Changes to the Code
H.R. 6503 · Broadband for Americans through Responsible Streamlining (BARS) Act · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
In committee · step 2 of 5
47 U.S.C. § 1455 Wireless facilities deployment
+11 −2Shown
1 change the bill asks for here, 1 carried out
- Carried out:
Section 6409(a)(3) of the Middle Class Tax Relief and Job Creation Act of 2012 (47 U.S.C. 1455(a)(3)) is amended to read as follows:
(3) Application of NEPA; NHPA.— (A) NEPA exemption.— A Federal authorization with respect to an eligible facilities request or an eligible wireline communications facilities request may not be considered a major Federal action under section 102(2)(C) of the National …
§ 1455(a)–(b)
Start of § 1455 to (a)(2)(A) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (a)(2)(B) | (B) | (B) | ||
| removal of transmission equipment; or | removal of transmission equipment; or | |||
| (a)(2)(C) | (C) | (C) | ||
| replacement of transmission equipment. | replacement of transmission equipment. | |||
| (a)(3) | (3) | (3) [inserted: Application] of [inserted: NEPA;] [inserted: NHPA.—] | ||
| (a)(3)(A) | (A) [inserted: NEPA exemption.—] | |||
| [inserted: A Federal authorization with respect to an eligible facilities request or an eligible wireline communications facilities request may not be considered a major Federal action under section 102(2)(C) of the National Environmental Policy Act of 1969 (42 U.S.C. 4332(2)(C)).] | ||||
| (a)(3)(B) | (B) [inserted: National Historic Preservation Act exemption.—] | |||
| [inserted: An eligible facilities request or an eligible wireline communications facilities request may not be considered an undertaking under section 300320 of title 54, United States Code.] | ||||
| (a)(3)(C) | (C) [inserted: Federal authorization defined.—] | |||
| [inserted: In this paragraph, the term “Federal authorization”—] | ||||
| (a)(3)(C)(i) | (i) [inserted: ] | |||
| [inserted: means any authorization required under Federal law with respect to an eligible facilities request or an eligible wireline communications facilities request; and] | ||||
| (a)(3)(C)(ii) | (ii) [inserted: ] | |||
| [inserted: includes any permits, special use authorizations, certifications, opinions, or other approvals as may be required under Federal law with respect to an eligible facilities request or an eligible wireline communications facilities request.] | ||||
| (a)(3) | ||||
| (b) | (b) Federal easements, rights-of-way, and leases | (b) Federal easements, rights-of-way, and leases | ||
| (b)(1) | (1) Grant | (1) Grant | ||
| If an executive agency, a State, a political subdivision or agency of a State, or a person, firm, or organization applies for the grant of an easement, right-of-way, or lease to, in, over, or on a building or other property owned by the Federal Government for the right to install, construct, modify, or maintain a communications facility installation, the executive agency having control of the building or other property may grant to the applicant, on behalf of the Federal Government, subject to paragraph (3), an easement, right-of-way, or lease to perform such installation, construction, modification, or maintenance. | If an executive agency, a State, a political subdivision or agency of a State, or a person, firm, or organization applies for the grant of an easement, right-of-way, or lease to, in, over, or on a building or other property owned by the Federal Government for the right to install, construct, modify, or maintain a communications facility installation, the executive agency having control of the building or other property may grant to the applicant, on behalf of the Federal Government, subject to paragraph (3), an easement, right-of-way, or lease to perform such installation, construction, modification, or maintenance. | |||
Rest of § 1455 unchanged