Changes to 41 U.S.C. § 109
H.R. 4123 · Federal Improvement in Technology Procurement Act · Referred The text sent to a committee of the other chamber after one chamber passed it.
FIT Procurement Act
Passed the House · step 3 of 5
41 U.S.C. § 109 Major system
+2 −2Shown
3 changes the bill asks for here, 3 carried out
- Carried out:
by striking
$75,000,000 (based on fiscal year 1980 constant dollars)
and inserting$275,000,000 (based on fiscal year 2024 dollars)
; and - Carried out:
by striking
$300,000,000 (based on fiscal year 1980 constant dollars)
and inserting$1,300,000,000 (based on fiscal year 2024 dollars)
; and - Carried out:
in subsection (b)(2), by striking
$750,000 (based on fiscal year 1980 constant dollars)
and inserting$2,000,000 (based on fiscal year 2024 dollars)
.
§ 109(a)–(b)
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| § 109. Major system | § 109. Major system | |||
| (a) | (a) In General.— | (a) In General.— | ||
| In this subtitle, the term “major system” means a combination of elements that will function together to produce the capabilities required to fulfill a mission need. These elements may include hardware, equipment, software, or a combination of hardware, equipment, and software, but do not include construction or other improvements to real property. | In this subtitle, the term “major system” means a combination of elements that will function together to produce the capabilities required to fulfill a mission need. These elements may include hardware, equipment, software, or a combination of hardware, equipment, and software, but do not include construction or other improvements to real property. | |||
| (b) | (b) System Deemed To Be Major System.— | (b) System Deemed To Be Major System.— | ||
| A system is deemed to be a major system if— | A system is deemed to be a major system if— | |||
| (b)(1) | (1) | (1) | ||
| the Department of Defense is responsible for the system and the total expenditures for research, development, testing, and evaluation for the system are estimated to exceed $ | the Department of Defense is responsible for the system and the total expenditures for research, development, testing, and evaluation for the system are estimated to exceed $[inserted: 275],000,000 (based on fiscal year [inserted: 2024] dollars) or the eventual total expenditure for procurement exceeds $[inserted: 1,]300,000,000 (based on fiscal year [inserted: 2024] dollars); | |||
| (b)(2) | (2) | (2) | ||
| a civilian agency is responsible for the system and total expenditures for the system are estimated to exceed the greater of $ | a civilian agency is responsible for the system and total expenditures for the system are estimated to exceed the greater of $[inserted: 2],000[inserted: ,000] (based on fiscal year [inserted: 2024] dollars) or the dollar threshold for a major system established by the agency pursuant to Office of Management and Budget (OMB) Circular A–109, entitled “Major Systems Acquisitions”; or | |||
| (b)(3) | (3) | (3) | ||
| the head of the agency responsible for the system designates the system a major system. | the head of the agency responsible for the system designates the system a major system. |