Title 23 · HighwaysTransportation

Changes to 23 U.S.C. § 139

H.R. 8870 · BUILD America 250 Act ·

Reported by committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

23 U.S.C. § 139 Efficient environmental reviews for project decisionmaking and One Federal Decision

+65 −39Shown
More for 23 U.S.C. § 139
Read § 139
30 changes the bill asks for here, 30 carried out
  1. Carried out:

    in paragraph (1)(B) by striking may and inserting shall; and

  2. Carried out:

    in subparagraph (A) by striking shall review and inserting shall biennially review; and

  3. Carried out:

    in the heading by striking Report and inserting Briefing; and

  4. Carried out:

    by striking Not later than and all that follows through that includes and inserting Not later than 30 days after the completion of each review required under subparagraph (A), the Secretary shall provide to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Environment and Public Works of the Senate a briefing that includes;

  5. Carried out:

    in paragraph (2) by striking 45 days and inserting 30 days;

  6. Carried out:

    in paragraph (8)(D) by striking project if and inserting project only if; and

  7. Carried out:

    in subparagraph (B) by striking final; and

  8. Carried out:

    in subparagraph (C) by striking subparagraph (A) if and inserting subparagraph (A) only if;

  9. Carried out:

    in paragraph (1) by striking process and inserting process and before the definition of a project’s purpose and need in paragraph (2); and

  10. Carried out:

    by striking paragraph (2) and inserting the following:(2) Definition.— (A) In general.— The lead agency shall define such project's purpose and need for purposes of any document which the lead agency is responsible for preparing for the project. (B) Deadline.— The lead agency shall define such project’s purpose and need not later …

  11. Carried out:

    in subparagraph (B) by striking clause (iii) and inserting the following:(iii) Major project schedule.— To the maximum extent practicable and consistent with applicable Federal law, in the case of a major project, the lead agency shall develop, in concurrence with the project sponsor, a schedule for the major project that is consistent with the …

  12. Carried out:

    by striking subparagraph (D) and inserting the following:(D) Modification.— (i) In general.— Subject to the provisions of this subparagraph, the lead agency may not lengthen or shorten a schedule established under subparagraph (B) except for good cause. (ii) Provisions.— (I) Lengthened schedules.— The lead agency may only lengthen a …

  13. Carried out:

    in paragraph (4) by striking unless significant and inserting unless, as determined by the lead agency, significant and relevant;

  14. Carried out:

    in paragraph (7)(D) by striking certifies that and inserting certifies to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Environment and Public Works of the Senate that; and

  15. Carried out:

    in the matter preceding clause (i) by striking 120 days after the date of enactment of the MAP–21 and inserting 90 days; and

  16. Carried out:

    by striking clause (ii) and inserting the following:(ii) A project that requires the preparation of an environmental impact statement. (iii) A sample of not less than 5 percent of the projects requiring preparation of an environmental assessment in each State.;

  17. Carried out:

    in subsection (i) by striking establish and inserting establish, maintain, and continuously improve;

  18. Carried out:

    in subsection (j)(3) by striking section 204 and inserting section 203 or section 204;

  19. Carried out:

    in subsection (l)(1) by striking highway or public transportation and inserting highway, public transportation, or rail;

  20. Carried out:

    in subsection (n) by striking paragraph (3) and inserting the following:(3) Length of environmental documents.— (A) Environmental impact statements.— (i) In general.— Except as provided in clause (ii), an environmental impact statement shall not exceed 150 pages, not including any citations or appendices. (ii) Extraordinary complexity.— An …

  21. Carried out:

    in paragraph (1) by striking Not later than 60 days after the date of enactment of this subsection, and every 4 years thereafter, the Secretary shall and inserting Not less than every 3 years, the Secretary shall; and

  22. Carried out:

    in subparagraph (F) by striking and at the end;

  23. Carried out:

    by redesignating subparagraph (G) as subparagraph (H); and

  24. Carried out:

    by inserting after subparagraph (F) the following:(G) the Environmental Protection Agency; and.

