15 U.S.C. § 717b Exportation or importation of natural gas; LNG terminals

+1 −1Shown
More for 15 U.S.C. § 717b
Read § 717bOnly this section
1 change the bill asks for here, 1 carried out
  1. Carried out:

    Section 3(c) of the Natural Gas Act (15 U.S.C. 717b(c)) is amended by adding at the end the following: In the case of an application for the importation of natural gas from, or the exportation of natural gas to, Canada or Mexico, the Commission shall grant the application not later than 30 days after the date on which the Commission receives the complete application..

§ 717b(b)–(d)

Start of § 717b to (b)(1) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(b)(2)(2) (2)
the Commission shall not, on the basis of national origin, treat any such imported natural gas on an unjust, unreasonable, unduly discriminatory, or preferential basis.the Commission shall not, on the basis of national origin, treat any such imported natural gas on an unjust, unreasonable, unduly discriminatory, or preferential basis.
(c)(c) Expedited application and approval process(c) Expedited application and approval process
For purposes of subsection (a), the importation of the natural gas referred to in subsection (b), or the exportation of natural gas to a nation with which there is in effect a free trade agreement requiring national treatment for trade in natural gas, shall be deemed to be consistent with the public interest, and applications for such importation or exportation shall be granted without modification or delay.For purposes of subsection (a), the importation of the natural gas referred to in subsection (b), or the exportation of natural gas to a nation with which there is in effect a free trade agreement requiring national treatment for trade in natural gas, shall be deemed to be consistent with the public interest, and applications for such importation or exportation shall be granted without modification or delay.[inserted: In the case of an application for the importation of natural gas from, or the exportation of natural gas to, Canada or Mexico, the Commission shall grant the application not later than 30 days after the date on which the Commission receives the complete application.]
(d)(d) Construction with other laws(d) Construction with other laws
Except as specifically provided in this chapter, nothing in this chapter affects the rights of States under—Except as specifically provided in this chapter, nothing in this chapter affects the rights of States under—
(d)(1)(1) (1)
the Coastal Zone Management Act of 1972 (16 U.S.C. 1451 et seq.);the Coastal Zone Management Act of 1972 (16 U.S.C. 1451 et seq.);

Rest of § 717b unchanged

16 U.S.C. § 824a Interconnection and coordination of facilities; emergencies; transmission to foreign countries

+1 −2Shown
More for 16 U.S.C. § 824a
Read § 824aOnly this section
2 changes the bill asks for here, 2 carried out
  1. Carried out:

    Section 202(e) of the Federal Power Act (16 U.S.C. 824a(e)) is repealed.

  2. Carried out:

    Section 202(f) of the Federal Power Act (16 U.S.C. 824a(f)) is amended by striking insofar as such State regulation does not conflict with the exercise of the Commission's powers under or relating to subsection (e).

§ 824a(d)–(g)

