Title 10 · Armed ForcesThe military
Became law December 18, 2025 (Pub. L. 119-60): what it changed in 10 U.S.C. § 4211
S. 1071 · National Defense Authorization Act for Fiscal Year 2026 · Enrolled The final text both chambers passed, sent to the President to sign. If signed, it becomes law.
Became law as Public Law 119-60
Shown against the Code as it stood just before the law (current through Pub. L. 119-36, September 5, 2025): words it removed and words it added are marked.
10 U.S.C. § 4211 Acquisition strategy
7 changes the bill asks for here, 5 carried out
- Carried out:
in subsection (a), by striking
milestone
; - Not carried out:
in subsection (b), by striking the term
milestone
each place it appears;We can't read how this instruction is worded yet, so it isn't shown in the text.
Technical detail
no-pattern: striking the term “ milestone ” each place it appears; - Not carried out:
in matter preceding subparagraph (A), by striking the term
milestone
each place it appears;We can't read how this instruction is worded yet, so it isn't shown in the text.
Technical detail
no-pattern: in matter preceding subparagraph (X), by striking the term “ milestone ” each place it appears; - Carried out:
by amending subparagraph (A) to read as follows:
(A) the strategy clearly describes the proposed business case and capability management approach for the program or system, and to the maximum extent practicable, describes how capability requirements will be met through delivery of such program or system;; and
- Carried out:
in subparagraph (B), by striking
how the strategy is designed to be implemented with available resources, such as time, funding, and management capacity
and insertingthe resources, such as time, funding, and management capacity, necessary to meet capability requirements
; and - Carried out:
by amending paragraph (2) to read as follows:
(2) Each strategy shall, where appropriate, consider the following:(A) An approach that delivers required capabilities in increments, each depending on available mature technology, and that recognizes up front the need for future capability improvements or transitions to …
- Carried out:
by striking subsections (d) and (e) and inserting the following new subsections:
(d) Review.—The decision authority shall review and approve, as appropriate, the acquisition strategy for a major defense acquisition program or major system prior to the acquisition decision memorandum and ensure that the strategy is updated at regular intervals to incorporate …
§ 4211(a)–(e)
§ 4211. Acquisition strategy
(a) Acquisition Strategy Required.— There shall be an acquisition strategy for each major defense acquisition program and each major system approved by a [struck: milestone ]decision authority.
(b) Responsible Official.— For each acquisition strategy required by subsection (a), the Under Secretary of Defense for Acquisition and Sustainment, or the milestone decision authority, when the milestone decision authority is the service acquisition executive of the military department that is managing the program, is responsible for issuing and maintaining the requirements for—
(1) the content of the strategy; and
(2) the review and approval process for the strategy.
(c) Considerations.—
(1) In issuing requirements for the content of an acquisition strategy for a major defense acquisition program or major system, the Under Secretary, or the milestone decision authority, when the milestone decision authority is the service acquisition executive of the military department that is managing the program, shall ensure that—
(A) the strategy clearly describes the proposed [struck: top-level ]business [inserted: case ]and [struck: technical][inserted: capability] management approach for the program or system, [struck: in][inserted: and] [struck: sufficient detail ]to [struck: allow ]the [struck: milestone][inserted: maximum] [struck: decision][inserted: extent] [struck: authority][inserted: practicable,] [struck: to][inserted: describes] [struck: assess][inserted: how] [struck: the][inserted: capability] [struck: viability][inserted: requirements] [struck: of][inserted: will] [struck: the][inserted: be] [struck: proposed][inserted: met] [struck: approach,][inserted: through] [struck: the][inserted: delivery] [struck: method ]of [struck: implementing][inserted: such] [struck: laws and policies, and ]program [struck: objectives][inserted: or system];
(B) the strategy contains a clear explanation of [struck: how ]the [struck: strategy is designed to be implemented with available ]resources, such as time, funding, and management capacity[inserted: , necessary to meet capability requirements];
(C) the strategy is tailored to address program requirements and constraints; and
(D) the strategy considers the items listed in paragraph (2).