  25. Carried out:

    by striking clause (i)(II) and inserting the following:(II) the evaluations of alternatives in a planning or review process described in clause (ii)(I).; and

  26. Carried out:

    by striking subclause (I) and inserting the following:(I) the alternative was considered in— (aa) a metropolitan planning process by a metropolitan planning organization; (bb) a State environmental review process by a State or local transportation agency; or (cc) a State rail plan under chapter 227 of title 49 that has been approved by the Secretary;;

  27. Carried out:

    in subclause (II) by striking metropolitan planning organization or State or local transportation agency, as applicable, and inserting applicable planning or review entity;

  28. Carried out:

    in subclause (III) by striking metropolitan planning process or State environmental review process and inserting planning or review process;

  29. Carried out:

    in subclause (IV) by striking metropolitan planning organization or State or local transportation agency and inserting planning or review entity; and

  30. Carried out:

    in subclause (V) by striking metropolitan planning organization or State or local transportation agency and inserting planning or review entity.

§ 139(c)Lead Agencies.—(1)–(3)

Start of § 139 to (c)(1) unchanged ·

(A) In general.— The Department of Transportation, or an operating administration thereof designated by the Secretary, shall be the Federal lead agency in the environmental review process for a project.

(B) Modal administration.— If the project requires approval from more than 1 modal administration within the Department, the Secretary [struck: may][inserted: shall] designate a single modal administration to serve as the Federal lead agency for the Department in the environmental review process for the project.

(2) Joint lead agencies.— Nothing in this section precludes another agency from being a joint lead agency in accordance with regulations under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).

(3) Project sponsor as joint lead agency.— Any project sponsor that is a State or local governmental entity receiving funds under this title or chapter 53 of title 49 for the project shall serve as a joint lead agency with the Department for purposes of preparing any environmental document under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and may prepare any such environmental document required in support of any action or approval by the Secretary if the Federal lead agency furnishes guidance in such preparation and independently evaluates such document and the document is approved and adopted by the Secretary prior to the Secretary taking any subsequent action or making any approval based on such document, whether or not the Secretary’s action or approval results in Federal funding.

§ 139(c)–(d)

(c)(4)–(6) unchanged ·

(D) to calculate annually the average time taken by the lead agency to complete all environmental documents for each project during the previous fiscal year.

(7) Process improvements for projects.—

(A) In general.— The Secretary shall [inserted: biennially ]review—

(i) existing practices, procedures, rules, regulations, and applicable laws to identify impediments to meeting the requirements applicable to projects under this section; and

(ii) best practices, programmatic agreements, and potential changes to internal departmental procedures that would facilitate an efficient environmental review process for projects.

(B) Consultation.— In conducting the review under subparagraph (A), the Secretary shall consult, as appropriate, with the heads of other Federal agencies that participate in the environmental review process.

(C) [struck: Report][inserted: Briefing].— Not later than [struck: 2][inserted: 30] [struck: years][inserted: days] after the [struck: date][inserted: completion] of [struck: enactment][inserted: each] [struck: of][inserted: review] [struck: the][inserted: required] [struck: Surface][inserted: under] [struck: Transportation][inserted: subparagraph] [struck: Reauthorization Act of 2021][inserted: (A)], the Secretary shall [struck: submit][inserted: provide] to the Committee on [struck: Environment][inserted: Transportation] and [struck: Public][inserted: Infrastructure] [struck: Works ]of the [struck: Senate][inserted: House] [inserted: of Representatives ]and the Committee on [struck: Transportation][inserted: Environment] and [struck: Infrastructure][inserted: Public] [inserted: Works ]of the [struck: House][inserted: Senate] [struck: of Representatives ]a [struck: report][inserted: briefing] that includes—

(i) the results of the review under subparagraph (A); and

(ii) an analysis of whether additional funding would help the Secretary meet the requirements applicable to projects under this section.

(d) Participating Agencies.—

(1) In general.— The lead agency shall be responsible for inviting and designating participating agencies in accordance with this subsection.

(2) Invitation.— Not later than [struck: 45][inserted: 30] days after the date of publication of a notice of intent to prepare an environmental impact statement or the initiation of an environmental assessment, the lead agency shall identify any other Federal and non-Federal agencies that may have an interest in the project, and shall invite such agencies to become participating agencies in the environmental review process for the project. The invitation shall set a deadline for responses to be submitted. The deadline may be extended by the lead agency for good cause.