Start of § 824a to (c)(5) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(d)(d) Temporary connection during emergency by persons without jurisdiction of Commission(d) Temporary connection during emergency by persons without jurisdiction of Commission
During the continuance of any emergency requiring immediate action, any person or municipality engaged in the transmission or sale of electric energy and not otherwise subject to the jurisdiction of the Commission may make such temporary connections with any public utility subject to the jurisdiction of the Commission or may construct such temporary facilities for the transmission of electric energy in interstate commerce as may be necessary or appropriate to meet such emergency, and shall not become subject to the jurisdiction of the Commission by reason of such temporary connection or temporary construction: Provided, That such temporary connection shall be discontinued or such temporary construction removed or otherwise disposed of upon the termination of such emergency: Provided further, That upon approval of the Commission permanent connections for emergency use only may be made hereunder.During the continuance of any emergency requiring immediate action, any person or municipality engaged in the transmission or sale of electric energy and not otherwise subject to the jurisdiction of the Commission may make such temporary connections with any public utility subject to the jurisdiction of the Commission or may construct such temporary facilities for the transmission of electric energy in interstate commerce as may be necessary or appropriate to meet such emergency, and shall not become subject to the jurisdiction of the Commission by reason of such temporary connection or temporary construction: Provided, That such temporary connection shall be discontinued or such temporary construction removed or otherwise disposed of upon the termination of such emergency: Provided further, That upon approval of the Commission permanent connections for emergency use only may be made hereunder.
(e)(e) Transmission of electric energy to foreign country(e) Transmission of electric energy to foreign country
[struck: After six months from August 26, 1935, no person shall transmit any electric energy from the United States to a foreign country without first having secured an order of the Commission authorizing it to do so. The Commission shall issue such order upon application unless, after opportunity for hearing, it finds that the proposed transmission would impair the sufficiency of electric supply within the United States or would impede or tend to impede the coordination in the public interest of facilities subject to the jurisdiction of the Commission. The Commission may by its order grant such application in whole or in part, with such modifications and upon such terms and conditions as the Commission may find necessary or appropriate, and may from time to time, after opportunity for hearing and for good cause shown, make such supplemental orders in the premises as it may find necessary or appropriate.]
(f)(f) Transmission or sale at wholesale of electric energy; regulation(f) Transmission or sale at wholesale of electric energy; regulation
The ownership or operation of facilities for the transmission or sale at wholesale of electric energy which is (a) generated within a State and transmitted from the State across an international boundary and not thereafter transmitted into any other State, or (b) generated in a foreign country and transmitted across an international boundary into a State and not thereafter transmitted into any other State, shall not make a person a public utility subject to regulation as such under other provisions of this subchapter. The State within which any such facilities are located may regulate any such transaction [struck: insofar as such State regulation does not conflict with the exercise of the Commission’s powers under or relating to subsection (e)].The ownership or operation of facilities for the transmission or sale at wholesale of electric energy which is (a) generated within a State and transmitted from the State across an international boundary and not thereafter transmitted into any other State, or (b) generated in a foreign country and transmitted across an international boundary into a State and not thereafter transmitted into any other State, shall not make a person a public utility subject to regulation as such under other provisions of this subchapter. The State within which any such facilities are located may regulate any such transaction .
(g)(g) Continuance of service(g) Continuance of service
In order to insure continuity of service to customers of public utilities, the Commission shall require, by rule, each public utility to—In order to insure continuity of service to customers of public utilities, the Commission shall require, by rule, each public utility to—
(g)(1)(1) (1)
report promptly to the Commission and any appropriate State regulatory authorities any anticipated shortage of electric energy or capacity which would affect such utility’s capability of serving its wholesale customers,report promptly to the Commission and any appropriate State regulatory authorities any anticipated shortage of electric energy or capacity which would affect such utility’s capability of serving its wholesale customers,

Rest of § 824a unchanged

16 U.S.C. § 824a–4 Seasonal diversity electricity exchange

+1 −1Shown
More for 16 U.S.C. § 824a–4
Read § 824a–4Only this section
1 change the bill asks for here, 1 carried out
  1. Carried out:

    Section 602(b) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 824a–4(b)) is amended by striking the Commission has conducted hearings and made the findings required under section 202(e) of the Federal Power Act and all that follows through the period at the end and inserting the Secretary has conducted hearings and finds that the proposed transmission facilities would not impair the sufficiency of electric supply within the United States or would not impede or tend to impede the coordination in the public interest of facilities subject to the jurisdiction of the Secretary..

§ 824a–4(a)–(d)