(2) Each strategy shall, where appropriate, consider the following:
(A) An approach that delivers required [struck: capability][inserted: capabilities] in increments, each depending on available mature technology, and that recognizes up front the need for future capability improvements[inserted: or transitions to alternative end items through use of continuous competition].
(B) [struck: Acquisition][inserted: Requirements] [struck: approach][inserted: related to logistics], [struck: including][inserted: maintenance,] [struck: industrial][inserted: and] [struck: base][inserted: sustainment] [struck: considerations][inserted: in] [inserted: accordance with sections 2464 and 2466 of this title, and the acquisition of technical data, computer software, and associated licenses, to enable such requirements ]in accordance with [struck: section][inserted: sections] [struck: 4820][inserted: 3771] [inserted: through 3775 ]of this title.
(C) [struck: Risk][inserted: A] [struck: management][inserted: process for collaborative interaction and market research with the science and technology community], including [struck: such][inserted: Department] [struck: methods][inserted: of] [struck: as][inserted: Defense] [struck: competitive][inserted: science] [struck: prototyping][inserted: and] [struck: at][inserted: technology] [struck: the][inserted: reinvention] [struck: system][inserted: laboratories], [struck: subsystem][inserted: government innovation cells], [struck: or][inserted: academia,] [struck: component][inserted: small] [struck: level][inserted: businesses, nontraditional defense contractors, and other contractors].
(D) [struck: Business][inserted: Identification] [struck: strategy,][inserted: of] [struck: including][inserted: enterprise-wide] [struck: measures][inserted: designs] [struck: to][inserted: and] [struck: ensure][inserted: standards] [struck: competition][inserted: in] [struck: at][inserted: support] [struck: the][inserted: of] [struck: system][inserted: an] [struck: and][inserted: architecture] [struck: subsystem][inserted: that] [struck: level][inserted: provides] [struck: throughout][inserted: for] [struck: the][inserted: an] [struck: life-cycle][inserted: integrated] [inserted: suite ]of [struck: the][inserted: capabilities] [struck: program][inserted: that] [struck: or][inserted: focuses] [struck: system][inserted: on] [struck: in][inserted: simplicity] [struck: accordance][inserted: of] [struck: with][inserted: implementation] [struck: section][inserted: and] [struck: 4324][inserted: speed] of [struck: this title][inserted: delivery].
(E) [inserted: Overarching roadmaps that create integrated strategic schedules of legacy systems and new capabilities.]
[struck: Contracting strategy, including—]
[struck: (i)] [struck: contract type and how the type selected relates to level of program risk in each acquisition phase;]
[struck: (ii)] [struck: how the plans for the program or system to reduce risk enable the use of fixed-price elements in subsequent contracts and the timing of the use of those fixed price elements;]
[struck: (iii)] [struck: market research; and]
[struck: (iv)] [struck: consideration of small business participation.]
(F) [struck: Intellectual][inserted: A] [struck: property][inserted: contracting] strategy [struck: in][inserted: that] [struck: accordance][inserted: develops] [inserted: long-term partnerships ]with [struck: sections][inserted: multiple] [struck: 3771][inserted: companies] [struck: through][inserted: to] [struck: 3775][inserted: actively] [inserted: contribute to architectures, development, production, and sustainment across the capabilities to be developed by decomposing large systems into smaller sets ]of [struck: this][inserted: projects] [struck: title][inserted: across time and technical component].
(G) [struck: International][inserted: An] [struck: involvement][inserted: assignment of roles and responsibilities of key personnel of the acquisition workforce], [inserted: identification of external stakeholder dependencies, and the need for subject matter expert inputs at critical points in the program, ]including [struck: foreign][inserted: the] [struck: military][inserted: need] [struck: sales][inserted: for] [inserted: special hiring authority or advisory ]and [struck: cooperative][inserted: assistance] [struck: opportunities][inserted: services], in [struck: accordance][inserted: order] [struck: with][inserted: to] [struck: section][inserted: deliver] [struck: 2350a][inserted: the] [struck: of][inserted: desired] [struck: this title][inserted: capabilities].