(3) Federal participating agencies.— Any Federal agency that is invited by the lead agency to participate in the environmental review process for a project shall be designated as a participating agency by the lead agency unless the invited agency informs the lead agency, in writing, by the deadline specified in the invitation that the invited agency—

(A) has no jurisdiction or authority with respect to the project;

§ 139(d)(8)Single environmental document.—(C)–(D)

(d)(3)(B)–(8)(B) unchanged ·

(C) Treatment as participating and cooperating agencies.— A Federal agency required to make an approval or take an action for a project, as described in subparagraph (B), shall work with the lead agency for the project to ensure that the agency making the approval or taking the action is treated as being both a participating and cooperating agency for the project.

(D) Exceptions.— The lead agency may waive the application of subparagraph (A) with respect to a project [inserted: only ]if—

(i) the project sponsor requests that agencies issue separate environmental documents;

(ii) the obligations of a cooperating agency or participating agency under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) have already been satisfied with respect to the project; or

§ 139(d)(10)Timely authorizations for major projects.—(A)–(C)

(d)(8)(D)(iii)–(10) unchanged ·

(A) Deadline.— Except as provided in subparagraph (C), all authorization decisions necessary for the construction of a major project shall be completed by not later than 90 days after the date of the issuance of a record of decision for the major project.

(B) Detail.— The [struck: final ]environmental impact statement for a major project shall include an adequate level of detail to inform decisions necessary for the role of the participating agencies and cooperating agencies in the environmental review process.

(C) Extension of deadline.— The head of the lead agency may extend the deadline under subparagraph (A) [inserted: only ]if—

(i) Federal law prohibits the lead agency or another agency from issuing an approval or permit within the period described in that subparagraph;

(ii) the project sponsor requests that the permit or approval follow a different timeline; or

§ 139(e)–(f)

(d)(10)(C)(iii)–(e)(5)(B)(ii) unchanged ·

(iii) to improve interagency collaboration to help expedite the permitting process for the lead agency and participating agencies.

(f) Purpose and Need; Alternatives Analysis.—

(1) Participation.— As early as practicable during the environmental review process[inserted: and before the definition of a project’s purpose and need in paragraph (2)], the lead agency shall provide an opportunity for involvement by participating agencies and the public in defining the purpose and need for a project.

(2) Definition.—

(A) [inserted: In general.—] [inserted: The lead agency shall define such project's purpose and need for purposes of any document which the lead agency is responsible for preparing for the project.]

(B) [inserted: Deadline.—] [inserted: The lead agency shall define such project’s purpose and need not later than 45 days after—]

(i) [inserted: the submission by the project sponsor of the appropriate information to inform the purpose and need description; or]

(ii) [inserted: any appropriately completed proposed revision to a project that affects the purpose and need description previously prepared or accepted by the lead agency.]

(C) [inserted: Technical assistance.—] [inserted: The Secretary may provide a project sponsor with technical assistance in drafting—]

(i) [inserted: a purpose and need statement; and]

(ii) [inserted: any necessary supporting documentation for projects involving Federal approvals from more than 1 Federal agency.]

[struck: Following participation under paragraph (1), the lead agency shall define the project’s purpose and need for purposes of any document which the lead agency is responsible for preparing for the project.]

(3) Objectives.— The statement of purpose and need shall include a clear statement of the objectives that the proposed action is intended to achieve, which may include—

(A) achieving a transportation objective identified in an applicable statewide or metropolitan transportation plan;

§ 139(f)(4)(E)Reduction of duplication.—(i)–(ii)

(f)(3)(B)–(4)(E) unchanged ·

(I) the evaluation of alternatives under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and

(II) the [struck: evaluation][inserted: evaluations] of alternatives in [struck: the][inserted: a] [struck: metropolitan transportation ]planning [struck: process under section 134 ]or [struck: an environmental ]review process [struck: carried][inserted: described] [struck: out under State law (referred to ]in [struck: this][inserted: clause] [struck: subparagraph as a “State environmental review process”][inserted: (ii])[inserted: (I)].

