16 U.S.C. § 824 Declaration of policy; application of subchapter
3 changes the bill asks for here, 1 carried out
- Not carried out:
striking
210, 211, 211A, 212
the second place it appears; and“210, 211, 211A, 212” isn't in § 824(b)(2) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“210, 211, 211A, 212” not found in /us/usc/t16/s824/b/2 - Carried out:
striking
an electric utility or other entity
and insertingany entity that is otherwise exempt under section 201(f)
. - Not carried out:
Section 201(e) of the Federal Power Act (16 U.S.C. 824(e)) is amended by striking
210, 211, 211A, 212,
.“210, 211, 211A, 212,” isn't in § 824(e) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“210, 211, 211A, 212,” not found in /us/usc/t16/s824/e
§ 824(b)–(d)
Start of § 824 to (b) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (b)(1) | (1) | (1) | ||
| The provisions of this subchapter shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce, but except as provided in paragraph (2) shall not apply to any other sale of electric energy or deprive a State or State commission of its lawful authority now exercised over the exportation of hydroelectric energy which is transmitted across a State line. The Commission shall have jurisdiction over all facilities for such transmission or sale of electric energy, but shall not have jurisdiction, except as specifically provided in this subchapter and subchapter III of this chapter, over facilities used for the generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter. | The provisions of this subchapter shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce, but except as provided in paragraph (2) shall not apply to any other sale of electric energy or deprive a State or State commission of its lawful authority now exercised over the exportation of hydroelectric energy which is transmitted across a State line. The Commission shall have jurisdiction over all facilities for such transmission or sale of electric energy, but shall not have jurisdiction, except as specifically provided in this subchapter and subchapter III of this chapter, over facilities used for the generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter. | |||
| (b)(2) | (2) | (2) | ||
| Notwithstanding subsection (f), the provisions of sections 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, and 824v of this title shall apply to the entities described in such provisions, and such entities shall be subject to the jurisdiction of the Commission for purposes of carrying out such provisions and for purposes of applying the enforcement authorities of this chapter with respect to such provisions. Compliance with any order or rule of the Commission under the provisions of section 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, or 824v of this title, shall not make | Notwithstanding subsection (f), the provisions of sections 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, and 824v of this title shall apply to the entities described in such provisions, and such entities shall be subject to the jurisdiction of the Commission for purposes of carrying out such provisions and for purposes of applying the enforcement authorities of this chapter with respect to such provisions. Compliance with any order or rule of the Commission under the provisions of section 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, or 824v of this title, shall not make [inserted: any] [inserted: entity] [inserted: that] [inserted: is] [inserted: otherwise] [inserted: exempt] [inserted: under section 201(f) ]subject to the jurisdiction of the Commission for any purposes other than the purposes specified in the preceding sentence. | |||
| (c) | (c) Electric energy in interstate commerce | (c) Electric energy in interstate commerce | ||
| For the purpose of this subchapter, electric energy shall be held to be transmitted in interstate commerce if transmitted from a State and consumed at any point outside thereof; but only insofar as such transmission takes place within the United States. | For the purpose of this subchapter, electric energy shall be held to be transmitted in interstate commerce if transmitted from a State and consumed at any point outside thereof; but only insofar as such transmission takes place within the United States. | |||
| (d) | (d) “Sale of electric energy at wholesale” defined | (d) “Sale of electric energy at wholesale” defined | ||
| The term “sale of electric energy at wholesale” when used in this subchapter, means a sale of electric energy to any person for resale. | The term “sale of electric energy at wholesale” when used in this subchapter, means a sale of electric energy to any person for resale. |
Rest of § 824 unchanged
16 U.S.C. § 824k Orders requiring interconnection or wheeling
1 change the bill asks for here, 1 carried out
- Carried out:
Section 212 of the Federal Power Act (16 U.S.C. 824k) is amended by striking subsection (k).
