Changes to the Code
S. 3682 · Power for the People Act of 2026 · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
In committee · step 2 of 5
16 U.S.C. § 2621 Consideration and determination respecting certain ratemaking standards
1 change the bill asks for here, 1 carried out
- Carried out:
Section 111(d) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621(d)) is amended by adding at the end the following:
(22) Data centers.— (A) Definitions.— In this paragraph, the terms “data center”, “data center owner or operator”, and “load interconnection request” have the meanings given those terms in section 3 of the Power for the People Act of 2026. (B) Standard.— Each State in which at …
§ 2621(d)Establishment(21)–(22)
Start of § 2621 to (d)(21)(B) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (21)(C) | (C) | (C) | ||
| accelerate third-party investment in electric vehicle charging for light-, medium-, and heavy-duty vehicles; and | accelerate third-party investment in electric vehicle charging for light-, medium-, and heavy-duty vehicles; and | |||
| (21)(D) | (D) | (D) | ||
| appropriately recover the marginal costs of delivering electricity to electric vehicles and electric vehicle charging infrastructure. | appropriately recover the marginal costs of delivering electricity to electric vehicles and electric vehicle charging infrastructure. | |||
| (22) | (22) [inserted: Data centers.—] | |||
| (22)(A) | (A) [inserted: Definitions.—] | |||
| [inserted: In this paragraph, the terms “data center”, “data center owner or operator”, and “load interconnection request” have the meanings given those terms in section 3 of the Power for the People Act of 2026.] | ||||
| (22)(B) | (B) [inserted: Standard.—] | |||
| [inserted: Each State in which at least 1 data center is located or has been proposed via load interconnection request, legal filing, or public announcement shall consider—] | ||||
| (22)(B)(i) | (i) [inserted: ] | |||
| [inserted: establishing a rate class specific to data centers to ensure that data center owners and operators are covering the full cost of the generation, transmission, and distribution upgrades necessary to serve data centers; and] | ||||
| (22)(B)(ii) | (ii) [inserted: ] | |||
| [inserted: including as requirements for the data center rate class, in addition to any other potential requirements the State chooses to examine—] | ||||
| (22)(B)(ii)(I) | (I) [inserted: ] | |||
| [inserted: minimum demand charges for data center owners and operators based on requested peak electricity demand if the monthly usage of a data center is less than its requested demand to ensure that ratepayers are not paying increased costs for generation and transmission built to serve data centers;] | ||||
| (22)(B)(ii)(II) | (II) [inserted: ] | |||
| [inserted: an extension of minimum utility contract lengths for data center customers to ensure that data center load does not leave utilities and ratepayers with stranded costs;] | ||||
| (22)(B)(ii)(III) | (III) [inserted: ] | |||
| [inserted: an increase in up-front interconnection study costs, deposit amounts, or collateral requirements for data center projects to ensure that the interconnection queue is not slowed down by projects that are unlikely to come to fruition;] | ||||
| (22)(B)(ii)(IV) | (IV) [inserted: ] | |||
| [inserted: permissible “load ramp” periods for data centers that allow data center customers to start service with a lower-than-requested capacity and gradually increase their power demand over a period of multiple years to reach their full requested capacity, subject to the condition that flexible load interconnection pursuant to this subclause does not undermine grid reliability;] | ||||
| (22)(B)(ii)(V) | (V) [inserted: ] | |||
| [inserted: a “clean transition tariff” that allows data center customers to financially support novel zero-emissions energy technologies to meet their electricity demand in cooperation with intermediaries, such as a utility company; and] | ||||
| (22)(B)(ii)(VI) | (VI) [inserted: ] | |||
| [inserted: the use of contribution in aid of construction (commonly referred to as “CIAC”) as a tool to have the data center customer pay upfront for the utility investment determined to be the responsibility of that data center.] | ||||
16 U.S.C. § 2622 Obligations to consider and determine
4 changes the bill asks for here, 4 carried out
- Carried out:
by adding at the end the following:
(9) (A) Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated electric utility shall commence consideration under section …
- Carried out:
Section 112(c) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622(c)) is amended by adding at the end the following:
In the case of the standard established by paragraph (22) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (22).