Start of § 824a–4 to (a)(1)(C) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(a)(2)(2) (2)
after consultation with the Secretary of the Interior and the heads of other affected Federal agencies, that the Secretary of the Interior and the heads of such,1 other agencies concur in writing in the location of such portion of the transmission facilities as crosses Federal land under the jurisdiction of such Secretary or such other Federal agency, as the case may be.after consultation with the Secretary of the Interior and the heads of other affected Federal agencies, that the Secretary of the Interior and the heads of such,1 other agencies concur in writing in the location of such portion of the transmission facilities as crosses Federal land under the jurisdiction of such Secretary or such other Federal agency, as the case may be.
(a)The Secretary shall provide to any State such cooperation and technical assistance as the State may request and as he determines appropriate in the selection of a transmission route. If the transmission route approved by any State does not appear to be feasible and in the public interest, the Secretary shall encourage such State to review such route and to develop a route that is feasible and in the public interest. Any exercise by the Secretary of the power of eminent domain under this section shall be in accordance with other applicable provisions of Federal law. The Secretary shall provide public notice of his intention to acquire any right-of-way before exercising such power of eminent domain with respect to such right-of-way.The Secretary shall provide to any State such cooperation and technical assistance as the State may request and as he determines appropriate in the selection of a transmission route. If the transmission route approved by any State does not appear to be feasible and in the public interest, the Secretary shall encourage such State to review such route and to develop a route that is feasible and in the public interest. Any exercise by the Secretary of the power of eminent domain under this section shall be in accordance with other applicable provisions of Federal law. The Secretary shall provide public notice of his intention to acquire any right-of-way before exercising such power of eminent domain with respect to such right-of-way.
(b)(b) Permit(b) Permit
Notwithstanding any transfer of functions under the first sentence of section 301(b) of the Department of Energy Organization Act [42 U.S.C. 7151(b)], no permit referred to in subsection (a)(1)(B) may be issued unless the [struck: Commission] has conducted hearings and [struck: made] [struck: the] [struck: findings required under section 202(e) of ]the [struck: Federal] [struck: Power] [struck: Act] [struck: [16] [struck: U.S.C.] [struck: 824a(e)]] [struck: and under ]the [struck: applicable] [struck: execution order respecting the construction, operation, maintenance, or connection at the borders ]of [struck: the United States of facilities for the transmission of ]electric [struck: energy] [struck: between] the United States [struck: and] [struck: a] [struck: foreign] [struck: country.] [struck: Any] [struck: finding] [struck: of] the [struck: Commission] [struck: under an applicable executive order referred to ]in [struck: this] [struck: subsection] [struck: shall] [struck: be treated for purposes ]of [struck: judicial] [struck: review] [struck: as] [struck: an] [struck: order] [struck: issued under section 202(e) ]of the [struck: Federal Power Act].Notwithstanding any transfer of functions under the first sentence of section 301(b) of the Department of Energy Organization Act [42 U.S.C. 7151(b)], no permit referred to in subsection (a)(1)(B) may be issued unless the [inserted: Secretary] has conducted hearings and [inserted: finds] [inserted: that] the [inserted: proposed] [inserted: transmission] [inserted: facilities] [inserted: would] [inserted: not] [inserted: impair] the [inserted: sufficiency] of electric [inserted: supply] [inserted: within] the United States [inserted: or] [inserted: would] [inserted: not] [inserted: impede] [inserted: or] [inserted: tend] [inserted: to] [inserted: impede ]the [inserted: coordination] in [inserted: the] [inserted: public] [inserted: interest] of [inserted: facilities] [inserted: subject] [inserted: to] [inserted: the] [inserted: jurisdiction] of the [inserted: Secretary].
(c)(c) Timely acquisition by other means(c) Timely acquisition by other means
The Secretary may not acquire any rights-of-day2 under this section unless he determines that the holder or holders of a permit referred to in subsection (a)(1)(B) are unable to acquire such rights-of-way under State condemnation authority, or after reasonable opportunity for negotiation, without unreasonably delaying construction, taking into consideration the impact of such delay on completion of the facilities in a timely fashion.The Secretary may not acquire any rights-of-day2 under this section unless he determines that the holder or holders of a permit referred to in subsection (a)(1)(B) are unable to acquire such rights-of-way under State condemnation authority, or after reasonable opportunity for negotiation, without unreasonably delaying construction, taking into consideration the impact of such delay on completion of the facilities in a timely fashion.
(d)(d) Payments by permittees(d) Payments by permittees

Rest of § 824a–4 unchanged