H.R. 9655 · Fair Allocation of Infrastructure Responsibility for Data Act · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
FAIR Data Act
In committee · step 2 of 5
16 U.S.C. § 2621 Consideration and determination respecting certain ratemaking standards
2 changes the bill asks for here, 2 carried out
- Carried out:
Section 111(d) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621(d)) is amended by adding at the end the following:
(22) Costs associated with covered data centers.— (A) Cost recovery relating to covered data centers.— No covered utility may recover from residential or small business electric consumers, including through rates charged by such covered utility for providing electric service, …
- Carried out:
Section 111(a) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621(a)) is amended by striking
Each State
and insertingExcept as otherwise provided in this section, each State
.
§ 2621(a)–(b)
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| § 2621. Consideration and determination respecting certain ratemaking standards | § 2621. Consideration and determination respecting certain ratemaking standards | |||
| (a) | (a) Consideration and determination | (a) Consideration and determination | ||
| [inserted: Except] [inserted: as otherwise provided in this section, each ]State regulatory authority (with respect to each electric utility for which it has ratemaking authority) and each nonregulated electric utility shall consider each standard established by subsection (d) and make a determination concerning whether or not it is appropriate to implement such standard to carry out the purposes of this chapter. For purposes of such consideration and determination in accordance with subsections (b) and (c), and for purposes of any review of such consideration and determination in any court in accordance with section 2633 of this title, the purposes of this chapter supplement otherwise applicable State law. Nothing in this subsection prohibits any State regulatory authority or nonregulated electric utility from making any determination that it is not appropriate to implement any such standard, pursuant to its authority under otherwise applicable State law. | ||||
| (b) | (b) Procedural requirements for consideration and determination | (b) Procedural requirements for consideration and determination | ||
| (b)(1) | (1) | (1) | ||
| The consideration referred to in subsection (a) shall be made after public notice and hearing. The determination referred to in subsection (a) shall be— | The consideration referred to in subsection (a) shall be made after public notice and hearing. The determination referred to in subsection (a) shall be— |
§ 2621(d)Establishment(21)–(22)
(b)(1)(A)–(d)(21)(B) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (21)(C) | (C) | (C) | ||
| accelerate third-party investment in electric vehicle charging for light-, medium-, and heavy-duty vehicles; and | accelerate third-party investment in electric vehicle charging for light-, medium-, and heavy-duty vehicles; and | |||
| (21)(D) | (D) | (D) | ||
| appropriately recover the marginal costs of delivering electricity to electric vehicles and electric vehicle charging infrastructure. | appropriately recover the marginal costs of delivering electricity to electric vehicles and electric vehicle charging infrastructure. | |||
| (22) | (22) [inserted: Costs associated with covered data centers.—] | |||
| (22)(A) | (A) [inserted: Cost recovery relating to covered data centers.—] | |||
| [inserted: No covered utility may recover from residential or small business electric consumers, including through rates charged by such covered utility for providing electric service, any costs of the covered utility associated with covered data centers, including any costs associated with any upgrade made to the generation, transmission, or distribution facilities of the electric grid in order to meet the demand for electric energy from covered data centers.] | ||||
| (22)(B) | (B) [inserted: Definitions.—] | |||
| [inserted: In this paragraph:] | ||||
| (22)(B)(i) | (i) [inserted: Covered utility.—] | |||
| [inserted: The term “covered utility” means a State regulated electric utility that is investor owned.] | ||||
| (22)(B)(ii) | (ii) [inserted: Covered data center.—] | |||
| [inserted: The term “covered data center” means a facility, or an aggregation of facilities at a single site, with respect to which the peak demand of such facility or such aggregation of facilities exceeds 75 megawatts, that primarily contain electronic equipment used to process, store, transmit, or host digital information and the electrical, mechanical, and environmental control equipment to maintain the proper conditions for the operation of electronic equipment.] | ||||
16 U.S.C. § 2622 Obligations to consider and determine
4 changes the bill asks for here, 3 carried out
- Carried out:
in subsection (b), by adding at the end the following:
(9) (A) Not later than 6 months after the date of enactment of this paragraph, each State regulatory authority (with respect to each covered utility (as defined in paragraph (22) of section 111(d)) for which the State has ratemaking authority) shall commence consideration under …
- Carried out:
by striking
subsection (b)(2)
and insertingsubsection (b)
; and - Not carried out:
by inserting
Each State regulatory authority (with respect to each covered utility (as defined in paragraph (22) of section 111(d)) for which it has ratemaking authority) shall undertake the consideration, and make the determination, referred to in section 111 with respect to the standard established by paragraph (22) of section 111(d) in the first rate proceeding commenced after the date three years after the date of enactment of this sentence respecting the rates of such covered utility if such State regulatory authority has not, before such date, complied with subsection (b) with respect to such standard.
