- Introduced
- In committeeEnvironment and Public Works
- Passed the Senate (not yet)
- Passed the House (not yet)
- Law (not yet)
What it says
About this text
Text: Introduced The text as a member of Congress first filed it. Most bills never get further than this., (the only version so far)
This bill creates or directs, rather than amending the Code.
Its own words follow, as Congress.gov publishes them.
Sec. 1. Short title The Act may be cited as the Northwest Energy Security Act.
Sec. 2. Definitions In this Act:
(1) FCRPS The term FCRPS means those portions of the Federal Columbia River Power System that are the subject of the Supplemental Opinion.
(2) Secretaries The term Secretaries means—
(A) the Secretary of the Interior, acting through the Commissioner of Reclamation;
(B) the Secretary of Energy, acting through the Administrator of the Bonneville Power Administration; and
(C) the Secretary of the Army, acting through the Chief of Engineers.
(3) Supplemental Opinion The term Supplemental Opinion means the document entitled Columbia River System Operations Environmental Impact Statement Record of Decision and dated September 2020.
Sec. 3. Operation of FCRPS The Secretaries shall operate the FCRPS in a manner consistent with the reasonable and prudent alternative described in the Supplemental Opinion.
Sec. 4. Amendments to supplemental opinion
(a) In general Notwithstanding section 3, the Secretaries may amend portions of the Supplemental Opinion and operate the FCRPS in accordance with those amendments if all of the Secretaries determine, in the sole discretion of each Secretary, that—
(1) the amendment is necessary for public safety or transmission and grid reliability; or
(2) the actions, operations, or other requirements that the amendment would remove are no longer warranted.
(b) Restriction on amendments The process described in subsection (a) shall be the only method by which the Secretaries may operate the FCRPS in any way that is not consistent with the reasonable and prudent alternative set forth in the Supplemental Opinion.
Sec. 5. Limitation on restricting FCRPS electrical generation; clarification
(a) Restricting FCRPS electrical generation No structural modification, action, study, or engineering plan that restricts electrical generation at any FCRPS hydroelectric dam, or that limits navigation on the Snake River in the State of Washington, Oregon, or Idaho, shall proceed unless such proposal is specifically and expressly authorized by a Federal statute enacted after the date of the enactment of this Act.
(b) Clarification Nothing in this section affects or interferes with the authority of the Secretaries to conduct operation and maintenance activities or make capital improvements necessary to meet authorized project purposes of FCRPS facilities.