10 U.S.C. § 4376 Breach of critical cost growth threshold: reassessment of program; presumption of program termination

+32 −4Shown
More for 10 U.S.C. § 4376
Read § 4376
7 changes the bill asks for here, 7 carried out
  1. Carried out:

    in paragraph (1), by inserting (other than a program described in paragraph (4)(A)) after major defense acquisition program;

  2. Carried out:

    by striking A written and inserting (A) A written; and

  3. Carried out:

    by adding at the end the following new subparagraph:(B) The Secretary shall make publicly available on a website of the Department of Defense each report required under subparagraph (A).; and

  4. Carried out:

    by adding at the end the following new paragraphs:(4) Second critical breach.— (A) The Secretary may not submit to Congress a written certification under paragraph (1) with respect to a major defense acquisition program that has had more than one program acquisition unit cost increase or procurement unit cost increase resulting …

  5. Carried out:

    in paragraph (2), by striking and at the end;

  6. Carried out:

    in paragraph (3), by striking the period at the end and inserting ; and; and

  7. Carried out:

    by adding at the end the following new paragraph:(4) consideration of termination plans that maximize value, including— (A) immediate termination of the program with no further action; (B) termination of the program after completion of the end items in production and for which funds have been obligated or expended under the …

§ 4376(a)–(b)

Start of § 4376 to (a)(2)(C) unchanged ·

(D) the need to reduce funding for other programs due to the growth in cost of the program.

(b) Presumption of Termination.—

(1) Termination unless secretary submits certification and report.— After conducting the reassessment required by subsection (a) with respect to a major defense acquisition program[inserted: (other than a program described in paragraph (4)(A))], the Secretary shall terminate the program unless the Secretary submits to Congress, before the end of the 60-day period beginning on the day the Selected Acquisition Report containing the information described in section 4375(d) and (e) of this title is required to be submitted under section 4351(f) of this title, a written certification in accordance with paragraph (2).

(2) Certification.— A certification described by this paragraph with respect to a major defense acquisition program is a written certification that—

(A) the continuation of the program is essential to the national security;

§ 4376(b)–(c)

(b)(2)(B)–(D) unchanged ·

(E) the management structure for the program is adequate to manage and control program acquisition unit cost or procurement unit cost.

(3) Report.—

(A) [inserted: A written certification under paragraph (2) shall be accompanied by a report presenting the root cause analysis and assessment carried out pursuant to subsection (a) and the basis for each determination made in accordance with subparagraphs (A) through (E) of paragraph (2), together with supporting documentation.]

(B) [inserted: The Secretary shall make publicly available on a website of the Department of Defense each report required under subparagraph (A).]

(4) [inserted: Second critical breach.—]

(A) [inserted: The Secretary may not submit to Congress a written certification under paragraph (1) with respect to a major defense acquisition program that has had more than one program acquisition unit cost increase or procurement unit cost increase resulting in a reassessment under subsection (a).]

(B) [inserted: The Secretary shall terminate a major defense acquisition program described in subparagraph (A) not later than 90 days after conducting the reassessment required by subsection (a) with respect the program.]

(5) [inserted: Delegation.—] [inserted: The Secretary may not delegate the submission of a written certification under paragraph (1).]

[struck: A written certification under paragraph (2) shall be accompanied by a report presenting the root cause analysis and assessment carried out pursuant to subsection (a) and the basis for each determination made in accordance with subparagraphs (A) through (E) of paragraph (2), together with supporting documentation.]

(c) Actions if Program Terminated.— If a major defense acquisition program is terminated pursuant to subsection (b), the Secretary shall submit to Congress a written report setting forth—

(1) an explanation of the reasons for terminating the program;

(2) the alternatives considered to address any problems in the program;[struck: and]

(3) the course the Department plans to pursue to meet any continuing military requirements otherwise intended to be met by the program[struck: .][inserted: ; and]

(4) [inserted: consideration of termination plans that maximize value, including—]

(A) [inserted: immediate termination of the program with no further action;]

(B) [inserted: termination of the program after completion of the end items in production and for which funds have been obligated or expended under the program as of the date that—]

(i) [inserted: if the program was terminated under subsection (b)(1), is the last day of the applicable 60-day period described in such subsection for the program; or]

(ii) [inserted: if the program was terminated under subsection (b)(4), is 90 days after the date on which the Secretary completed the reassessment required by subsection (a) pursuant to which the program was so terminated;]

(C) [inserted: termination of the program after completion of the end items described in subparagraph (B) for which the resale value exceeds the cost of completing such end items; and]

(D) [inserted: any other course of action to maximize the value to the Government of the funds that have been obligated or expended under the program as of the date that—]

(i) [inserted: if the program was terminated under subsection (b)(1), is the last day of the applicable 60-day period described in such subsection for the program; or]

(ii) [inserted: if the program was terminated under subsection (b)(4), is 90 days after the date on which the Secretary completed the reassessment required by subsection (a) pursuant to which the program was so terminated.]