30 U.S.C. § 1265 Environmental protection performance standards

+9 −59 of 11 shown
More for 30 U.S.C. § 1265
Read § 1265
11 changes the bill asks for here, 9 carried out
  1. Carried out:

    by inserting and not later than 180 days after the date of the last coal production as reported pursuant to section 402(c) after except as provided in subsection (c);

  2. Carried out:

    by inserting ensure proper drainage control, after with respect to all surface coal mining operations; and

  3. Carried out:

    by inserting and complete all final backfilling and grading before the equipment necessary for backfilling and grading is removed from the site after to retain moisture to assist revegetation or as otherwise authorized pursuant to this Act);

  4. Carried out:

    in paragraph (16), by inserting , with such specific requirements for maximum time periods allowable for contemporaneous reclamation set forth in paragraphs (3), (19), and (20) of this subsection, paragraph (7) of subsection (c), and section 519(c) after contemporaneously as practicable with the surface coal mining operations;

  5. Carried out:

    in paragraph (19), by inserting not later than 36 months after the date of last coal production as reported pursuant to section 402(c) before establish on the regraded areas;

  6. Not carried out:

    in subparagraph (B), by striking the period at the end and inserting ; and; and

    The bill strikes “.” at the end of § 1265(b)(20)(B), but the text there doesn't end with it. The law may have changed since the bill was drafted.

    Technical detail“.” is not at the end of /us/usc/t30/s1265/b/20/B
  7. Carried out:

    by adding at the end the following:(C) in no instance shall the operator be allowed more than 1 year greater than the time periods set forth in this subsection to achieve successful revegetation;;

  8. Not carried out:

    in paragraph (22)(I), by striking the period at the end and inserting a semicolon;

    The bill strikes “.” at the end of § 1265(b)(22)(I), but the text there doesn't end with it. The law may have changed since the bill was drafted.

    Technical detail“.” is not at the end of /us/usc/t30/s1265/b/22/I
  9. Carried out:

    in paragraph (23), by striking and at the end; and

  10. Carried out:

    in paragraph (24), by adding and at the end; and

  11. Carried out:

    in subsection (c), by adding at the end the following:(7) All backfilling and regrading to ensure proper drainage control, prevent leaching of toxic materials, eliminate highwalls, spoil piles, and depressions (unless small depressions are needed in order to retain moisture to assist revegetation or as otherwise authorized pursuant …

§ 1265(b)General standards(2)–(5)

Start of § 1265 to (b)(1) unchanged ·

(2) restore the land affected to a condition capable of supporting the uses which it was capable of supporting prior to any mining, or higher or better uses of which there is reasonable likelihood, so long as such use or uses do not present any actual or probable hazard to public health or safety or pose any actual or probable threat of water diminution or pollution, and the permit applicants’ declared proposed land use following reclamation is not deemed to be impractical or unreasonable, inconsistent with applicable land use policies and plans, involves unreasonable delay in implementation, or is violative of Federal, State, or local law;