(H) [struck: Multiyear][inserted: A] [struck: procurement][inserted: process] [struck: in][inserted: of] [struck: accordance][inserted: testing] [inserted: and experimentation ]with [struck: section][inserted: the] [struck: 3501][inserted: test] [inserted: community and end users to ensure continuous user feedback, acceptance, and development ]of [struck: this][inserted: concepts] [struck: title][inserted: of operations].
[struck: (I)] [struck: Integration of current intelligence assessments into the acquisition process.]
[struck: (J)] [struck: Requirements related to logistics, maintenance, and sustainment in accordance with sections 2464 and 2466 of this title.]
(d) Review.— [inserted: The decision authority shall review and approve, as appropriate, the acquisition strategy for a major defense acquisition program or major system prior to the acquisition decision memorandum and ensure that the strategy is updated at regular intervals to incorporate significant changes to program requirements, resourcing, or acquisition decisions.]
[struck: (1)] [struck: The milestone decision authority shall review and approve, as appropriate, the acquisition strategy for a major defense acquisition program or major system at each of the following times:]
[struck: (A)] [struck: Milestone A approval.]
[struck: (B)] [struck: The decision to release the request for proposals for development of the program or system.]
[struck: (C)] [struck: Milestone B approval.]
[struck: (D)] [struck: Each subsequent milestone.]
[struck: (E)] [struck: Review of any decision to enter into full-rate production.]
[struck: (F)] [struck: When there has been—]
[struck: (i)] [struck: a significant change to the cost of the program or system;]
[struck: (ii)] [struck: a critical change to the cost of the program or system;]
[struck: (iii)] [struck: a significant change to the schedule of the program or system; or]
[struck: (iv)] [struck: a significant change to the performance of the program or system.]
[struck: (G)] [struck: Any other time considered relevant by the milestone decision authority.]
[struck: (2)] [struck: If the milestone decision authority revises an acquisition strategy for a program or system because of a change described in paragraph (1)(F), the milestone decision authority shall provide notice of the revision to the congressional defense committees.]
(e) [struck: Definitions][inserted: Decision Authority Defined].— [inserted: In this section, the term “decision authority”, with respect to a major defense acquisition program or major system, means the official within the Department of Defense designated with the overall responsibility and authority for acquisition decisions for the program or system, including authority to approve entry of the program or system into the next phase of the acquisition process.]
[struck: In this section:]
[struck: (1)] [struck: The term “Milestone A approval” means a decision to enter into technology maturation and risk reduction pursuant to guidance prescribed by the Secretary of Defense for the management of Department of Defense acquisition programs.]
[struck: (2)] [struck: The term “Milestone B approval” has the meaning provided in section 4172(e)(7) of this title.]
[struck: (3)] [struck: The term “milestone decision authority”, with respect to a major defense acquisition program or major system, means the official within the Department of Defense designated with the overall responsibility and authority for acquisition decisions for the program or system, including authority to approve entry of the program or system into the next phase of the acquisition process.]
[struck: (4)] [struck: The term “management capacity”, with respect to a major defense acquisition program or major system, means the capacity to manage the program or system through the use of highly qualified organizations and personnel with appropriate experience, knowledge, and skills.]
[struck: (5)] [struck: The term “significant change to the cost”, with respect to a major defense acquisition program or major system, means a significant cost growth threshold, as that term is defined in section 4371(a)(2) of this title.]
[struck: (6)] [struck: The term “critical change to the cost”, with respect to a major defense acquisition program or major system, means a critical cost growth threshold, as that term is defined in section 4371(a)(3) of this title.]
[struck: (7)] [struck: The term “significant change to the schedule”, with respect to a major defense acquisition program or major system, means any schedule delay greater than six months in a reported event.]