Changes to 15 U.S.C. § 8520
S. 3923 · Weather Research and Forecasting Innovation Reauthorization Act of 2026 · Engrossed The official text as one chamber (House or Senate) passed it.
Passed the Senate · step 3 of 5
15 U.S.C. § 8520 United States Weather Research Program
+16 −40Shown
4 changes the bill asks for here, 4 carried out
- Carried out:
by striking paragraph (5); and
- Carried out:
by redesignating paragraphs (6) through (12) as paragraphs (5) through (11), respectively;
- Carried out:
by striking subsection (b); and
- Carried out:
by redesignating subsection (c) as subsection (b).
§ 8520(a)–(b)
Start of § 8520 to (a)(2) unchanged
| Where | Mark | Text |
|---|---|---|
| (a)(3) | (3) | |
| address critical weather-related scientific issues; | ||
| (a)(4) | (4) | |
| coordinate governmental, university, and private-sector efforts; | ||
| (a)(5) | (5) | |
| (a)(5)(A) | (A) | |
| (a)(5)(B) | (B) | |
| (a)(5)(C) | (C) | |
| (a)(5)(D) | (D) | |
| (a)(5)(D)(i) | (i) | |
| (a)(5)(D)(ii) | (ii) | |
| (a)(5)(D)(iii) | (iii) | |
| (a)(5) | ||
| [inserted: (5)] | ||
| establish teams with staff from the Office of Oceanic and Atmospheric Research and the National Weather Service to oversee the operationalization of research products developed by the Office of Oceanic and Atmospheric Research; | ||
| establish teams with staff from the Office of Oceanic and Atmospheric Research and the National Weather Service to oversee the operationalization of research products developed by the Office of Oceanic and Atmospheric Research; | ||
| (a)(6) | ||
| [inserted: (6)] | ||
| develop mechanisms for research priorities of the Office of Oceanic and Atmospheric Research to be informed by the relevant line offices within the National Oceanic and Atmospheric Administration, the relevant user community, and the weather enterprise; | ||
| develop mechanisms for research priorities of the Office of Oceanic and Atmospheric Research to be informed by the relevant line offices within the National Oceanic and Atmospheric Administration, the relevant user community, and the weather enterprise; | ||
| (a)(7) | ||
| [inserted: (7)] | ||
| develop an internal mechanism to track the progress of each research project within the Office of Oceanic and Atmospheric Research and mechanisms to terminate a project that is not adequately progressing; | ||
| develop an internal mechanism to track the progress of each research project within the Office of Oceanic and Atmospheric Research and mechanisms to terminate a project that is not adequately progressing; | ||
| (a)(8) | ||
| [inserted: (8)] | ||
| develop and implement a system to track whether extramural research grant goals were accomplished; | ||
| develop and implement a system to track whether extramural research grant goals were accomplished; | ||
| (a)(9) | ||
| [inserted: (9)] | ||
| provide facilities for products developed by the Office of Oceanic and Atmospheric Research to be tested in operational simulations, such as test beds; | ||
| provide facilities for products developed by the Office of Oceanic and Atmospheric Research to be tested in operational simulations, such as test beds; | ||
| (a)(10) | ||
| [inserted: (10)] | ||
| encourage academic collaboration with the Office of Oceanic and Atmospheric Research and the National Weather Service by facilitating visiting scholars; and | ||
| encourage academic collaboration with the Office of Oceanic and Atmospheric Research and the National Weather Service by facilitating visiting scholars; and | ||
| (a)(11) | ||
| [inserted: (11)] | ||
| carry out the activities of the Earth Prediction Innovation Center as described in section 8512(b)(2) of this title. | ||
| carry out the activities of the Earth Prediction Innovation Center as described in section 8512(b)(2) of this title. | ||
| (b) | (b) | |
| (b)(1) | (1) | |
| (b)(2) | (2) | |
| (b)(3) | (3) | |
| (b) | ||
| [inserted: (b)] Subseasonal defined | ||
| In this section, the term “subseasonal” means the time range between 2 weeks and 3 months. | ||
| In this section, the term “subseasonal” means the time range between 2 weeks and 3 months. |