Changes to the Code
H.R. 8248 · Grid Expansion and Reliability Act · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
In committee · step 2 of 5
16 U.S.C. § 824p Siting of interstate electric transmission facilities
14 changes the bill asks for here, 13 carried out
- Carried out:
in paragraph (1), by striking Secretary of Energy (referred to in this section as the
Secretary
) and inserting Federal Energy Regulatory Commission; and - Carried out:
in paragraphs (2), (3), and (4), by striking
Secretary
each place it appears and insertingFederal Energy Regulatory Commission
; - Carried out:
by striking subsections (b) and (d) and inserting the following:
(b) Self certification prior to construction or modification of electric transmission facilities.— (1) In general.— Beginning on the date on which regulations are issued under paragraph (3), any person may construct or modify an electric transmission facility located in a …
The section already has a provision under this letter or number, so it would have two.
- Carried out:
by striking
a permit under subsection (b) for electric transmission facilities to be located
and insertinga person authorized pursuant to subsection (b) to construct or modify an electric transmission facility
; - Carried out:
by striking
the permit holder
each place it appears and insertingsuch person
; and - Not carried out:
by striking
and, in the determination of the Commission, the permit holder has made good faith efforts to engage with landowners and other stakeholders early in the applicable permitting process
and insertingpermitting process
;“and, in the determination of the Commission, the permit holder has made good faith efforts to engage with landowners and other stakeholders early in the applicable permitting process” isn't in § 824p(e)(1) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“and, in the determination of the Commission, the permit holder has made good faith efforts to engage with landowners and other stakeholders early in the applicable permitting process” not found in /us/usc/t16/s824p/e/1 - Carried out:
by striking
Secretary
each place it appears and insertingFederal Energy Regulatory Commission
; - Carried out:
in paragraph (2), by striking
Department of Energy
and insertingFederal Energy Regulatory Commission
; and - Carried out:
by striking subparagraph (A); and
- Carried out:
by redesignating subparagraphs (B) and (C) as subparagraphs (A) and (B), respectively; and
- Carried out:
in paragraph (2), by striking
Secretary
and insertingFederal Energy Regulatory Commission
; and - Carried out:
by inserting
Federal Energy Regulatory
beforeCommission
; - Carried out:
by striking
Secretary
and insertingFederal Energy Regulatory Commission
; and - Carried out:
by striking
in disagreement
and all that follows throughsubsection (a).
and inserting the following:in disagreement about the siting of transmission facilities within any State that is a party to the compact.
.
This bill puts a provision under a letter or number this section already uses, so the section would have two. The law has probably changed since the bill was written.
§ 824p(a)
§ 824p. Siting of interstate electric transmission facilities
(a) Designation of national interest electric transmission corridors
(1) Not later than 1 year after August 8, 2005, and every 3 years thereafter, the [struck: Secretary][inserted: Federal] [struck: of ]Energy [struck: (referred][inserted: Regulatory] [struck: to in this section as the “Secretary”)][inserted: Commission], in consultation with affected States and Indian Tribes, shall conduct a study of electric transmission capacity constraints and congestion.
(2) Not less frequently than once every 3 years, the [struck: Secretary][inserted: Federal Energy Regulatory Commission], after considering alternatives and recommendations from interested parties (including an opportunity for comment from affected States and Indian Tribes), shall issue a report, based on the study under paragraph (1) or other information relating to electric transmission capacity constraints and congestion, which may designate as a national interest electric transmission corridor any geographic area that—
(i) 1 is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or
(ii) 2 is expected to experience such energy transmission capacity constraints or congestion.
(3) Not less frequently than once every 3 years, the [struck: Secretary][inserted: Federal Energy Regulatory Commission], in conducting the study under paragraph (1) and issuing the report under paragraph (2), shall consult with any appropriate regional entity referred to in section 824o of this title.
(4) In determining whether to designate a national interest electric transmission corridor under paragraph (2), the [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]may consider whether—
(A) the economic vitality and development of the corridor, or the end markets served by the corridor, may be constrained by lack of adequate or reasonably priced electricity;
(B)
§ 824p(a)–(c)
(a)(4)(B)(i)–(G)(i) unchanged ·
(ii) avoids and minimizes, to the maximum extent practicable, and offsets to the extent appropriate and practicable, sensitive environmental areas and cultural heritage sites; and
(H) the designation would result in a reduction in the cost to purchase electric energy for consumers.
