Skip to content
The People's CodeSearch
Menu

Title 49 · TransportationTransportation

Changes to 49 U.S.C. § 60143

H.R. 5301 · PIPES Act of 2025 ·

Reported by committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

49 U.S.C. § 60143 Idled pipelines

+6 −4Shown
More for 49 U.S.C. § 60143
Read § 60143
4 changes the bill asks for here, 4 carried out
  1. Carried out:

    by striking paragraph (1) and inserting the following:(1) In general.— Not later than 180 days after the date of enactment of the PIPES Act of 2025, the Secretary shall issue a notice of proposed rulemaking prescribing the applicability of the pipeline safety requirements to idled natural gas or other gas transmission and hazardous liquid pipelines.; and

  2. Carried out:

    in paragraph (2), by adding at the end the following:(E) Consideration.— In promulgating regulations under this section, the Secretary shall consider the adoption of industry consensus standards..

  3. Carried out:

    in subsection (a)(2) by inserting carbon dioxide, after hazardous liquid,; and

  4. Carried out:

    in subsection (b) by striking gas transmission and hazardous liquid pipelines and inserting gas transmission, hazardous liquid, and carbon dioxide pipelines each place it appears.

§ 60143(a)–(b)

Start of § 60143 to (a)(1)(A) unchanged ·

(B) will not resume service for a period of not less than 180 days;

(2) has been isolated from all sources of hazardous liquid, [inserted: carbon dioxide, ]natural gas, or other gas; and

(3)

(A) has been purged of combustibles and hazardous materials and maintains a blanket of inert, nonflammable gas at low pressure; or

(B) has not been purged as described in subparagraph (A), but the volume of gas is so small that there is no potential hazard, as determined by the Secretary pursuant to a rule.

(b) Rulemaking.—

(1) In general.— Not later than [struck: 2][inserted: 180] [struck: years][inserted: days] after the date of enactment of the PIPES Act of [struck: 2020][inserted: 2025], the Secretary shall [struck: promulgate][inserted: issue] [struck: regulations][inserted: a] [inserted: notice of proposed rulemaking ]prescribing the applicability of the pipeline safety requirements to idled natural [inserted: gas ]or other gas transmission[inserted: ,] [struck: and ]hazardous liquid[inserted: ,] [inserted: and carbon dioxide ]pipelines.

(2) Requirements.—

(A) In general.— The applicability of the regulations under paragraph (1) shall be based on the risk that idled natural or other gas transmission[inserted: ,] [struck: and ]hazardous liquid[inserted: ,] [inserted: and carbon dioxide ]pipelines pose to the public, property, and the environment, and shall include requirements to resume operation.

(B) Inspection.— The Secretary or an appropriate State agency shall inspect each idled pipeline and verify that the pipeline has been purged of combustibles and hazardous materials, if required under subsection (a).

(C) Requirements for reinspection.— The Secretary shall determine the requirements for periodic reinspection of idled natural or other gas transmission[inserted: ,] [struck: and ]hazardous liquid[inserted: ,] [inserted: and carbon dioxide ]pipelines.

(D) Resumption of operations.— As a condition to allowing an idled pipeline to resume operations, the Secretary shall require that, prior to resuming operations, the pipeline shall be—

(i) inspected with—

§ 60143(b)(2)Requirements.—(D)–(E)

(b)(2)(D)(i)(I)–(II) unchanged ·

(III) if the use of hydrostatic pressure testing or an internal inspection device is not technologically feasible, another comparable technology or practice; and

(ii) in compliance with regulations promulgated under this chapter, including any regulations that became effective while the pipeline was idled.

(E) [inserted: Consideration.—] [inserted: In promulgating regulations under this section, the Secretary shall consider the adoption of industry consensus standards.]

Step through the changes