(ii) Consideration of alternatives.— The lead agency may eliminate from detailed consideration an alternative proposed in an environmental impact statement regarding a project if, as determined by the lead agency—

(I) [inserted: the alternative was considered in—]

(aa) [inserted: a metropolitan planning process by a metropolitan planning organization;]

(bb) [inserted: a State environmental review process by a State or local transportation agency; or]

(cc) [inserted: a State rail plan under chapter 227 of title 49 that has been approved by the Secretary;]

[struck: the alternative was considered in a metropolitan planning process or a State environmental review process by a metropolitan planning organization or a State or local transportation agency, as applicable;]

(II) the lead agency provided guidance to the [struck: metropolitan][inserted: applicable] planning [struck: organization ]or [struck: State][inserted: review] [struck: or][inserted: entity] [struck: local transportation agency, as applicable, ]regarding analysis of alternatives in the metropolitan planning process or State environmental review process, including guidance on the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and any other Federal law necessary for approval of the project;

(III) the applicable [struck: metropolitan ]planning [struck: process ]or [struck: State environmental ]review process included an opportunity for public review and comment;

(IV) the applicable [struck: metropolitan ]planning [struck: organization ]or [struck: State][inserted: review] [struck: or][inserted: entity] [struck: local transportation agency ]rejected the alternative after considering public comments;

(V) the Federal lead agency independently reviewed the alternative evaluation approved by the applicable [struck: metropolitan ]planning [struck: organization ]or [struck: State][inserted: review] [struck: or local transportation agency][inserted: entity]; and

(VI) the Federal lead agency determined—

(aa) in consultation with Federal participating or cooperating agencies, that the alternative to be eliminated from consideration is not necessary for compliance with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); or

§ 139(g)(1)Coordination plan.—(B)–(E)

(f)(4)(E)(ii)(VI)(bb)–(g)(1)(B)(ii)(IV) unchanged ·

(V) the sensitivity of the natural and historic resources that could be affected by the project.

(iii) Major project schedule.— To the maximum extent practicable and consistent with applicable Federal law, in the case of a major project, the lead agency shall develop, in concurrence with the project sponsor, a schedule for the major project that is consistent with [struck: an][inserted: the] [inserted: following ]agency [struck: average][inserted: averages] [struck: of not more than 2 years ]for the completion of the environmental review process for major projects[struck: , as measured from, as applicable]—

(I) [inserted: not more than 2 years for an environmental impact statement, as measured from ]the date of publication of a notice of intent to prepare an environmental impact statement to the record of decision; or

(II) [inserted: not more than 1 year for an environmental assessment, as measured from ]the date on which the head of the lead agency determines that an environmental assessment is required to a finding of no significant impact.

(C) Consistency with other time periods.— A schedule under subparagraph (B) shall be consistent with any other relevant time periods established under Federal law.

(D) Modification.—

(i) In general.— [struck: Except][inserted: Subject] [struck: as][inserted: to] [struck: provided][inserted: the] [struck: in][inserted: provisions] [struck: clause][inserted: of] [struck: (ii)][inserted: this subparagraph], the lead agency may [inserted: not ]lengthen or shorten a schedule established under subparagraph (B) [inserted: except ]for good cause.

(ii) [struck: Exceptions][inserted: Provisions].—

(I) [struck: Major][inserted: Lengthened] [struck: projects][inserted: schedules].— [struck: In][inserted: The] [struck: the case of a major project, the ]lead agency may [inserted: only ]lengthen a schedule under clause (i) for a cooperating Federal agency by not more than 1 year after the latest deadline established for the major project by the lead agency.

(II) Shortened schedules.— The lead agency may not shorten a schedule under clause (i) if doing so would impair the ability of a cooperating Federal agency to conduct necessary analyses or otherwise carry out relevant obligations of the Federal agency for the project.

(E) Failure to meet deadline.— If a cooperating Federal agency fails to meet a deadline established under subparagraph (D)(ii)(I)—

§ 139(h)Issue Identification and Resolution.—(3)–(5)

(g)(1)(E)(i)–(h)(2) unchanged ·

(3) Participating agency responsibilities.— Based on information received from the lead agency, participating agencies shall identify, as early as practicable, any issues of concern regarding the project’s potential environmental or socioeconomic impacts. In this paragraph, issues of concern include any issues that could substantially delay or prevent an agency from granting a permit or other approval that is needed for the project.

(4) Issue resolution.— Any issue resolved by the lead agency with the concurrence of participating agencies may not be reconsidered unless[inserted: ,] [inserted: as determined by the lead agency, ]significant [inserted: and relevant ]new information or circumstances arise.