afterparagraph (21).
; and“paragraph (21).” isn't in § 2622(c) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“paragraph (21).” not found in /us/usc/t16/s2622/c - Carried out:
by adding at the end the following:
(i) Other prior State actions.— Subsections (b) and (c) shall not apply to the standard established by paragraph (22) of section 111(d) in the case of a covered utility (as defined in paragraph (22) of section 111(d)) in a State if, before the date of enactment of this …
§ 2622(b)–(d)
Start of § 2622 to (b)(8) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (b)(8)(A) | (A) | (A) | ||
| Not later than 1 year after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 2621 of this title, or set a hearing date for consideration, with respect to the standard established by paragraph (21) of section 2621(d) of this title. | Not later than 1 year after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 2621 of this title, or set a hearing date for consideration, with respect to the standard established by paragraph (21) of section 2621(d) of this title. | |||
| (b)(8)(B) | (B) | (B) | ||
| Not later than 2 years after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 2621 of this title with respect to the standard established by paragraph (21) of section 2621(d) of this title. | Not later than 2 years after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 2621 of this title with respect to the standard established by paragraph (21) of section 2621(d) of this title. | |||
| (b)(9) | (9) [inserted: ] | |||
| (b)(9)(A) | (A) [inserted: ] | |||
| [inserted: Not later than 6 months after the date of enactment of this paragraph, each State regulatory authority (with respect to each covered utility (as defined in paragraph (22) of section 111(d)) for which the State has ratemaking authority) shall commence consideration under section 111, or set a hearing date for consideration, with respect to the standard established by such paragraph (22) of section 111(d).] | ||||
| (b)(9)(B) | (B) [inserted: ] | |||
| [inserted: Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each covered utility (as defined in paragraph (22) of section 111(d)) for which the State has ratemaking authority) shall complete the consideration and make the determination under section 111 with respect to the standard established by such paragraph (22) of section 111(d).] | ||||
| (c) | (c) Failure to comply | (c) Failure to comply | ||
| Each State regulatory authority (with respect to each electric utility for which it has ratemaking authority) and each nonregulated electric utility shall undertake the consideration, and make the determination, referred to in section 2621 of this title with respect to each standard established by section 2621(d) of this title in the first rate proceeding commenced after the date three years after November 9, 1978, respecting the rates of such utility if such State regulatory authority or nonregulated electric utility has not, before such date, complied with subsection (b) | Each State regulatory authority (with respect to each electric utility for which it has ratemaking authority) and each nonregulated electric utility shall undertake the consideration, and make the determination, referred to in section 2621 of this title with respect to each standard established by section 2621(d) of this title in the first rate proceeding commenced after the date three years after November 9, 1978, respecting the rates of such utility if such State regulatory authority or nonregulated electric utility has not, before such date, complied with subsection (b) with respect to such standard. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standards established by paragraphs (16) through (19) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to December 19, 2007. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021. | |||
| (d) | (d) Prior State actions relating to standard under certain paragraphs of section 2621(d) | (d) Prior State actions relating to standard under certain paragraphs of section 2621(d) | ||
| Subsections (b) and (c) of this section shall not apply to the standards established by paragraphs (11) through (13) and paragraphs (16) through (19) of section 2621(d) of this title in the case of any electric utility in a State if, before August 8, 2005— | Subsections (b) and (c) of this section shall not apply to the standards established by paragraphs (11) through (13) and paragraphs (16) through (19) of section 2621(d) of this title in the case of any electric utility in a State if, before August 8, 2005— | |||
| (d)(1) | (1) | (1) | ||
| the State has implemented for such utility the standard concerned (or a comparable standard); | the State has implemented for such utility the standard concerned (or a comparable standard); | |||
§ 2622(h)–(i)