§ 824k(i)–(k)
Start of § 824k to (i)(4) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (i)(5) | (5) | (5) | ||
| The Commission shall not issue any order under section 824i of this title, section 824j of this title, this section, or section 824l of this title requiring the Administrator of the Bonneville Power Administration to provide transmission service if such an order would impair the Administrator’s ability to provide such transmission service to the Administrator’s power and transmission customers in the Pacific Northwest, as that region is defined in section 839a(14) of this title, as is needed to assure adequate and reliable service to loads in that region. | The Commission shall not issue any order under section 824i of this title, section 824j of this title, this section, or section 824l of this title requiring the Administrator of the Bonneville Power Administration to provide transmission service if such an order would impair the Administrator’s ability to provide such transmission service to the Administrator’s power and transmission customers in the Pacific Northwest, as that region is defined in section 839a(14) of this title, as is needed to assure adequate and reliable service to loads in that region. | |||
| (j) | (j) Equitability within territory restricted electric systems | (j) Equitability within territory restricted electric systems | ||
| With respect to an electric utility which is prohibited by Federal law from being a source of power supply, either directly or through a distributor of its electric energy, outside an area set forth in such law, no order issued under section 824j of this title may require such electric utility (or a distributor of such electric utility) to provide transmission services to another entity if the electric energy to be transmitted will be consumed within the area set forth in such Federal law, unless the order is in furtherance of a sale of electric energy to that electric utility: Provided, however, That the foregoing provision shall not apply to any area served at retail by an electric transmission system which was such a distributor on October 24, 1992, and which before October 1, 1991, gave its notice of termination under its power supply contract with such electric utility. | With respect to an electric utility which is prohibited by Federal law from being a source of power supply, either directly or through a distributor of its electric energy, outside an area set forth in such law, no order issued under section 824j of this title may require such electric utility (or a distributor of such electric utility) to provide transmission services to another entity if the electric energy to be transmitted will be consumed within the area set forth in such Federal law, unless the order is in furtherance of a sale of electric energy to that electric utility: Provided, however, That the foregoing provision shall not apply to any area served at retail by an electric transmission system which was such a distributor on October 24, 1992, and which before October 1, 1991, gave its notice of termination under its power supply contract with such electric utility. | |||
| (k) | (k) | |||
| (k)(1) | (1) | |||
| (k)(2) | (2) | |||
| (k)(2)(A) | (A) | |||
| (k)(2)(B) | (B) | |||
16 U.S.C. § 824o Electric reliability
2 changes the bill asks for here, 2 carried out
- Carried out:
in subsection (a)(3), by striking
enlarge such facilities or to construct new transmission capacity or generation capacity
and insertingconstruct new generation capacity
; and - Carried out:
in subsection (i)(2), by striking
or transmission
.
§ 824o(a)Definitions(2)–(5)
Start of § 824o to (a)(1) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (2) | (2) | (2) | ||
| The terms “Electric Reliability Organization” and “ERO” mean the organization certified by the Commission under subsection (c) the purpose of which is to establish and enforce reliability standards for the bulk-power system, subject to Commission review. | The terms “Electric Reliability Organization” and “ERO” mean the organization certified by the Commission under subsection (c) the purpose of which is to establish and enforce reliability standards for the bulk-power system, subject to Commission review. | |||
| (3) | (3) | (3) | ||
| The term “reliability standard” means a requirement, approved by the Commission under this section, to provide for reliable operation of the bulk-power system. The term includes requirements for the operation of existing bulk-power system facilities, including cybersecurity protection, and the design of planned additions or modifications to such facilities to the extent necessary to provide for reliable operation of the bulk-power system, but the term does not include any requirement to | The term “reliability standard” means a requirement, approved by the Commission under this section, to provide for reliable operation of the bulk-power system. The term includes requirements for the operation of existing bulk-power system facilities, including cybersecurity protection, and the design of planned additions or modifications to such facilities to the extent necessary to provide for reliable operation of the bulk-power system, but the term does not include any requirement to construct new generation capacity. | |||
| (4) | (4) | (4) | ||