(5) Interim decision on achieving accelerated decisionmaking.—

(A) In general.— Not later than 30 days after the close of the public comment period on a draft environmental impact statement, the Secretary may convene a meeting with the project sponsor, lead agency, resource agencies, and any relevant State agencies to ensure that all parties are on schedule to meet deadlines for decisions to be made regarding the project.

§ 139(h)(7)Financial penalty provisions.—(C)–(D)

(h)(5)(B)–(7)(C) unchanged ·

(ii) Failure to decide.— The total amount rescinded in a fiscal year as a result of a failure by an agency to make a decision by an applicable deadline shall not exceed an amount equal to 7 percent of the funds made available for the applicable agency office for that fiscal year.

(D) No fault of agency.— A rescission of funds under this paragraph shall not be made if the lead agency for the project certifies [inserted: to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Environment and Public Works of the Senate ]that—

(i) the agency has not received necessary information or approvals from another entity, such as the project sponsor, in a manner that affects the ability of the agency to meet any requirements under State, local, or Federal law; or

(ii) significant new information or circumstances, including a major modification to an aspect of the project, requires additional analysis for the agency to make a decision on the project application.

§ 139(h)–(j)

(h)(7)(E)–(8) unchanged ·

(A) adequate resources made available under this title shall be devoted to ensuring that applicable environmental reviews under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) are completed on an expeditious basis and that the shortest existing applicable process under that Act is implemented; and

(B) the President shall submit to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Environment and Public Works of the Senate, not less frequently than once every [struck: 120][inserted: 90] days[struck: after the date of enactment of the MAP–21], a report on the status and progress of the following projects and activities funded under this title with respect to compliance with applicable requirements under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.):

(i) Projects and activities required to prepare an annual financial plan under section 106(i).

(ii) A [struck: sample][inserted: project] [struck: of][inserted: that] [struck: not][inserted: requires] [struck: less than 5 percent of ]the [struck: projects requiring ]preparation of an environmental impact statement[struck: or environmental assessment in each State].

(iii) [inserted: A sample of not less than 5 percent of the projects requiring preparation of an environmental assessment in each State.]

(i) Performance Measurement.— The Secretary shall establish[inserted: ,] [inserted: maintain, and continuously improve ]a program to measure and report on progress toward improving and expediting the planning and environmental review process.

(j) Assistance to Affected State and Federal Agencies.—

(1) In general.—

(A) Authority to provide funds.— The Secretary may allow a public entity receiving financial assistance from the Department of Transportation under this title or chapter 53 of title 49 to provide funds to Federal agencies (including the Department), State agencies, and Indian tribes participating in the environmental review process for the project or program.

(B) Use of funds.— Funds referred to in subparagraph (A) may be provided only to support activities that directly and meaningfully contribute to expediting and improving permitting and review processes, including planning, approval, and consultation processes for the project or program.

(2) Activities eligible for funding.— Activities for which funds may be provided under paragraph (1) include transportation planning activities that precede the initiation of the environmental review process, activities directly related to the environmental review process, dedicated staffing, training of agency personnel, information gathering and mapping, and development of programmatic agreements.

(3) Use of federal lands highway funds.— The Secretary may also use funds made available under section [inserted: 203 or section ]204 for a project for the purposes specified in this subsection with respect to the environmental review process for the project.

(4) Amounts.— Requests under paragraph (1) may be approved only for the additional amounts that the Secretary determines are necessary for the Federal agencies, State agencies, or Indian tribes participating in the environmental review process to meet the time limits for environmental review.

(5) Condition.— A request under paragraph (1) to expedite time limits for environmental review may be approved only if such time limits are less than the customary time necessary for such review.

§ 139(k)–(m)

(j)(6)–(k)(3) unchanged ·

(B) any power, jurisdiction, responsibility, or authority that a Federal, State, or local government agency, metropolitan planning organization, Indian tribe, or project sponsor has with respect to carrying out a project or any other provisions of law applicable to projects, plans, or programs.

(l) Limitations on Claims.—

(1) In general.— Notwithstanding any other provision of law, a claim arising under Federal law seeking judicial review of a permit, license, or approval issued by a Federal agency for a highway[inserted: ,] [struck: or ]public transportation[inserted: ,] [inserted: or rail ]capital project shall be barred unless it is filed within 150 days after publication of a notice in the Federal Register announcing that the permit, license, or approval is final pursuant to the law under which the agency action is taken, unless a shorter time is specified in the Federal law pursuant to which judicial review is allowed. Nothing in this subsection shall create a right to judicial review or place any limit on filing a claim that a person has violated the terms of a permit, license, or approval.