(3) except as provided in subsection (c) [inserted: and not later than 180 days after the date of the last coal production as reported pursuant to section 402(c) ]with respect to all surface coal mining operations [inserted: ensure proper drainage control, ]backfill, compact (where advisable to insure stability or to prevent leaching of toxic materials), and grade in order to restore the approximate original contour of the land with all highwalls, spoil piles, and depressions eliminated (unless small depressions are needed in order to retain moisture to assist revegetation or as otherwise authorized pursuant to this chapter)[inserted: and complete all final backfilling and grading before the equipment necessary for backfilling and grading is removed from the site]: Provided, however, That in surface coal mining which is carried out at the same location over a substantial period of time where the operation transects the coal deposit, and the thickness of the coal deposits relative to the volume of the overburden is large and where the operator demonstrates that the overburden and other spoil and waste materials at a particular point in the permit area or otherwise available from the entire permit area is insufficient, giving due consideration to volumetric expansion, to restore the approximate original contour, the operator, at a minimum, shall backfill, grade, and compact (where advisable) using all available overburden and other spoil and waste materials to attain the lowest practicable grade but not more than the angle of repose, to provide adequate drainage and to cover all acid-forming and other toxic materials, in order to achieve an ecologically sound land use compatible with the surrounding region: And provided further, That in surface coal mining where the volume of overburden is large relative to the thickness of the coal deposit and where the operator demonstrates that due to volumetric expansion the amount of overburden and other spoil and waste materials removed in the course of the mining operation is more than sufficient to restore the approximate original contour, the operator shall after restoring the approximate contour, backfill, grade, and compact (where advisable) the excess overburden and other spoil and waste materials to attain the lowest grade but not more than the angle of repose, and to cover all acid-forming and other toxic materials, in order to achieve an ecologically sound land use compatible with the surrounding region and that such overburden or spoil shall be shaped and graded in such a way as to prevent slides, erosion, and water pollution and is revegetated in accordance with the requirements of this chapter;

(4) stabilize and protect all surface areas including spoil piles affected by the surface coal mining and reclamation operation to effectively control erosion and attendant air and water pollution;

(5) remove the topsoil from the land in a separate layer, replace it on the backfill area, or if not utilized immediately, segregate it in a separate pile from other spoil and when the topsoil is not replaced on a backfill area within a time short enough to avoid deterioration of the topsoil, maintain a successful cover by quick growing plant or other means thereafter so that the topsoil is preserved from wind and water erosion, remains free of any contamination by other acid or toxic material, and is in a usable condition for sustaining vegetation when restored during reclamation, except if topsoil is of insufficient quantity or of poor quality for sustaining vegetation, or if other strata can be shown to be more suitable for vegetation requirements, then the operator shall remove, segregate, and preserve in a like manner such other strata which is best able to support vegetation;

§ 1265(b)General standards(15)–(16)

(b)(6)–(15) unchanged ·

(E) provide that upon the request of a resident or owner of a man-made dwelling or structure within one-half mile of any portion of the permitted area the applicant or permittee shall conduct a pre-blasting survey of such structures and submit the survey to the regulatory authority and a copy to the resident or owner making the request. The area of the survey shall be decided by the regulatory authority and shall include such provisions as the Secretary shall promulgate.4

(16) insure that all reclamation efforts proceed in an environmentally sound manner and as contemporaneously as practicable with the surface coal mining operations[inserted: , with such specific requirements for maximum time periods allowable for contemporaneous reclamation set forth in paragraphs (3), (19), and (20) of this subsection, paragraph (7) of subsection (c), and section 519(c)]: Provided, however, That where the applicant proposes to combine surface mining operations with underground mining operations to assure maximum practical recovery of the mineral resources, the regulatory authority may grant a variance for specific areas within the reclamation plan from the requirement that reclamation efforts proceed as contemporaneously as practicable to permit underground mining operations prior to reclamation:

(A) if the regulatory authority finds in writing that:

(i) the applicant has presented, as part of the permit application, specific, feasible plans for the proposed underground mining operations;

§ 1265(b)General standards(18)–(22)

(b)(16)(A)(ii)–(17) unchanged ·

(18) refrain from the construction of roads or other access ways up a stream bed or drainage channel or in such proximity to such channel so as to seriously alter the normal flow of water;

(19) [inserted: not later than 36 months after the date of last coal production as reported pursuant to section 402(c) ]establish on the regraded areas, and all other lands affected, a diverse, effective, and permanent vegetative cover of the same seasonal variety native to the area of land to be affected and capable of self-regeneration and plant succession at least equal in extent of cover to the natural vegetation of the area; except, that introduced species may be used in the revegetation process where desirable and necessary to achieve the approved postmining land use plan;

(20)