| The term “reliable operation” means operating the elements of the bulk-power system within equipment and electric system thermal, voltage, and stability limits so that instability, uncontrolled separation, or cascading failures of such system will not occur as a result of a sudden disturbance, including a cybersecurity incident, or unanticipated failure of system elements. | The term “reliable operation” means operating the elements of the bulk-power system within equipment and electric system thermal, voltage, and stability limits so that instability, uncontrolled separation, or cascading failures of such system will not occur as a result of a sudden disturbance, including a cybersecurity incident, or unanticipated failure of system elements. | |||
| (5) | (5) | (5) | ||
| The term “Interconnection” means a geographic area in which the operation of bulk-power system components is synchronized such that the failure of one or more of such components may adversely affect the ability of the operators of other components within the system to maintain reliable operation of the facilities within their control. | The term “Interconnection” means a geographic area in which the operation of bulk-power system components is synchronized such that the failure of one or more of such components may adversely affect the ability of the operators of other components within the system to maintain reliable operation of the facilities within their control. |
§ 824o(i)Savings provisions(1)–(4)
(a)(6)–(i) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (1) | (1) | (1) | ||
| The ERO shall have authority to develop and enforce compliance with reliability standards for only the bulk-power system. | The ERO shall have authority to develop and enforce compliance with reliability standards for only the bulk-power system. | |||
| (2) | (2) | (2) | ||
| This section does not authorize the ERO or the Commission to order the construction of additional generation | This section does not authorize the ERO or the Commission to order the construction of additional generation capacity or to set and enforce compliance with standards for adequacy or safety of electric facilities or services. | |||
| (3) | (3) | (3) | ||
| Nothing in this section shall be construed to preempt any authority of any State to take action to ensure the safety, adequacy, and reliability of electric service within that State, as long as such action is not inconsistent with any reliability standard, except that the State of New York may establish rules that result in greater reliability within that State, as long as such action does not result in lesser reliability outside the State than that provided by the reliability standards. | Nothing in this section shall be construed to preempt any authority of any State to take action to ensure the safety, adequacy, and reliability of electric service within that State, as long as such action is not inconsistent with any reliability standard, except that the State of New York may establish rules that result in greater reliability within that State, as long as such action does not result in lesser reliability outside the State than that provided by the reliability standards. | |||
| (4) | (4) | (4) | ||
| Within 90 days of the application of the Electric Reliability Organization or other affected party, and after notice and opportunity for comment, the Commission shall issue a final order determining whether a State action is inconsistent with a reliability standard, taking into consideration any recommendation of the ERO. | Within 90 days of the application of the Electric Reliability Organization or other affected party, and after notice and opportunity for comment, the Commission shall issue a final order determining whether a State action is inconsistent with a reliability standard, taking into consideration any recommendation of the ERO. |
Rest of § 824o unchanged
16 U.S.C. § 824p Siting of interstate electric transmission facilities
1 change the bill asks for here, 1 carried out
- Carried out:
Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (k).
§ 824p(j)–(k)
Start of § 824p to (j) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (j)(1) | (1) | (1) | ||
| Except as specifically provided, nothing in this section affects any requirement of an environmental law of the United States, including the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). | Except as specifically provided, nothing in this section affects any requirement of an environmental law of the United States, including the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). | |||
| (j)(2) | (2) | (2) | ||
| Subsection (h)(6) shall not apply to any unit of the National Park System, the National Wildlife Refuge System, the National Wild and Scenic Rivers System, the National Trails System, the National Wilderness Preservation System, or a National Monument. | Subsection (h)(6) shall not apply to any unit of the National Park System, the National Wildlife Refuge System, the National Wild and Scenic Rivers System, the National Trails System, the National Wilderness Preservation System, or a National Monument. | |||
| (k) | (k) | |||
16 U.S.C. § 824q Native load service obligation
1 change the bill asks for here, 1 carried out
- Carried out:
Section 217 of the Federal Power Act (16 U.S.C. 824q) is amended by striking subsection (h).