(2) New information.— The Secretary shall consider new information received after the close of a comment period if the information satisfies the requirements for a supplemental environmental impact statement under section 771.130 of title 23, Code of Federal Regulations. The preparation of a supplemental environmental impact statement when required shall be considered a separate final agency action and the deadline for filing a claim for judicial review of such action shall be 150 days after the date of publication of a notice in the Federal Register announcing such action.

(m) Enhanced Technical Assistance and Accelerated Project Completion.—

§ 139(n)–(o)

(m)(1)–(n)(2) unchanged ·

(A) the final environmental impact statement makes substantial changes to the proposed action that are relevant to environmental or safety concerns; or

(B) there is a significant new circumstance or information relevant to environmental concerns that bears on the proposed action or the impacts of the proposed action.

(3) Length of environmental [struck: document][inserted: documents].—

(A) [struck: In][inserted: Environmental] [struck: general][inserted: impact statements].—

(i) [inserted: In general.—] [inserted: Except as provided in clause (ii), an environmental impact statement shall not exceed 150 pages, not including any citations or appendices.]

(ii) [inserted: Extraordinary complexity.—] [inserted: An environmental impact statement for a proposed action of extraordinary complexity, as determined by the lead agency, shall not exceed 300 pages, not including any citations or appendices.]

[struck: Notwithstanding any other provision of law and except as provided in subparagraph (B), to the maximum extent practicable, the text of the items described in paragraphs (4) through (6) of section 1502.10(a) of title 40, Code of Federal Regulations (or successor regulations), of an environmental impact statement for a project shall be 200 pages or fewer.]

(B) [struck: Exemption][inserted: Environmental assessments].— An environmental [struck: impact][inserted: assessment] [struck: statement][inserted: shall] [struck: for][inserted: not] [struck: a project may ]exceed [struck: 200][inserted: 75] pages, [struck: if][inserted: not] [struck: the][inserted: including] [struck: lead][inserted: any] [struck: agency][inserted: citations] [struck: establishes][inserted: or] [struck: a new page limit for the environmental impact statement for that project][inserted: appendices].

(o) Improving Transparency in Environmental Reviews.—

(1) In general.— Not later than 18 months after the date of enactment of this subsection, the Secretary shall—

§ 139(p)–(q)

(o)(1)(A)–(p)(2)(B) unchanged ·

(C) the time taken to complete the environmental review process.

(q) Development of Categorical Exclusions.—

(1) In general.— Not [struck: later][inserted: less] than [struck: 60 days after the date of enactment of this subsection, and ]every [struck: 4][inserted: 3] years[struck: thereafter], the Secretary shall—

(A) in consultation with the agencies described in paragraph (2), identify the categorical exclusions described in section 771.117 of title 23, Code of Federal Regulations (or successor regulations), that would accelerate delivery of a project if those categorical exclusions were available to those agencies;

(B) collect existing documentation and substantiating information on the categorical exclusions described in subparagraph (A); and

§ 139(q)Development of Categorical Exclusions.—(2)–(3)

(q)(1)(C)–(2)(D) unchanged ·

(E) the Department of Energy;

(F) the Department of Defense;[struck: and]

(G) [inserted: the Environmental Protection Agency; and]

[struck: (G)] [inserted: (H)] any other Federal agency that has participated in an environmental review process for a project, as determined by the Secretary.

(3) Adoption of categorical exclusions.—

(A) In general.— Not later than 1 year after the date on which the Secretary provides a list under paragraph (1)(C), an agency described in paragraph (2) shall publish a notice of proposed rulemaking to propose any categorical exclusions from the list applicable to the agency, subject to the condition that the categorical exclusion identified under paragraph (1)(A) meets the criteria for a categorical exclusion under section 1508.1 of title 40, Code of Federal Regulations (or successor regulations).

(B) Public comment.— In a notice of proposed rulemaking under subparagraph (A), the applicable agency may solicit comments on whether any of the proposed new categorical exclusions meet the criteria for a categorical exclusion under section 1508.1 of title 40, Code of Federal Regulations (or successor regulations).