Title 50 · War and National DefenseThe military
Became law December 18, 2025 (Pub. L. 119-60): what it changed in 50 U.S.C. § 2753
S. 1071 · National Defense Authorization Act for Fiscal Year 2026 · Enrolled The final text both chambers passed, sent to the President to sign. If signed, it becomes law.
Became law as Public Law 119-60
Shown against the Code as it stood just before the law (current through Pub. L. 119-36, September 5, 2025): words it removed and words it added are marked.
50 U.S.C. § 2753
5 changes the bill asks for here, 5 carried out
- Carried out:
in paragraph (1)(A), in the first sentence, by inserting
prior to entry into Phase 6.4 or Phase 4, as appropriate
afterAdministration
; and - Carried out:
in paragraph (2)(A), by inserting
prior to entry into Phase 6.4
afterproject
; - Carried out:
by redesignating subparagraphs (B) and (C) as subparagraphs (C) and (D), respectively; and
- Carried out:
by inserting after subparagraph (A) the following new subparagraph (B):(B) a review of the revised baseline has been conducted by the Director of Cost Estimating and Program Evaluation of the National Nuclear Security Administration, consistent with section 3221(d)(1)(F) of the National Nuclear Security Administration Act (50 U.S.C. 2411(d)(1)(F)).; and
- Carried out:
in subsection (d)(1), by inserting
and the results of the review conducted by the Director of Cost Estimating and Program Evaluation under subsection (c)(2)(B)
aftersubsection (c)(2)
.
§ 2753(a)
§ 2753. Notification of cost overruns for certain Department of Energy projects
(a) Establishment of cost and schedule baselines
(1) Stockpile life extension and new nuclear weapon program projects
(A) In general The Administrator shall establish a cost and schedule baseline for each nuclear stockpile life extension or new nuclear weapon program project of the Administration[inserted: prior to entry into Phase 6].[inserted: 4] [inserted: or Phase 4, as appropriate. ]In addition to the requirement under subparagraph (B), the cost and schedule baseline of a nuclear stockpile life extension or new nuclear weapon program project established under this subparagraph shall be the cost and schedule as described in the first Selected Acquisition Report submitted under section 2537(a) of this title for the project.
(B) Per unit cost The cost baseline developed under subparagraph (A) shall include, with respect to each life extension project,1 an estimated cost for each warhead in the project.
(C) Notification to congressional defense committees Not later than 30 days after establishing a cost and schedule baseline under subparagraph (A), the Administrator shall submit the cost and schedule baseline to the congressional defense committees.
(2) Major alteration projects
(A) In general The Administrator shall establish a cost and schedule baseline for each major alteration project[inserted: prior to entry into Phase 6].[inserted: 4.]
(B) Per unit cost The cost baseline developed under subparagraph (A) shall include, with respect to each major alteration project, an estimated cost for each warhead in the project.
(C) Notification to congressional defense committees Not later than 30 days after establishing a cost and schedule baseline under subparagraph (A), the Administrator shall submit the cost and schedule baseline to the congressional defense committees.
§ 2753(c)Notification of determination with respect to termination or continuation of projects and root cause analyses(2)–(3)
(a)(2)(D)–(c)(1) unchanged ·
(2) if the project will be continued, certify to the congressional defense committees that—
(A) a revised cost and schedule baseline has been established for the project and, in the case of a stockpile life extension or new nuclear weapon program project referred to in subparagraph (A) or (B) of subsection (a)(1) or a major alteration project referred to in subsection (a)(2), a revised estimate of the cost for each warhead in the project has been made;
(B) [inserted: a review of the revised baseline has been conducted by the Director of Cost Estimating and Program Evaluation of the National Nuclear Security Administration, consistent with section 3221(d)(1)(F) of the National Nuclear Security Administration Act (50 U.S.C. 2411(d)(1)(F)).]
[struck: (B)] [inserted: (C)] the continuation of the project is necessary to the mission of the Department of Energy and there is no alternative to the project that would meet the requirements of that mission; and
[struck: (C)] [inserted: (D)] a management structure is in place adequate to manage and control the cost and schedule of the project; and
(3) submit to the congressional defense committees an assessment of the root cause or causes of the growth in the total cost of the project, including the contribution of any shortcomings in cost, schedule, or performance of the program, including the role, if any, of—
(A) unrealistic performance expectations;
§ 2753(d)Applicability of requirements to revised cost and schedule baselines(1)–(2)
(c)(3)(B)–(H) unchanged ·
(d) Applicability of requirements to revised cost and schedule baselines A revised cost and schedule baseline established under subsection (c) shall—
(1) be submitted to the congressional defense committees with the certification submitted under subsection (c)(2)[inserted: and the results of the review conducted by the Director of Cost Estimating and Program Evaluation under subsection (c)(2)(B)]; and
(2) be subject to the notification requirements of subsections (b) and (c) in the same manner and to the same extent as a cost and schedule baseline established under subsection (a).