(d)(2)–(h)(1) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (h)(2) | (2) | (2) | ||
| the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or | the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or | |||
| (h)(3) | (3) | (3) | ||
| the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility during the 3-year period ending on November 15, 2021. | the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility during the 3-year period ending on November 15, 2021. | |||
| (i) | (i) [inserted: Other prior State actions.—] | |||
| [inserted: Subsections (b) and (c) shall not apply to the standard established by paragraph (22) of section 111(d) in the case of a covered utility (as defined in paragraph (22) of section 111(d)) in a State if, before the date of enactment of this subsection—] | ||||
| (i)(1) | (1) [inserted: ] | |||
| [inserted: the State has implemented for the covered utility the standard (or a comparable standard);] | ||||
| (i)(2) | (2) [inserted: ] | |||
| [inserted: the State regulatory authority for the State has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the covered utility; or] | ||||
| (i)(3) | (3) [inserted: ] | |||
| [inserted: the State legislature has voted on the implementation of the standard (or a comparable standard) for the covered utility during the 3-year period ending on that date of enactment.] | ||||
16 U.S.C. § 2634 Prior and pending proceedings
The bill's words for this section
- Not carried out:
Section 124 of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2634) is amended by inserting
For purposes of subtitle A and B, and this subtitle, proceedings commenced by State regulatory authorities (with respect to covered utilities (as defined in paragraph (22) of section 111(d)) for which it has ratemaking authority) before the date of the enactment of this sentence and actions taken before such date in such proceedings shall be treated as complying with the requirements of subtitles A and B, and this subtitle, if such proceedings and actions substantially conform to such requirements. For purposes of subtitles A and B, and this subtitle, any such proceeding or action commenced before the date of enactment of this sentence, but not completed before such date, shall comply with the requirements of subtitles A and B, and this subtitle, to the maximum extent practicable, with respect to so much of such proceeding or action as takes place after such date, except as otherwise provided in section 121(c).
afterparagraph (21).
.“paragraph (21).” isn't in § 2634 in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“paragraph (21).” not found in /us/usc/t16/s2634
§ 2634
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| § 2634. Prior and pending proceedings | § 2634. Prior and pending proceedings | |||
| For purposes of subchapters I and II, and this subchapter, proceedings commenced by State regulatory authorities (with respect to electric utilities for which it has ratemaking authority) and nonregulated electric utilities before November 9, 1978, and actions taken before such date in such proceedings shall be treated as complying with the requirements of subchapters I and II, and this subchapter if such proceedings and actions substantially conform to such requirements. For purposes of subchapters I and II, and this subchapter, any such proceeding or action commenced before November 9, 1978, but not completed before such date, shall comply with the requirements of subchapters I and II, and this subchapter, to the maximum extent practicable, with respect to so much of such proceeding or action as takes place after such date, except as otherwise provided in section 2631(c) of this title. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of each standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. | For purposes of subchapters I and II, and this subchapter, proceedings commenced by State regulatory authorities (with respect to electric utilities for which it has ratemaking authority) and nonregulated electric utilities before November 9, 1978, and actions taken before such date in such proceedings shall be treated as complying with the requirements of subchapters I and II, and this subchapter if such proceedings and actions substantially conform to such requirements. For purposes of subchapters I and II, and this subchapter, any such proceeding or action commenced before November 9, 1978, but not completed before such date, shall comply with the requirements of subchapters I and II, and this subchapter, to the maximum extent practicable, with respect to so much of such proceeding or action as takes place after such date, except as otherwise provided in section 2631(c) of this title. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of each standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. |