(b) [struck: Construction][inserted: Self] [struck: permit][inserted: certification prior to construction or modification of electric transmission facilities.—] [struck: Except as provided in subsection (i), the Commission may, after notice and an opportunity for hearing, issue one or more permits for the construction or modification of electric transmission facilities in a national interest electric transmission corridor designated by the Secretary under subsection (a) if the Commission finds that—]
(1) [inserted: In general.—] [inserted: Beginning on the date on which regulations are issued under paragraph (3), any person may construct or modify an electric transmission facility located in a national interest electric transmission corridor designated under subsection (a) if such person certifies the information described in paragraph (2).]
[struck: (A)] [struck: a State in which the transmission facilities are to be constructed or modified does not have authority to—]
[struck: (i)] [struck: approve the siting of the facilities; or]
[struck: (ii)] [struck: consider the interstate benefits or interregional benefits expected to be achieved by the proposed construction or modification of transmission facilities in the State;]
[struck: (B)] [struck: the applicant for a permit is a transmitting utility under this chapter but does not qualify to apply for a permit or siting approval for the proposed project in a State because the applicant does not serve end-use customers in the State; or]
[struck: (C)] [struck: a State commission or other entity that has authority to approve the siting of the facilities—]
[struck: (i)] [struck: has not made a determination on an application seeking approval pursuant to applicable law by the date that is 1 year after the later of—]
[struck: (I)] [struck: the date on which the application was filed; and]
[struck: (II)] [struck: the date on which the relevant national interest electric transmission corridor was designated by the Secretary under subsection (a);]
[struck: (ii)] [struck: has conditioned its approval in such a manner that the proposed construction or modification will not significantly reduce transmission capacity constraints or congestion in interstate commerce or is not economically feasible; or]
[struck: (iii)] [struck: has denied an application seeking approval pursuant to applicable law;]
(2) [inserted: Information described.—] [inserted: The information described in this paragraph is the following:]
(A) [inserted: The exact legal name, title, mailing address, and principal place of business of the person who will construct or modify the electric transmission facility.]
(B) [inserted: Whether the person who will construct or modify the electric transmission facility is an individual or corporation, and if the person is a corporation, the State under the laws of which such corporation is organized.]
(C) [inserted: A concise description of any existing operations of the person who will construct or modify the electric transmission facility.]
(D) [inserted: A concise description of the electric transmission facility to be constructed or modified, including the dates on which such construction or modification is expected to begin and be completed.]
(E) [inserted: A table of contents that lists each document included in the certification.]
[struck: the facilities to be authorized by the permit will be used for the transmission of electric energy in interstate commerce;]
(3) [inserted: Regulations.—] [inserted: Not later than 365 days after ]the [struck: proposed][inserted: date] [struck: construction][inserted: of] [struck: or][inserted: enactment] [struck: modification][inserted: of] [struck: is][inserted: the] [struck: consistent][inserted: Grid] [struck: with][inserted: Expansion] [inserted: and Reliability Act, ]the [struck: public][inserted: Federal] [struck: interest;][inserted: Energy Regulatory Commission shall issue regulations to carry out this subsection.]
(c) [inserted: Annual audits and reports.—]
(1) [inserted: Audits.—] [inserted: The Federal Energy Regulatory Commission shall annually audit each certification made under subsection (b) to determine whether the certification included the information required by paragraph (2) of such subsection.]
(2) [inserted: Reports.—] [inserted: Not later than 365 days after the date of enactment of the Grid Expansion and Reliability Act, and annually thereafter, the Federal Energy Regulatory Commission shall submit to Congress a report describing—]
(A) [inserted: the efficacy of the certification process under subsection (b) for authorizing the construction and modification of electric transmission facilities;]
(B) [inserted: any issues that result from such process; and]
(C) [inserted: recommendations for how to improve such process through additional legislation or regulation, if needed.]
[struck: (4)] [struck: the proposed construction or modification will significantly reduce transmission congestion in interstate commerce and protects or benefits consumers;]
[struck: (5)] [struck: the proposed construction or modification is consistent with sound national energy policy and will enhance energy independence; and]
[struck: (6)] [struck: the proposed modification will maximize, to the extent reasonable and economical, the transmission capabilities of existing towers or structures.]