(A) assume the responsibility for successful revegetation, as required by paragraph (19) above, for a period of five full years after the last year of augmented seeding, fertilizing, irrigation, or other work in order to assure compliance with paragraph (19) above, except in those areas or regions of the country where the annual average precipitation is twenty-six inches or less, then the operator’s assumption of responsibility and liability will extend for a period of ten full years after the last year of augmented seeding, fertilizing, irrigation, or other work: Provided, That when the regulatory authority approves a long-term intensive agricultural postmining land use, the applicable five- or ten-year period of responsibility for revegetation shall commence at the date of initial planting for such long-term intensive agricultural postmining land use: Provided further, That when the regulatory authority issues a written finding approving a long-term, intensive, agricultural postmining land use as part of the mining and reclamation plan, the authority may grant exception to the provisions of paragraph (19) above;

(B) on lands eligible for remining assume the responsibility for successful revegetation for a period of two full years after the last year of augmented seeding, fertilizing, irrigation, or other work in order to assure compliance with the applicable standards, except in those areas or regions of the country where the annual average precipitation is twenty-six inches or less, then the operator’s assumption of responsibility and liability will be extended for a period of five full years after the last year of augmented seeding, fertilizing, irrigation, or other work in order to assure compliance with the applicable standards.4

(C) [inserted: in no instance shall the operator be allowed more than 1 year greater than the time periods set forth in this subsection to achieve successful revegetation;]

(21) protect offsite areas from slides or damage occurring during the surface coal mining and reclamation operations, and not deposit spoil material or locate any part of the operations or waste accumulations outside the permit area;

(22) place all excess spoil material resulting from coal surface mining and reclamation activities in such a manner that—

§ 1265(b)–(c)

(b)(22)(A)–(H) unchanged ·

(I) all other provisions of this chapter are met.4

(23) meet such other criteria as are necessary to achieve reclamation in accordance with the purposes of this chapter, taking into consideration the physical, climatological, and other characteristics of the site;[struck: and]

(24) to the extent possible using the best technology currently available, minimize disturbances and adverse impacts of the operation on fish, wildlife, and related environmental values, and achieve enhancement of such resources where practicable;[inserted: and]

(25) provide for an undisturbed natural barrier beginning at the elevation of the lowest coal seam to be mined and extending from the outslope for such distance as the regulatory authority shall determine shall be retained in place as a barrier to slides and erosion.

(c) Procedures; exception to original contour restoration requirements

§ 1265(c)–(d)

(c)(1)–(4) unchanged ·

(5) The regulatory authority shall promulgate specific regulations to govern the granting of permits in accord with the provisions of this subsection, and may impose such additional requirements as he deems to be necessary.

(6) All permits granted under the provisions of this subsection shall be reviewed not more than three years from the date of issuance of the permit, unless the applicant affirmatively demonstrates that the proposed development is proceeding in accordance with the terms of the approved schedule and reclamation plan.

(7) [inserted: All backfilling and regrading to ensure proper drainage control, prevent leaching of toxic materials, eliminate highwalls, spoil piles, and depressions (unless small depressions are needed in order to retain moisture to assist revegetation or as otherwise authorized pursuant to this Act), and ensure stability, shall be completed not later than 180 days after the date of coal production as reported pursuant to section 402(c).]

(d) Steep-slope surface coal mining standards The following performance standards shall be applicable to steep-slope surface coal mining and shall be in addition to those general performance standards required by this section: Provided, however, That the provisions of this subsection (d) shall not apply to those situations in which an operator is mining on flat or gently rolling terrain, on which an occasional steep slope is encountered through which the mining operation is to proceed, leaving a plain or predominantly flat area or where an operator is in compliance with provisions of subsection (c) hereof:

(1) Insure that when performing surface coal mining on steep slopes, no debris, abandoned or disabled equipment, spoil material, or waste mineral matter be placed on the downslope below the bench or mining cut: Provided, That spoil material in excess of that required for the reconstruction of the approximate original contour under the provisions of subsection (b)(3) or (d)(2) shall be permanently stored pursuant to subsection (b)(22).

Rest of § 1265 unchanged ·