Changes to 42 U.S.C. § 15942

S. 4795 · Fighting for Reliable Energy and Ending Doubt for Open Markets Act ·

FREEDOM Act

In committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

42 U.S.C. § 15942 NEPA review

+3 −3Shown
More for 42 U.S.C. § 15942
Read § 15942
5 changes the bill asks for here, 5 carried out
  1. Carried out:

    by striking (NEPA) and inserting (42 U.S.C. 4321 et seq.) (referred to in this section as NEPA);

  2. Carried out:

    by inserting (30 U.S.C. 181 et seq.) after Mineral Leasing Act; and

  3. Carried out:

    by inserting or the Geothermal Steam Act of 1970 (30 U.S.C. 1001 et seq.) for the purpose of exploration or development of geothermal resources before the period at the end; and

  4. Carried out:

    in paragraph (2), by striking oil or gas and inserting oil, gas, or geothermal resources; and

  5. Carried out:

    in paragraph (3), by striking oil or gas and inserting oil, gas, or geothermal resources.

§ 15942(a)–(b)

§ 15942. NEPA review

(a) NEPA review Action by the Secretary of the Interior in managing the public lands, or the Secretary of Agriculture in managing National Forest System Lands, with respect to any of the activities described in subsection (b) shall be subject to a rebuttable presumption that the use of a categorical exclusion under the National Environmental Policy Act of 1969 [42 U.S.C. 4321 et seq.] ([inserted: 42 U.S.C. 4321 et seq.) (referred to in this section as “]NEPA[inserted: ”]) would apply if the activity is conducted pursuant to the Mineral Leasing Act [inserted: (30 U.S.C. 181 et seq.) ][30 U.S.C. 181 et seq.] for the purpose of exploration or development of oil or gas[inserted: or the Geothermal Steam Act of 1970 (30 U].[inserted: S.C. 1001 et seq.) for the purpose of exploration or development of geothermal resources.]

(b) Activities described The activities referred to in subsection (a) are the following:

(1) Individual surface disturbances of less than 5 acres so long as the total surface disturbance on the lease is not greater than 150 acres and site-specific analysis in a document prepared pursuant to NEPA has been previously completed.

(2) Drilling an oil[inserted: ,] [inserted: gas, ]or [struck: gas][inserted: geothermal] [inserted: resources ]well at a location or well pad site at which drilling has occurred previously within 5 years prior to the date of spudding the well.

(3) Drilling an oil[inserted: ,] [inserted: gas, ]or [struck: gas][inserted: geothermal] [inserted: resources ]well within a developed field for which an approved land use plan or any environmental document prepared pursuant to NEPA analyzed such drilling as a reasonably foreseeable activity, so long as such plan or document was approved within 5 years prior to the date of spudding the well.

(4) Placement of a pipeline in an approved right-of-way corridor, so long as the corridor was approved within 5 years prior to the date of placement of the pipeline.

(5) Maintenance of a minor activity, other than any construction or major renovation or a building or facility.