H.R. 5414 · Dam Assessment and Mitigation Support Act ·

DAMS Act

In committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

33 U.S.C. § 467f National dam safety program

+0 −2Shown
More for 33 U.S.C. § 467f
Read § 467fOnly this section
1 change the bill asks for here, 1 carried out
  1. Carried out:

    Section 8(e) of the National Dam Safety Program Act (33 U.S.C. 467f(e)) is amended by striking paragraph (4).

§ 467f(e)Assistance for State dam safety programs(2)–(5)

Start of § 467f to (e)(2)(A)(xi)(III) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(2)(B)(B) Budgeting requirement(B) Budgeting requirement
For a State to be eligible for assistance under this subsection, State appropriations must be budgeted to carry out the legislation of the State under subparagraph (A).For a State to be eligible for assistance under this subsection, State appropriations must be budgeted to carry out the legislation of the State under subparagraph (A).
(3)(3) Work plans(3) Work plans
The Administrator shall enter into a2 agreement with each State receiving assistance under paragraph (2) to develop a work plan necessary for the State dam safety program to reach a level of program performance specified in the agreement.The Administrator shall enter into a2 agreement with each State receiving assistance under paragraph (2) to develop a work plan necessary for the State dam safety program to reach a level of program performance specified in the agreement.
(4)(4) [struck: Maintenance of effort]
[struck: Assistance may not be provided to a State under this subsection for a fiscal year unless the State enters into such agreement with the Administrator as the Administrator requires to ensure that the State will maintain the aggregate expenditures of the State from all other sources for programs to ensure dam safety for the protection of human life and property at or above a level equal to the average annual level of such expenditures for the 2 fiscal years preceding the fiscal year.]
(5)(5) Approval of programs(5) Approval of programs
(5)(A)(A) Submission(A) Submission
For a State to be eligible for assistance under this subsection, a plan for a State dam safety program shall be submitted to the Administrator for approval.For a State to be eligible for assistance under this subsection, a plan for a State dam safety program shall be submitted to the Administrator for approval.

Rest of § 467f unchanged

33 U.S.C. § 467f–2 Rehabilitation of high hazard potential dams

+2 −2Shown
More for 33 U.S.C. § 467f–2
Read § 467f–2Only this section
2 changes the bill asks for here, 2 carried out
  1. Carried out:

    Section 8A(f) of the National Dam Safety Program Act (33 U.S.C. 467f–2(f)) is amended by inserting , which system shall be used by any State that is not using a risk-based priority system developed by the State for identifying such dams before the period at the end.

  2. Carried out:

    Section 8A(j)(4) of the National Dam Safety Program Act (33 U.S.C. 467f–2(j)(4)) is amended by striking 2026 and inserting 2031.

§ 467f–2(e)–(g)

Start of § 467f–2 to (e)(3)(C) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(e)(4)(4) Plan criteria and technical support(4) Plan criteria and technical support
The Administrator, in consultation with the Board, shall provide criteria, and may provide technical support, for the development and implementation of floodplain management plans prepared under this subsection.The Administrator, in consultation with the Board, shall provide criteria, and may provide technical support, for the development and implementation of floodplain management plans prepared under this subsection.
(f)(f) Priority system(f) Priority system
The Administrator, in consultation with the Board, shall develop a risk-based priority system for use in identifying eligible high hazard potential dams for which grants may be made under this section.The Administrator, in consultation with the Board, shall develop a risk-based priority system for use in identifying eligible high hazard potential dams for which grants may be made under this section[inserted: , which system shall be used by any State that is not using a risk-based priority system developed by the State for identifying such dams].
(g)(g) Funding(g) Funding
(g)(1)(1) Cost sharing(1) Cost sharing
(g)(1)(A)(A) In general(A) In general
Except as provided in subparagraph (C), any assistance provided under this section for a project shall be subject to a non-Federal cost-sharing requirement of not less than 35 percent.Except as provided in subparagraph (C), any assistance provided under this section for a project shall be subject to a non-Federal cost-sharing requirement of not less than 35 percent.

§ 467f–2(j)Authorization of appropriations(3)–(4)

(g)(1)(B)–(j)(2) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(3)(3) (3)
$40,000,000 for fiscal year 2020; and$40,000,000 for fiscal year 2020; and
(4)(4) (4)
$60,000,000 for each of fiscal years 2021 through [struck: 2026].$60,000,000 for each of fiscal years 2021 through [inserted: 2031].