. - Carried out:
in subsection (h), in the subsection heading, by striking
Other
; and - Carried out:
by adding at the end the following:
(i) Prior State actions.— Subsections (b) and (c) shall not apply to the standard established by paragraph (22) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection— (1) the State has implemented the standard (or a …
§ 2622(b)–(d)
Start of § 2622 to (b)(8) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (b)(8)(A) | (A) | (A) | ||
| Not later than 1 year after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 2621 of this title, or set a hearing date for consideration, with respect to the standard established by paragraph (21) of section 2621(d) of this title. | Not later than 1 year after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 2621 of this title, or set a hearing date for consideration, with respect to the standard established by paragraph (21) of section 2621(d) of this title. | |||
| (b)(8)(B) | (B) | (B) | ||
| Not later than 2 years after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 2621 of this title with respect to the standard established by paragraph (21) of section 2621(d) of this title. | Not later than 2 years after November 15, 2021, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 2621 of this title with respect to the standard established by paragraph (21) of section 2621(d) of this title. | |||
| (b)(9) | (9) [inserted: ] | |||
| (b)(9)(A) | (A) [inserted: ] | |||
| [inserted: Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated electric utility shall commence consideration under section 111, or set a hearing date for consideration, with respect to the standard established by paragraph (22) of section 111(d).] | ||||
| (b)(9)(B) | (B) [inserted: ] | |||
| [inserted: Not later than 2 years after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 111 with respect to the standard established by paragraph (22) of section 111(d).] | ||||
| (c) | (c) Failure to comply | (c) Failure to comply | ||
| Each State regulatory authority (with respect to each electric utility for which it has ratemaking authority) and each nonregulated electric utility shall undertake the consideration, and make the determination, referred to in section 2621 of this title with respect to each standard established by section 2621(d) of this title in the first rate proceeding commenced after the date three years after November 9, 1978, respecting the rates of such utility if such State regulatory authority or nonregulated electric utility has not, before such date, complied with subsection (b)(2) with respect to such standard. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standards established by paragraphs (16) through (19) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to December 19, 2007. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021. | Each State regulatory authority (with respect to each electric utility for which it has ratemaking authority) and each nonregulated electric utility shall undertake the consideration, and make the determination, referred to in section 2621 of this title with respect to each standard established by section 2621(d) of this title in the first rate proceeding commenced after the date three years after November 9, 1978, respecting the rates of such utility if such State regulatory authority or nonregulated electric utility has not, before such date, complied with subsection (b)(2) with respect to such standard. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standards established by paragraphs (16) through (19) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to December 19, 2007. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this subsection to November 9, 1978, shall be deemed to be a reference to November 15, 2021.[inserted: In the case of the standard established by paragraph (22) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (22).] | |||
| (d) | (d) Prior State actions relating to standard under certain paragraphs of section 2621(d) | (d) Prior State actions relating to standard under certain paragraphs of section 2621(d) | ||
| Subsections (b) and (c) of this section shall not apply to the standards established by paragraphs (11) through (13) and paragraphs (16) through (19) of section 2621(d) of this title in the case of any electric utility in a State if, before August 8, 2005— | Subsections (b) and (c) of this section shall not apply to the standards established by paragraphs (11) through (13) and paragraphs (16) through (19) of section 2621(d) of this title in the case of any electric utility in a State if, before August 8, 2005— | |||
| (d)(1) | (1) | (1) | ||
| the State has implemented for such utility the standard concerned (or a comparable standard); | the State has implemented for such utility the standard concerned (or a comparable standard); | |||
§ 2622(g)–(i)
(d)(2)–(g)(1) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (g)(2) | (2) | (2) | ||
| the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or | the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or | |||
| (g)(3) | (3) | (3) | ||
| the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility. | the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility. | |||
| (h) | (h) | (h) prior State actions | ||
| Subsections (b) and (c) shall not apply to the standard established by paragraph (21) of section 2621(d) of this title in the case of any electric utility in a State if, before November 15, 2021— | Subsections (b) and (c) shall not apply to the standard established by paragraph (21) of section 2621(d) of this title in the case of any electric utility in a State if, before November 15, 2021— | |||
| (h)(1) | (1) | (1) | ||
| the State has implemented for the electric utility the standard (or a comparable standard); | the State has implemented for the electric utility the standard (or a comparable standard); | |||
| (h)(2) | (2) | (2) | ||
| the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or | the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or | |||
| (h)(3) | (3) | (3) | ||
| the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility during the 3-year period ending on November 15, 2021. | the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility during the 3-year period ending on November 15, 2021. | |||
| (i) | (i) [inserted: Prior State actions.—] | |||
| [inserted: Subsections (b) and (c) shall not apply to the standard established by paragraph (22) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection—] | ||||
| (i)(1) | (1) [inserted: ] | |||
| [inserted: the State has implemented the standard (or a comparable standard) for the electric utility;] | ||||
| (i)(2) | (2) [inserted: ] | |||
| [inserted: the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or] | ||||
| (i)(3) | (3) [inserted: ] | |||
| [inserted: the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility.] | ||||
16 U.S.C. § 2634 Prior and pending proceedings
1 change the bill asks for here, 1 carried out
- Carried out:
Section 124 of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2634) is amended by adding at the end the following:
In the case of the standard established by paragraph (22) of section 111(d), the reference contained in this section to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (22).
.
§ 2634
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| § 2634. Prior and pending proceedings | § 2634. Prior and pending proceedings | |||
| For purposes of subchapters I and II, and this subchapter, proceedings commenced by State regulatory authorities (with respect to electric utilities for which it has ratemaking authority) and nonregulated electric utilities before November 9, 1978, and actions taken before such date in such proceedings shall be treated as complying with the requirements of subchapters I and II, and this subchapter if such proceedings and actions substantially conform to such requirements. For purposes of subchapters I and II, and this subchapter, any such proceeding or action commenced before November 9, 1978, but not completed before such date, shall comply with the requirements of subchapters I and II, and this subchapter, to the maximum extent practicable, with respect to so much of such proceeding or action as takes place after such date, except as otherwise provided in section 2631(c) of this title. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of each standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. | For purposes of subchapters I and II, and this subchapter, proceedings commenced by State regulatory authorities (with respect to electric utilities for which it has ratemaking authority) and nonregulated electric utilities before November 9, 1978, and actions taken before such date in such proceedings shall be treated as complying with the requirements of subchapters I and II, and this subchapter if such proceedings and actions substantially conform to such requirements. For purposes of subchapters I and II, and this subchapter, any such proceeding or action commenced before November 9, 1978, but not completed before such date, shall comply with the requirements of subchapters I and II, and this subchapter, to the maximum extent practicable, with respect to so much of such proceeding or action as takes place after such date, except as otherwise provided in section 2631(c) of this title. In the case of each standard established by paragraphs (11) through (13) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (14) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of each standard established by paragraph (15) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to August 8, 2005. In the case of the standard established by paragraph (20) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021. In the case of the standard established by paragraph (21) of section 2621(d) of this title, the reference contained in this section to November 9, 1978, shall be deemed to be a reference to November 15, 2021.[inserted: In the case of the standard established by paragraph (22) of section 111(d), the reference contained in this section to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (22).] |