Title 49 · TransportationTransportation
Changes to 49 U.S.C. § 60132
H.R. 5537 · Pipeline Accountability Act of 2025 · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
In committee · step 2 of 5
49 U.S.C. § 60132 National pipeline mapping system
15 changes the bill asks for here, 12 carried out
- Carried out:
in subsection (b), by striking
subsection (a)
and insertingsubparagraph (A)
; - Carried out:
by redesignating subsection (b) as subparagraph (C) and indenting appropriately;
- Not carried out:
in paragraph (4), in the second sentence, by striking The Secretary and inserting the following:(B) Notice requirement.— With respect to data requested from operators under subparagraph (A)(vi), the Secretary;
The bill puts these words in a provision numbered (B), which can't be the first one in § 60132(a)(4), so we couldn't tell where it goes.
Technical detail
(B) can't be the first provision of /us/usc/t49/s60132/a/4 - Carried out:
by redesignating paragraphs (1) through (4) as clauses (i), (ii), (v), and (vi), respectively, and indenting appropriately;
- Carried out:
by inserting after clause (ii) (as so redesignated) the following:
(iii) Information on the matters described in paragraph (2)(E). (iv) The location and type of any valves installed on the pipeline.; and
- Carried out:
by striking
and gathering lines
; - Carried out:
by striking
of Transportation
; and - Not carried out:
by striking the subsection designation and heading and all that follows through this section, the and inserting the following:
(a) Definitions.— In this section: (1) Class location.— The term “class location” means a class location described in section 192.5 of title 49, Code of Federal Regulations (or a successor regulation). (2) Covered facility.— The term “covered facility” means— (A) a covered …
We can't read how this instruction is worded yet, so it isn't shown in the text.
Technical detail
no-pattern: striking the subsection designation and heading and all that follows through QTEXT and inserting the following: QCONTENT; - Not carried out:
in subsection (b) (as so designated), by adding at the end the following:
(2) Information to be provided to the public.— (A) In general.— Not later than 1 year after the date of enactment of the Pipeline Accountability Act of 2025, each operator of a covered facility shall provide to the public, free of charge, on a publicly accessible website, in a …
The bill points to subsection (b) of § 60132, which isn't there in the Code as we have it. It may have been renumbered or removed since the bill was drafted.
Technical detail
target not found: no subsection (b) in /us/usc/t49/s60132 - Carried out:
in the subsection heading, by striking
high-consequence
and insertinghigh consequence
; - Carried out:
by striking
high-consequence areas (as described in section 60109(a))
and insertinghigh consequence areas
; and - Carried out:
by striking
and
at the end; - Carried out:
in paragraph (2), by striking the period at the end and inserting
; and
; and - Carried out:
by adding at the end the following:
(3) make the map available to the public on an internet website, in a machine-readable format, as part of the National Pipeline Mapping System Public Map Viewer or at an alternative location.; and
- Carried out:
in subsection (f), by striking
subsection (a)
and insertingsubsection (b)(1)
.
§ 60132(a)–(f)
§ 60132. National pipeline mapping system
(a) Information To Be Provided.— Not later than 6 months after the date of enactment of this section, the operator of a pipeline facility (except distribution lines[struck: and gathering lines]) shall provide to the Secretary [struck: of Transportation ]the following information with respect to the facility:
[struck: (1)] [inserted: (i)] Geospatial data appropriate for use in the National Pipeline Mapping System or data in a format that can be readily converted to geospatial data.
[struck: (2)] [inserted: (ii)] The name and address of the person with primary operational control to be identified as its operator for purposes of this chapter.
(iii) [inserted: Information on the matters described in paragraph (2)(E).]
(iv) [inserted: The location and type of any valves installed on the pipeline.]
[struck: (3)] [inserted: (v)] A means for a member of the public to contact the operator for additional information about the pipeline facilities it operates.
[struck: (4)] [inserted: (vi)] Any other geospatial or technical data, including design and material specifications, that the Secretary determines are necessary to carry out the purposes of this section. The Secretary shall give reasonable notice to operators that the data are being requested.
[struck: (b)] [inserted: (C)] Updates.— A person providing information under [struck: subsection][inserted: subparagraph] ([struck: a][inserted: A]) shall provide to the Secretary updates of the information to reflect changes in the pipeline facility owned or operated by the person and as otherwise required by the Secretary.
(c) Technical Assistance To Improve Local Response Capabilities.— The Secretary may provide technical assistance to State and local officials to improve local response capabilities for pipeline emergencies by adapting information available through the National Pipeline Mapping System to software used by emergency response personnel responding to pipeline emergencies.
(d) Map of [struck: High-][inserted: high ]consequence Areas.— The Secretary shall—
(1) maintain, as part of the National Pipeline Mapping System, a map of designated high[struck: -][inserted: ]consequence areas [struck: (as described ]in [struck: section 60109(a)) in ]which pipelines are required to meet integrity management program regulations, excluding any proprietary or sensitive security information;[struck: and]
(2) update the map biennially[struck: .][inserted: ; and]
(3) [inserted: make the map available to the public on an internet website, in a machine-readable format, as part of the National Pipeline Mapping System Public Map Viewer or at an alternative location.]
(e) Program To Promote Awareness of National Pipeline Mapping System.— Not later than 1 year after the date of enactment of this subsection, the Secretary shall develop and implement a program promoting greater awareness of the existence of the National Pipeline Mapping System to State and local emergency responders and other interested parties. The program shall include guidance on how to use the National Pipeline Mapping System to locate pipelines in communities and local jurisdictions.
(f) Public Disclosure Limited.— The Secretary may not disclose information collected pursuant to subsection ([struck: a][inserted: b])[inserted: (1)] except to the extent permitted by section 552 of title 5.