- Introduced
- In committeeNatural Resources
- Passed the House (not yet)
- Passed the Senate (not yet)
- Law (not yet)
What it says
About this text
Text: Introduced The text as a member of Congress first filed it. Most bills never get further than this., (the only version so far)
This bill creates or directs, rather than amending the Code.
Its own words follow, as Congress.gov publishes them.
Sec. 1. Coordination with Federal Permitting Improvement Steering Council With respect to any covered project (as defined under section 41001 of the FAST Act (42 U.S.C. 4370m)) for which a certification or permit from a State under section 401, 402, or 404 of the Federal Water Pollution Control Act is required, the State is encouraged to choose to participate, to the maximum extent practicable, in the environmental review and authorization process under section 41003(c) of the FAST Act (42 U.S.C. 4370m–2(c)), pursuant to paragraph (3)(A) of such section.