

33 U.S.C. § 1344 Permits for dredged or fill material

+29 −22 of 3 shown
More for 33 U.S.C. § 1344
Read § 1344Only this section
3 changes the bill asks for here, 2 carried out
  1. Carried out:

    by redesignating subsection (t) as subsection (u);

  2. Not carried out:

    in subsection (u), as so redesignated, by striking Nothing in the section and inserting Savings provision.—Nothing in this section; and

    “Nothing in the section” isn't in § 1344(u) in the Code as we have it. The law may have changed since the bill was drafted.

    Technical detail“Nothing in the section” not found in /us/usc/t33/s1344/u
  3. Carried out:

    by inserting after subsection (s) the following:(t) Judicial review.— (1) Statute of limitations.— Notwithstanding any applicable provision of law relating to statutes of limitations— (A) an action seeking judicial review of an individual permit or general permit issued under this section shall be filed not later than the …

§ 1344(s)–(u)

Start of § 1344 to (s)(2) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(s)(3)(3) (3)
The Secretary is authorized to commence a civil action for appropriate relief, including a permanent or temporary injunction for any violation for which he is authorized to issue a compliance order under paragraph (1) of this subsection. Any action under this paragraph may be brought in the district court of the United States for the district in which the defendant is located or resides or is doing business, and such court shall have jurisdiction to restrain such violation and to require compliance. Notice of the commencement of such acton1 shall be given immediately to the appropriate State.The Secretary is authorized to commence a civil action for appropriate relief, including a permanent or temporary injunction for any violation for which he is authorized to issue a compliance order under paragraph (1) of this subsection. Any action under this paragraph may be brought in the district court of the United States for the district in which the defendant is located or resides or is doing business, and such court shall have jurisdiction to restrain such violation and to require compliance. Notice of the commencement of such acton1 shall be given immediately to the appropriate State.
(s)(4)(4) (4)
Any person who violates any condition or limitation in a permit issued by the Secretary under this section, and any person who violates any order issued by the Secretary under paragraph (1) of this subsection, shall be subject to a civil penalty not to exceed $25,000 per day for each violation. In determining the amount of a civil penalty the court shall consider the seriousness of the violation or violations, the economic benefit (if any) resulting from the violation, any history of such violations, any good-faith efforts to comply with the applicable requirements, the economic impact of the penalty on the violator, and such other matters as justice may require.Any person who violates any condition or limitation in a permit issued by the Secretary under this section, and any person who violates any order issued by the Secretary under paragraph (1) of this subsection, shall be subject to a civil penalty not to exceed $25,000 per day for each violation. In determining the amount of a civil penalty the court shall consider the seriousness of the violation or violations, the economic benefit (if any) resulting from the violation, any history of such violations, any good-faith efforts to comply with the applicable requirements, the economic impact of the penalty on the violator, and such other matters as justice may require.
(t)(t) [inserted: Judicial review.—]
(t)(1)(1) [inserted: Statute of limitations.—]
[inserted: Notwithstanding any applicable provision of law relating to statutes of limitations—]
(t)(1)(A)(A) [inserted: ]
[inserted: an action seeking judicial review of an individual permit or general permit issued under this section shall be filed not later than the date that is 60 days after the date on which the permit was issued; and]
(t)(1)(B)(B) [inserted: ]
[inserted: an action seeking judicial review of a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section shall be filed not later than the date that is 60 days after the date on which such verification was issued.]
(t)(2)(2) [inserted: Limitation on commencement of certain actions.—]
[inserted: Notwithstanding any other provision of law, no action described in paragraph (1) may be commenced unless the action—]
(t)(2)(A)(A) [inserted: ]
[inserted: is filed by a party that submitted a comment—]
(t)(2)(A)(i)(i) [inserted: ]
[inserted: during the public comment period for the administrative proceedings related to the applicable action described in such paragraph; and]
(t)(2)(A)(ii)(ii) [inserted: ]
[inserted: which was sufficiently detailed to put the Secretary or the State, as applicable, on notice of the issue upon which the party seeks judicial review; and]
(t)(2)(B)(B) [inserted: ]
[inserted: is related to such comment.]
(t)(3)(3) [inserted: Remedy.—]
[inserted: If a court determines that the Secretary or the State, as applicable, did not comply with the requirements of this section in issuing an individual or general permit under this section, or in verifying that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, as applicable—]
(t)(3)(A)(A) [inserted: ]
[inserted: the court shall remand the matter to the Secretary or the State, as applicable, for further proceedings consistent with the determination of the court;]
(t)(3)(B)(B) [inserted: ]
[inserted: with respect to a determination regarding the issuance of an individual or general permit under this section, the court may not vacate, revoke, enjoin, or otherwise limit the permit, unless the court finds that activities authorized under the permit would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law; and]
(t)(3)(C)(C) [inserted: ]
[inserted: with respect to a determination regarding a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, the court may not enjoin or otherwise limit the discharge unless the court finds that the activity would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law.]
(t)(4)(4) [inserted: Timeline to act on court order.—]
[inserted: If a court remands a matter under paragraph (2), the court shall set and enforce a reasonable schedule and deadline, which may not exceed 180 days from the date on which the court remands such matter, except as otherwise required by law, for the Secretary or the State, as applicable, to take such actions as the court may order.]
(u)[struck: (t)] Navigable waters within State jurisdiction[inserted: (u)] Navigable waters within State jurisdiction
Nothing in this section shall preclude or deny the right of any State or interstate agency to control the discharge of dredged or fill material in any portion of the navigable waters within the jurisdiction of such State, including any activity of any Federal agency, and each such agency shall comply with such State or interstate requirements both substantive and procedural to control the discharge of dredged or fill material to the same extent that any person is subject to such requirements. This section shall not be construed as affecting or impairing the authority of the Secretary to maintain navigation.Nothing in this section shall preclude or deny the right of any State or interstate agency to control the discharge of dredged or fill material in any portion of the navigable waters within the jurisdiction of such State, including any activity of any Federal agency, and each such agency shall comply with such State or interstate requirements both substantive and procedural to control the discharge of dredged or fill material to the same extent that any person is subject to such requirements. This section shall not be construed as affecting or impairing the authority of the Secretary to maintain navigation.

Step through the changes