(c) Permit applications
(1) Permit applications under subsection (b) shall be made in writing to the Commission.
§ 824p(c)–(e)
(c)(2) unchanged ·
(B) the information to be contained in the application; and
(C) the manner of service of notice of the permit application on interested persons.
[struck: (d)] [struck: Comments] [struck: In any proceeding before the Commission under subsection (b), the Commission shall afford each State in which a transmission facility covered by the permit is or will be located, each affected Federal agency and Indian tribe, private property owners, and other interested persons, a reasonable opportunity to present their views and recommendations with respect to the need for and impact of a facility covered by the permit.]
(e) Rights-of-way
(1) In the case of a [struck: permit][inserted: person] [struck: under][inserted: authorized] [inserted: pursuant to ]subsection (b) [struck: for][inserted: to] [struck: electric][inserted: construct] [struck: transmission][inserted: or] [struck: facilities][inserted: modify] [struck: to][inserted: an] [struck: be][inserted: electric] [struck: located][inserted: transmission] [inserted: facility ]on property other than property owned by the United States or a State, if [struck: the][inserted: such] [struck: permit][inserted: person] [struck: holder ]cannot acquire by contract, or is unable to agree with the owner of the property to the compensation to be paid for, the necessary right-of-way to construct or modify, and operate and maintain, the transmission facilities and, in the determination of the Commission, [struck: the][inserted: such] [struck: permit][inserted: person] [struck: holder ]has made good faith efforts to engage with landowners and other stakeholders early in the applicable permitting process, [struck: the][inserted: such] [struck: permit][inserted: person] [struck: holder ]may acquire the right-of-way by the exercise of the right of eminent domain in the district court of the United States for the district in which the property concerned is located, or in the appropriate court of the State in which the property is located.
(2) Any right-of-way acquired under paragraph (1) shall be used exclusively for the construction or modification of electric transmission facilities within a reasonable period of time after the acquisition.
(3) The practice and procedure in any action or proceeding under this subsection in the district court of the United States shall conform as nearly as practicable to the practice and procedure in a similar action or proceeding in the courts of the State in which the property is located.
§ 824p(h)Coordination of Federal authorizations for transmission facilities(1)–(6)
(e)(4)–(h)(1) unchanged ·
(B) The term “Federal authorization” includes such permits, special use authorizations, certifications, opinions, or other approvals as may be required under Federal law in order to site a transmission facility.
(2) The [struck: Department][inserted: Federal] [struck: of ]Energy [inserted: Regulatory Commission ]shall act as the lead agency for purposes of coordinating all applicable Federal authorizations and related environmental reviews of the facility.
(3) To the maximum extent practicable under applicable Federal law, the [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]shall coordinate the Federal authorization and review process under this subsection with any Indian tribes, multistate entities, and State agencies that are responsible for conducting any separate permitting and environmental reviews of the facility, to ensure timely and efficient review and permit decisions.
(4)
(A) As head of the lead agency, the [struck: Secretary][inserted: Federal Energy Regulatory Commission], in consultation with agencies responsible for Federal authorizations and, as appropriate, with Indian tribes, multistate entities, and State agencies that are willing to coordinate their own separate permitting and environmental reviews with the Federal authorization and environmental reviews, shall establish prompt and binding intermediate milestones and ultimate deadlines for the review of, and Federal authorization decisions relating to, the proposed facility.
(B) The [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]shall ensure that, once an application has been submitted with such data as the [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]considers necessary, all permit decisions and related environmental reviews under all applicable Federal laws shall be completed—
(i) within 1 year; or
(ii) if a requirement of another provision of Federal law does not permit compliance with clause (i), as soon thereafter as is practicable.
(C) The [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]shall provide an expeditious pre-application mechanism for prospective applicants to confer with the agencies involved to have each such agency determine and communicate to the prospective applicant not later than 60 days after the prospective applicant submits a request for such information concerning—
(i) the likelihood of approval for a potential facility; and
(ii) key issues of concern to the agencies and public.