§ 824q(f)–(j)
Start of § 824q to (e) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (f) | (f) Contracts | (f) Contracts | ||
| Nothing in this section shall provide a basis for abrogating any contract or service agreement for firm transmission service or rights in effect as of August 8, 2005. If an ISO in the Western Interconnection had allocated financial transmission rights prior to August 8, 2005, but had not done so with respect to one or more load-serving entities’ firm transmission rights held under contracts to which the preceding sentence applies (or held by reason of ownership or future ownership of transmission facilities), such load-serving entities may not be required, without their consent, to convert such firm transmission rights to tradable or financial rights, except where the load-serving entity has voluntarily joined the ISO as a participating transmission owner (or its successor) in accordance with the ISO tariff. | Nothing in this section shall provide a basis for abrogating any contract or service agreement for firm transmission service or rights in effect as of August 8, 2005. If an ISO in the Western Interconnection had allocated financial transmission rights prior to August 8, 2005, but had not done so with respect to one or more load-serving entities’ firm transmission rights held under contracts to which the preceding sentence applies (or held by reason of ownership or future ownership of transmission facilities), such load-serving entities may not be required, without their consent, to convert such firm transmission rights to tradable or financial rights, except where the load-serving entity has voluntarily joined the ISO as a participating transmission owner (or its successor) in accordance with the ISO tariff. | |||
| (g) | (g) Water pumping facilities | (g) Water pumping facilities | ||
| The Commission shall ensure that any entity described in section 824(f) of this title that owns transmission facilities used predominately to support its own water pumping facilities shall have, with respect to the facilities, protections for transmission service comparable to those provided to load-serving entities pursuant to this section. | The Commission shall ensure that any entity described in section 824(f) of this title that owns transmission facilities used predominately to support its own water pumping facilities shall have, with respect to the facilities, protections for transmission service comparable to those provided to load-serving entities pursuant to this section. | |||
| (h) | (h) | |||
| (i) | (i) Jurisdiction | (i) Jurisdiction | ||
| This section does not authorize the Commission to take any action not otherwise within the jurisdiction of the Commission. | This section does not authorize the Commission to take any action not otherwise within the jurisdiction of the Commission. | |||
| (j) | (j) TVA area | (j) TVA area | ||
Rest of § 824q unchanged
16 U.S.C. § 824t Electricity market transparency rules
1 change the bill asks for here, 1 carried out
- Carried out:
Section 220 of the Federal Power Act (16 U.S.C. 824t) is amended by striking subsection (f).
§ 824t(e)–(f)
Start of § 824t to (e) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (e)(1) | (1) | (1) | ||
| Except as provided in paragraph (2), no person shall be subject to any civil penalty under this section with respect to any violation occurring more than 3 years before the date on which the person is provided notice of the proposed penalty under section 825o–1 of this title. | Except as provided in paragraph (2), no person shall be subject to any civil penalty under this section with respect to any violation occurring more than 3 years before the date on which the person is provided notice of the proposed penalty under section 825o–1 of this title. | |||
| (e)(2) | (2) | (2) | ||
| Paragraph (1) shall not apply in any case in which the Commission finds that a seller that has entered into a contract for the sale of electric energy at wholesale or transmission service subject to the jurisdiction of the Commission has engaged in fraudulent market manipulation activities materially affecting the contract in violation of section 824v of this title. | Paragraph (1) shall not apply in any case in which the Commission finds that a seller that has entered into a contract for the sale of electric energy at wholesale or transmission service subject to the jurisdiction of the Commission has engaged in fraudulent market manipulation activities materially affecting the contract in violation of section 824v of this title. | |||
| (f) | (f) | |||
42 U.S.C. § 18713 Transmission facilitation program
1 change the bill asks for here, 1 carried out
- Carried out:
Section 40106(d)(2) of the Infrastructure Investment and Jobs Act (42 U.S.C. 18713(d)(2)) is amended by striking
$2,500,000,000
and inserting$13,500,000,000
.
§ 18713(d)Funding(1)–(4)
Start of § 18713 to (d)(1)(B) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (1)(C) | (C) | (C) | ||
| any amounts appropriated to the Secretary for the program. | any amounts appropriated to the Secretary for the program. | |||
| (2) | (2) Borrowing authority | (2) Borrowing authority | ||
| The Secretary of the Treasury may, without further appropriation and without fiscal year limitation, loan to the Secretary on such terms as may be fixed by the Secretary and the Secretary of the Treasury, such sums as, in the judgment of the Secretary, are from time to time required for the purpose of carrying out the program, not to exceed, in the aggregate (including deferred interest), $ | The Secretary of the Treasury may, without further appropriation and without fiscal year limitation, loan to the Secretary on such terms as may be fixed by the Secretary and the Secretary of the Treasury, such sums as, in the judgment of the Secretary, are from time to time required for the purpose of carrying out the program, not to exceed, in the aggregate (including deferred interest), $[inserted: 13],500,000,000 in outstanding repayable balances at any 1 time. | |||
| (3) | (3) Authorization of appropriations | (3) Authorization of appropriations | ||
| There is authorized to be appropriated to the Secretary to carry out the program, including for any administrative expenses of carrying out the program that are not recovered under paragraph (4), $10,000,000 for each of fiscal years 2022 through 2026. | There is authorized to be appropriated to the Secretary to carry out the program, including for any administrative expenses of carrying out the program that are not recovered under paragraph (4), $10,000,000 for each of fiscal years 2022 through 2026. | |||
| (4) | (4) Cost recovery | (4) Cost recovery |
Rest of § 18713 unchanged