Title 43 · Public LandsParks and public lands
Changes to 43 U.S.C. § 1772
H.R. 471 · Fix Our Forests Act · Engrossed The official text as one chamber (House or Senate) passed it.
Passed the House · step 3 of 5
43 U.S.C. § 1772 Vegetation managment, facility inspection, and operation and maintenance relating to electric transmission and distribution facility rights of way
5 changes the bill asks for here, 5 carried out
- Carried out:
Section 512(a)(1)(B)(ii) of the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1772(a)(1)(B)(ii)) is amended by striking
10
and inserting150
. - Carried out:
in clause (i), by striking
and
at the end; - Carried out:
in clause (ii), by striking the period and inserting
; and
; and - Carried out:
by adding at the end the following:
(iii) consulting with a private landowner with respect to any hazard trees identified for removal from land owned by the private landowner..
- Carried out:
Section 512(c)(4)(A)(iv) of such Act (43 U.S.C. 1772(c)(4)(A)(iv)) is amended to read as follows:
(iv) ensures that— (I) a plan submitted without a modification under clause (iii) shall be automatically approved 120 days after being submitted; and (II) with respect to a plan submitted with a modification under clause (iii), if not approved within 120 days after being …
§ 1772(a)Definitions(1)–(3)
Start of § 1772 to (a)(1)(B) unchanged ·
(i) cause substantial damage or disruption to a transmission or distribution facility; or
(ii) come within [struck: 10][inserted: 150] feet of an electric power line.
(2) Owner; operator The terms “owner” and “operator” include contractors or other agents engaged by the owner or operator of an electric transmission or distribution facility.
(3) Plan The term “plan” means a vegetation management, facility inspection, and operation and maintenance plan that—
§ 1772(c)Vegetation management, facility inspection, and operation and maintenance plans(3)–(4)
(a)(3)(A)–(c)(3)(D) unchanged ·
(E) describe processes for—
(i) identifying changes in conditions;[struck: and]
(ii) modifying the approved plan, if necessary[struck: .][inserted: ; and]
(iii) [inserted: consulting with a private landowner with respect to any hazard trees identified for removal from land owned by the private landowner.]
(4) Review and approval process
(A) In general The Secretary concerned shall jointly develop a consolidated and coordinated process for the review and approval of plans submitted under paragraph (1) that—
§ 1772(c)(4)Review and approval process(A)–(B)
(c)(4)(A)(i)–(ii) unchanged ·
(iii) includes a process for modifications to a plan in a prompt manner if changed conditions necessitate a modification to a plan; and
(iv) [inserted: ensures that—]
(I) [inserted: a plan submitted without a modification under clause (iii) shall be automatically approved 120 days after being submitted; and]
(II) [inserted: with respect to a plan submitted with a modification under clause (iii), if not approved within 120 days after being submitted, the Secretary concerned shall develop and submit a letter to the owner and operator describing—]
(aa) [inserted: a detailed timeline (to conclude within 165 days after the submission of the plan) for completing review of the plan;]
(bb) [inserted: any identified deficiencies with the plan and specific opportunities for the owner and operator to address such deficiencies; and]
(cc) [inserted: any other relevant information, as determined by the Secretary concerned.]
[struck: ensures, to the maximum extent practicable, a prompt review and approval process not to exceed 120 days.]
(B) Plan modification Upon reasonable advance notice to an owner or operator of an electric transmission or distribution facility of any changed conditions that warrant a modification to a plan, the Secretary concerned shall—
(i) provide an opportunity for the owner or operator to submit a proposed plan modification, consistent with the process described under subparagraph (A)(iii), to address the changed condition identified by the Secretary concerned;
Rest of § 1772 unchanged ·