Changes to the Code
S. 4856 · Remote Waste Storage Act · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
In committee · step 2 of 5
42 U.S.C. § 6921 Identification and listing of hazardous waste
1 change the bill asks for here, 1 carried out
- Carried out:
Section 3001(d)(6) of the Solid Waste Disposal Act (42 U.S.C. 6921(d)(6)) is amended, in the second sentence, by inserting
, or for not more than 2 years if such generator lacks year-round surface transportation access to a treatment, storage, or disposal facility and the accumulation of the hazardous waste is conducted in compliance with all applicable laws (including regulations)
before the period at the end.
§ 6921(d)Small quantity generator waste(5)–(7)
Start of § 6921 to (d)(4) unchanged ·
(5) Until the effective date of standards required to be promulgated under paragraph (1), any hazardous waste identified or listed under this section generated by any generator during any calendar month in a total quantity greater than one hundred kilograms but less than one thousand kilograms, which is not treated, stored, or disposed of at a hazardous waste treatment, storage, or disposal facility with a permit under section 6925 of this title, shall be disposed of only in a facility which is permitted, licensed, or registered by a State to manage municipal or industrial solid waste.
(6) Standards promulgated as provided in paragraph (1) shall, at a minimum, require that all treatment, storage, or disposal of hazardous wastes generated by generators referred to in paragraph (1) shall occur at a facility with interim status or a permit under this subchapter, except that onsite storage of hazardous waste generated by a generator generating a total quantity of hazardous waste greater than one hundred kilograms, but less than one thousand kilograms during a calendar month, may occur without the requirement of a permit for up to one hundred and eighty days. Such onsite storage may occur without the requirement of a permit for not more than six thousand kilograms for up to two hundred and seventy days if such generator must ship or haul such waste over two hundred miles[inserted: , or for not more than 2 years if such generator lacks year-round surface transportation access to a treatment, storage, or disposal facility and the accumulation of the hazardous waste is conducted in compliance with all applicable laws (including regulations)].
(7)
(A) Nothing in this subsection shall be construed to affect or impair the validity of regulations promulgated by the Secretary of Transportation pursuant to chapter 51 of title 49.
Rest of § 6921 unchanged ·