H.R. 9340 · Ratepayer Protection Act · Placed on calendar The text put on a chamber's list of bills that may be brought up for a vote.
Passed the House · step 3 of 5
16 U.S.C. § 2621 Consideration and determination respecting certain ratemaking standards
1 change the bill asks for here, 1 carried out
- Carried out:
Section 111(d) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621(d)) is amended by adding at the end the following:
(22) Standards for large-load customers.— (A) Recovery of full, incremental cost of upgrades.— A rate charged, or entered into, by an electric utility for providing electric service to a large-load customer shall be designed to recover from the large-load customer the full, …
§ 2621(d)Establishment(21)–(22)
Start of § 2621 to (d)(21)(B) unchanged ·
(C) accelerate third-party investment in electric vehicle charging for light-, medium-, and heavy-duty vehicles; and
(D) appropriately recover the marginal costs of delivering electricity to electric vehicles and electric vehicle charging infrastructure.
(22) [inserted: Standards for large-load customers.—]
(A) [inserted: Recovery of full, incremental cost of upgrades.—] [inserted: A rate charged, or entered into, by an electric utility for providing electric service to a large-load customer shall be designed to recover from the large-load customer the full, incremental cost of any generation, transmission, or distribution upgrade necessary to serve the load of such large-load customer, including in the event of such large-load customer terminating a contract or other agreement with the electric utility pertaining to the sale of electric energy, or otherwise ceasing the purchase of electric energy from the electric utility.]
(B) [inserted: Financial assurances and contributions.—] [inserted: Before making any generation, transmission, or distribution upgrade that is necessary to serve the load of a large-load customer, an electric utility shall require the large-load customer provide to the electric utility financial assurances or contributions to cover the cost of such upgrade.]
(C) [inserted: Large-load customer defined.—] [inserted: In this paragraph, the term “large-load customer” means a non-residential electric consumer that, on or after the date of the enactment of this paragraph, requests to enter into, or enters into, a contract or other agreement pertaining to the sale of electric energy for one or more facilities that—]
(i) [inserted: require electric energy primarily to operate information technology infrastructure and related systems pertaining to data storage and computational applications and services; and]
(ii) [inserted: have, in the aggregate, a peak electric demand of 100 megawatts or more at a single site or campus.]
16 U.S.C. § 2622 Obligations to consider and determine
4 changes the bill asks for here, 3 carried out
- Carried out:
in subsection (b), by adding at the end the following:
(9) (A) Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated electric utility shall commence consideration under section …
- Carried out:
by striking
subsection (b)(2)
and insertingsubsection (b)
; and - Not carried out:
by inserting
In the case of the standard established by paragraph (22) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (22).
afterparagraph (21).
; and“paragraph (21).” isn't in § 2622(c) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“paragraph (21).” not found in /us/usc/t16/s2622/c - Carried out:
by adding at the end the following:
(i) Other prior state actions.— Subsections (b) and (c) shall not apply to the standard established by paragraph (22) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection— (1) the State has implemented for the …
§ 2622(b)–(d)
Start of § 2622 to (b)(8) unchanged ·
(A) Not later than 1 year after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 2621 of this title, or set a hearing date for consideration, with respect to the standard established by paragraph (21) of section 2621(d) of this title.
(B) Not later than 2 years after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 2621 of this title with respect to the standard established by paragraph (21) of section 2621(d) of this title.
(9)
(A) [inserted: Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated electric utility shall commence consideration under section 111, or set a hearing date for consideration, with respect to the standard established by paragraph (22) of section 111(d).]
(B) [inserted: Not later than 2 years after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated electric utility shall complete the consideration and make the determination under section 111 with respect to the standard established by paragraph (22) of section 111(d).]
(c) Failure to comply Each State regulatory authority (with respect to each electric utility for which it has ratemaking authority) and each nonregulated electric utility shall undertake the consideration, and make the determination, referred to in section 2621 of this title with respect to each standard established by section 2621(d) of this title in the first rate proceeding commenced after the date three years after November 9, 1978, respecting the rates of such utility if such State regulatory authority or nonregulated electric utility has not, before such date, complied with subsection (b)[struck: (2)] with respect to such standard. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standards established by paragraphs (16) through (19) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to December 19, 2007. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021.
(d) Prior State actions relating to standard under certain paragraphs of section 2621(d) Subsections (b) and (c) of this section shall not apply to the standards established by paragraphs (11) through (13) and paragraphs (16) through (19) of section 2621(d) of this title in the case of any electric utility in a State if, before August 8, 2005—
(1) the State has implemented for such utility the standard concerned (or a comparable standard);
§ 2622(h)–(i)
(d)(2)–(h)(1) unchanged ·
(2) the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or
(3) the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility during the 3-year period ending on November 15, 2021.
(i) [inserted: Other prior state actions.—] [inserted: Subsections (b) and (c) shall not apply to the standard established by paragraph (22) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection—]
(1) [inserted: the State has implemented for the electric utility the standard (or a comparable standard);]
(2) [inserted: the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or]
(3) [inserted: the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility.]
16 U.S.C. § 2634 Prior and pending proceedings
1 change the bill asks for here, 1 carried out
- Carried out:
Section 124 of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2634) is amended by adding at the end the following:
In the case of the standard established by paragraph (22) of section 111(d), the reference contained in this section to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (22).
.
§ 2634
§ 2634. Prior and pending proceedings
For purposes of subchapters I and II, and this subchapter, proceedings commenced by State regulatory authorities (with respect to electric utilities for which it has ratemaking authority) and nonregulated electric utilities before November 9, 1978, and actions taken before such date in such proceedings shall be treated as complying with the requirements of subchapters I and II, and this subchapter if such proceedings and actions substantially conform to such requirements. For purposes of subchapters I and II, and this subchapter, any such proceeding or action commenced before November 9, 1978, but not completed before such date, shall comply with the requirements of subchapters I and II, and this subchapter, to the maximum extent practicable, with respect to so much of such proceeding or action as takes place after such date, except as otherwise provided in section 2631(c) of this title. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of each standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021.[inserted: In the case of the standard established by paragraph (22) of section 111(d), the reference contained in this section to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (22).]