33 U.S.C. § 2332 Shoreline and riverine protection and restoration

+11 −1Shown
More for 33 U.S.C. § 2332
Read § 2332
2 changes the bill asks for here, 2 carried out
  1. Carried out:

    in subsection (e)(2), by adding at the end the following:(N) Blackstone River watershed, Rhode Island. (O) Passumpsic River watershed, Vermont. (P) Island End River, Massachusetts. (Q) Cobbs Creek and Darby Creek, Pennsylvania. (R) Western shoreline of the State of Alaska.; and

  2. Carried out:

    in subsection (f)(2), by striking $15,000,000 and inserting $20,000,000.

§ 2332(e)–(g)

Start of § 2332 to (e)(2)(K) unchanged

WhereMarkThe Code nowMarkAs the bill would leave it
(e)(2)(L)(L) (L)
Shoreline of the State of Connecticut.Shoreline of the State of Connecticut.
(e)(2)(M)(M) (M)
Winooski River tributary watershed, Vermont.Winooski River tributary watershed, Vermont.
(e)(2)(N)(N) [inserted: ]
[inserted: Blackstone River watershed, Rhode Island.]
(e)(2)(O)(O) [inserted: ]
[inserted: Passumpsic River watershed, Vermont.]
(e)(2)(P)(P) [inserted: ]
[inserted: Island End River, Massachusetts.]
(e)(2)(Q)(Q) [inserted: ]
[inserted: Cobbs Creek and Darby Creek, Pennsylvania.]
(e)(2)(R)(R) [inserted: ]
[inserted: Western shoreline of the State of Alaska.]
(f)(f) Procedure(f) Procedure
(f)(1)(1) All projects(1) All projects
The Secretary shall not implement any project under this section until—The Secretary shall not implement any project under this section until—
(f)(1)(A)(A) (A)
the Secretary submits to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a written notification describing the project and the determinations made under subsection (d)(1); andthe Secretary submits to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a written notification describing the project and the determinations made under subsection (d)(1); and
(f)(1)(B)(B) (B)
21 calendar days have elapsed after the date on which the notification was received by the committees.21 calendar days have elapsed after the date on which the notification was received by the committees.
(f)(2)(2) Projects requiring specific authorization(2) Projects requiring specific authorization
If the Federal share of the cost to design and construct a project under this section exceeds $[struck: 15],000,000, the Secretary may only carry out the project if Congress enacts a law authorizing the Secretary to carry out the project.If the Federal share of the cost to design and construct a project under this section exceeds $[inserted: 20],000,000, the Secretary may only carry out the project if Congress enacts a law authorizing the Secretary to carry out the project.
(g)(g) Definitions(g) Definitions
In this section:In this section:
(g)(1)(1) Economically disadvantaged community(1) Economically disadvantaged community
The term “economically disadvantaged community” has the meaning given the term as defined by the Secretary under section 160 of the Water Resources Development Act of 2020 (33 U.S.C. 2201 note).The term “economically disadvantaged community” has the meaning given the term as defined by the Secretary under section 160 of the Water Resources Development Act of 2020 (33 U.S.C. 2201 note).
(g)(2)(2) Natural feature; nature-based feature(2) Natural feature; nature-based feature
The terms “natural feature” and “nature-based feature” have the meanings given those terms in section 2289a(a) of this title.The terms “natural feature” and “nature-based feature” have the meanings given those terms in section 2289a(a) of this title.