Changes to 10 U.S.C. § 3244

H.R. 8800 · National Defense Authorization Act for Fiscal Year 2027 ·

Passed the House · step 3 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

10 U.S.C. § 3244 Use of lowest price technically acceptable source selection process New section

+29 −0Shown
More for 10 U.S.C. § 3244
Every bill that would add § 3244
1 change the bill asks for here, 1 carried out
  1. Carried out:

    Chapter 223 of title 10, United States Code, is amended by inserting after section 3243 the following new section:3244. Use of lowest price technically acceptable source selection process (a) Statement of policy.— It shall be the policy of the Department of Defense to avoid using lowest price technically acceptable source selection criteria in circumstances that would deny the Department the benefits of cost and technical tradeoffs in the source selection process. (b) Regulations.— The Secretary of Defense shall ensure the Defense Federal Acquisition Regulation Supplement requires that lowest price technically acceptable source selection criteria are used only in situations in which— (1) the Department of Defense is able to comprehensively and clearly describe the minimum requirements expressed in terms of performance objectives, measures, and standards that will be used to determine acceptability of offers; (2) the Department of Defense would realize no, or minimal, value from a contract proposal exceeding the minimum technical or performance requirements set forth in the request for proposal; (3) the proposed technical approaches will require no, or minimal, subjective judgment by the source selection authority as to the desirability of one offeror’s proposal versus a competing proposal; (4) the source selection authority has a high degree of confidence that a review of technical proposals of offerors other than the lowest bidder would not result in the identification of factors that could provide value or benefit to the Department; (5) the contracting officer has included a justification for the use of a lowest price technically acceptable evaluation methodology in the contract file; (6) the Department of Defense has determined that the lowest price reflects full life-cycle costs, including for operations and support; (7) the Department of Defense would realize no, or minimal, additional innovation or future technological advantage by using a different methodology; and (8) with respect to a contract for procurement of goods, the goods procured are predominantly expendable in nature, nontechnical, or have a short life expectancy or short shelf life. (c) Avoidance of use of lowest price technically acceptable source selection criteria in certain procurements.— To the maximum extent practicable, the use of lowest price technically acceptable source selection criteria shall be avoided in the case of a procurement that is predominately for the acquisition of— (1) information technology services, cybersecurity services, systems engineering and technical assistance services, advanced electronic testing, audit or audit readiness services, or other knowledge-based professional services; (2) personal protective equipment; or (3) knowledge-based training or logistics services in contingency operations or other operations outside the United States..

§ 3244(a)–(c)

§ 3244. [inserted: Use of lowest price technically acceptable source selection process]

(a) [inserted: Statement of policy.—] [inserted: It shall be the policy of the Department of Defense to avoid using lowest price technically acceptable source selection criteria in circumstances that would deny the Department the benefits of cost and technical tradeoffs in the source selection process.]

(b) [inserted: Regulations.—] [inserted: The Secretary of Defense shall ensure the Defense Federal Acquisition Regulation Supplement requires that lowest price technically acceptable source selection criteria are used only in situations in which—]

(1) [inserted: the Department of Defense is able to comprehensively and clearly describe the minimum requirements expressed in terms of performance objectives, measures, and standards that will be used to determine acceptability of offers;]

(2) [inserted: the Department of Defense would realize no, or minimal, value from a contract proposal exceeding the minimum technical or performance requirements set forth in the request for proposal;]

(3) [inserted: the proposed technical approaches will require no, or minimal, subjective judgment by the source selection authority as to the desirability of one offeror’s proposal versus a competing proposal;]

(4) [inserted: the source selection authority has a high degree of confidence that a review of technical proposals of offerors other than the lowest bidder would not result in the identification of factors that could provide value or benefit to the Department;]

(5) [inserted: the contracting officer has included a justification for the use of a lowest price technically acceptable evaluation methodology in the contract file;]

(6) [inserted: the Department of Defense has determined that the lowest price reflects full life-cycle costs, including for operations and support;]

(7) [inserted: the Department of Defense would realize no, or minimal, additional innovation or future technological advantage by using a different methodology; and]

(8) [inserted: with respect to a contract for procurement of goods, the goods procured are predominantly expendable in nature, nontechnical, or have a short life expectancy or short shelf life.]

(c) [inserted: Avoidance of use of lowest price technically acceptable source selection criteria in certain procurements.—] [inserted: To the maximum extent practicable, the use of lowest price technically acceptable source selection criteria shall be avoided in the case of a procurement that is predominately for the acquisition of—]

(1) [inserted: information technology services, cybersecurity services, systems engineering and technical assistance services, advanced electronic testing, audit or audit readiness services, or other knowledge-based professional services;]

(2) [inserted: personal protective equipment; or]

(3) [inserted: knowledge-based training or logistics services in contingency operations or other operations outside the United States.]

Step through the changes