(5)
(A) As lead agency head, the [struck: Secretary][inserted: Federal Energy Regulatory Commission], in consultation with the affected agencies, shall prepare a single environmental review document, which shall be used as the basis for all decisions on the proposed project under Federal law.
(B) The [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]and the heads of other agencies shall streamline the review and permitting of transmission within corridors designated under section 503 of the Federal Land Policy and Management Act (43 U.S.C. 1763) by fully taking into account prior analyses and decisions relating to the corridors.
(C) The document shall include consideration by the relevant agencies of any applicable criteria or other matters as required under applicable law.
(6)
(A) If any agency has denied a Federal authorization required for a transmission facility, or has failed to act by the deadline established by the [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]pursuant to this section for deciding whether to issue the authorization, the applicant or any State in which the facility would be located may file an appeal with the President, who shall, in consultation with the affected agency, review the denial or failure to take action on the pending application.
(B) Based on the overall record and in consultation with the affected agency, the President may—
(i) issue the necessary authorization with any appropriate conditions; or
§ 824p(h)–(j)
(h)(6)(B)(ii)–(D)(iv) unchanged ·
(v) the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1701 et seq.).
(7)
(A) Not later than 18 months after August 8, 2005, the [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]shall issue any regulations necessary to implement this subsection.
(B)
(i) Not later than 1 year after August 8, 2005, the [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]and the heads of all Federal agencies with authority to issue Federal authorizations shall enter into a memorandum of understanding to ensure the timely and coordinated review and permitting of electricity transmission facilities.
(ii) Interested Indian tribes, multistate entities, and State agencies may enter the memorandum of understanding.
(C) The head of each Federal agency with authority to issue a Federal authorization shall designate a senior official responsible for, and dedicate sufficient other staff and resources to ensure, full implementation of the regulations and memorandum required under this paragraph.
(8)
(A) Each Federal land use authorization for an electricity transmission facility shall be issued—
(i) for a duration, as determined by the [struck: Secretary][inserted: Federal Energy Regulatory Commission], commensurate with the anticipated use of the facility; and
(ii) with appropriate authority to manage the right-of-way for reliability and environmental protection.
(B) On the expiration of the authorization (including an authorization issued before August 8, 2005), the authorization shall be reviewed for renewal taking fully into account reliance on such electricity infrastructure, recognizing the importance of the authorization for public health, safety, and economic welfare and as a legitimate use of Federal land.
(9) In exercising the responsibilities under this section, the [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]shall consult regularly with—
[struck: (A)] [struck: the Federal Energy Regulatory Commission;]
[struck: (B)] [inserted: (A)] electric reliability organizations (including related regional entities) approved by the Commission; and
[struck: (C)] [inserted: (B)] Transmission Organizations approved by the Commission.
(i) Interstate compacts
(1) The consent of Congress is given for three or more contiguous States to enter into an interstate compact, subject to approval by Congress, establishing regional transmission siting agencies to—
(A) facilitate siting of future electric energy transmission facilities within those States; and
(B) carry out the electric energy transmission siting responsibilities of those States.
(2) The [struck: Secretary][inserted: Federal] [inserted: Energy Regulatory Commission ]shall provide technical assistance to regional transmission siting agencies established under this subsection.
(3) The regional transmission siting agencies shall have the authority to review, certify, and permit siting of transmission facilities, including facilities in national interest electric transmission corridors (other than facilities on property owned by the United States).
(4) [inserted: The Federal Energy Regulatory Commission shall have no authority to issue a permit for the construction or modification of an electric transmission facility within a State that is a party to a compact, unless the Federal Energy Regulatory Commission determines that the members of the compact are in disagreement about the siting of transmission facilities within any State that is a party to the compact.]
[struck: The Commission shall have no authority to issue a permit for the construction or modification of an electric transmission facility within a State that is a party to a compact, unless the Secretary determines that the members of the compact are in disagreement after the later of—]
[struck: (A)] [struck: the date that is 1 year after the date on which the relevant application for the facility was filed; and]
[struck: (B)] [struck: the date that is 1 year after the date on which the relevant national interest electric transmission corridor was designated by the Secretary under subsection (a).]
(j) Relationship to other laws
(1) Except as specifically provided, nothing in this section affects any requirement of an environmental law of the United States, including the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
Rest of § 824p unchanged ·