Changes to 49 U.S.C. § 60118

S. 2975 · Pipeline Integrity, Protection, and Enhancement for Leveraging Investments in the Nation's Energy to assure Safety Act of 2025 ·

PIPELINE Safety Act of 2025

Passed the Senate · step 3 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

49 U.S.C. § 60118 Compliance and waivers

+13 −3Shown
More for 49 U.S.C. § 60118
Read § 60118
4 changes the bill asks for here, 4 carried out
  1. Carried out:

    in subparagraph (A), by striking not inconsistent and inserting consistent;

  2. Carried out:

    in subparagraph (B), by inserting and comment after only after notice; and

  3. Carried out:

    by adding at the end the following:(C) Action on application.— Not later than 180 days after receiving an application for a waiver under this paragraph, the Secretary shall— (i) complete any applicable review relating to the application and act on the application by— (I) issuing an order granting the waiver; or …

  4. Carried out:

    by striking paragraph (3) and inserting the following:(3) Statement of reasons.— The Secretary shall state in an order issued under this subsection that is publicly posted on the website of the Pipeline and Hazardous Materials Safety Administration the reasons for granting or denying the waiver..

§ 60118(c)Waivers by Secretary.—(1)–(2)

Start of § 60118 to (b) unchanged ·

(c) Waivers by Secretary.—

(1) Nonemergency waivers.—

(A) In general.— On application of an owner or operator of a pipeline facility, the Secretary by order may waive compliance with any part of an applicable standard prescribed under this chapter with respect to such facility on terms the Secretary considers appropriate if the Secretary determines that the waiver is [struck: not][inserted: consistent] [struck: inconsistent ]with pipeline safety.

(B) Hearing.— The Secretary may act on a waiver under this paragraph only after notice and [inserted: comment and ]an opportunity for a hearing.

(C) [inserted: Action on application.—] [inserted: Not later than 180 days after receiving an application for a waiver under this paragraph, the Secretary shall—]

(i) [inserted: complete any applicable review relating to the application and act on the application by—]

(I) [inserted: issuing an order granting the waiver; or]

(II) [inserted: denying the application; or]

(ii) [inserted: inform the applicant that additional time is needed to review the application, including by providing notifications of the need for additional time at least once every 180 days until the waiver is granted or the application is denied.]

(2) Emergency waivers.—

(A) In general.— The Secretary by order may waive compliance with any part of an applicable standard prescribed under this chapter on terms the Secretary considers appropriate without prior notice and comment if the Secretary determines that—

§ 60118(c)–(e)

(c)(2)(A)(i)–(iii) unchanged ·

(B) Period of waiver.— A waiver under this paragraph may be issued for a period of not more than 60 days and may be renewed upon application to the Secretary only after notice and an opportunity for a hearing on the waiver. The Secretary shall immediately revoke the waiver if continuation of the waiver would not be consistent with the goals and objectives of this chapter.

(3) Statement of reasons.— The Secretary shall state in an order issued under this subsection [inserted: that is publicly posted on ]the [inserted: website of the Pipeline and Hazardous Materials Safety Administration the ]reasons for granting [inserted: or denying ]the waiver.

(d) Waivers by State Authorities.— If a certification under section 60105 of this title or an agreement under section 60106 of this title is in effect, the State authority may waive compliance with a safety standard to which the certification or agreement applies in the same way and to the same extent the Secretary may waive compliance under subsection (c) of this section. However, the authority must give the Secretary written notice of the waiver at least 60 days before its effective date. If the Secretary makes a written objection before the effective date of the waiver, the waiver is stayed. After notifying the authority of the objection, the Secretary shall provide a prompt opportunity for a hearing. The Secretary shall make the final decision on granting the waiver.

(e) Operator Assistance in Investigations.—

Rest of § 60118 unchanged ·

Step through the changes