Changes to the Code
S. 4960 · CLEAN Act · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
Introduced · step 1 of 5
30 U.S.C. § 1003 Leasing procedures
4 changes the bill asks for here, 3 carried out
- Carried out:
in paragraph (2), by striking
2 years
and insertingyear
; - Carried out:
by redesignating paragraphs (3) and (4) as paragraphs (5) and (6), respectively; and
- Not carried out:
after paragraph (2), by inserting the following:
(3) Replacement Sales.— If a lease sale under paragraph (1) for a year is canceled or delayed, the Secretary of the Interior shall conduct a replacement sale during the same year. (4) Requirement.— Of the nominated parcels eligible for geothermal development and utilization …
We can't read how this instruction is worded yet, so it isn't shown in the text.
Technical detail
no-pattern: after paragraph (X), by inserting the following: QCONTENT. - Carried out:
Section 4 of the Geothermal Steam Act of 1970 (30 U.S.C. 1003) is amended by adding at the end the following:
(h) Deadlines for consideration of geothermal drilling permits.— (1) Notice.— Not later than 30 days after the date on which the Secretary receives an application for any geothermal drilling permit, the Secretary shall— (A) provide written notice to the applicant that the …
§ 1003(b)–(d)
Start of § 1003 to (b) unchanged ·
(1) In general Except as otherwise specifically provided by this chapter, all land to be leased that is not subject to leasing under subsection (c) shall be leased as provided in this subsection to the highest responsible qualified bidder, as determined by the Secretary.
(2) Competitive lease sales The Secretary shall hold a competitive lease sale at least once every [struck: 2][inserted: year] [struck: years ]for land in a State that has nominations pending under subsection (a) if the land is otherwise available for leasing.
[struck: (3)] [inserted: (5)] Lands subject to mining claims Lands that are subject to a mining claim for which a plan of operations has been approved by the relevant Federal land management agency may be available for noncompetitive leasing under this section to the mining claim holder.
[struck: (4)] [inserted: (6)] Land subject to oil and gas lease Land under an oil and gas lease issued pursuant to the Mineral Leasing Act (30 U.S.C. 181 et seq.) or the Mineral Leasing Act for Acquired Lands (30 U.S.C. 351 et seq.) that is subject to an approved application for permit to drill and from which oil and gas production is occurring may be available for noncompetitive leasing under subsection (c) by the holder of the oil and gas lease—
(A) on a determination that geothermal energy will be produced from a well producing or capable of producing oil and gas; and
(B) to provide for the coproduction of geothermal energy with oil and gas.
(c) Noncompetitive leasing The Secretary shall make available for a period of 2 years for noncompetitive leasing any tract for which a competitive lease sale is held, but for which the Secretary does not receive any bids in a competitive lease sale.
(d) Pending lease applications
§ 1003(g)–(h)
(d)(1)–(g) unchanged ·
(1) In general Subject to paragraph (2), a geothermal lease for the direct use of geothermal resources shall cover not more than the quantity of acreage determined by the Secretary to be reasonably necessary for the proposed use.
(2) Limitations The quantity of acreage covered by the lease shall not exceed the limitations established under section 1006 of this title.
(h) [inserted: Deadlines for consideration of geothermal drilling permits.—]
(1) [inserted: Notice.—] [inserted: Not later than 30 days after the date on which the Secretary receives an application for any geothermal drilling permit, the Secretary shall—]
(A) [inserted: provide written notice to the applicant that the application is complete; or]
(B) [inserted: notify the applicant that information is missing and specify any information that is required to be submitted for the application to be complete.]
(2) [inserted: Issuance or deferral.—]
(A) [inserted: In general.—] [inserted: Not later than 30 days after the Secretary has provided written notice to an applicant for a geothermal drilling permit that the application for such permit is complete pursuant to paragraph (1)(A), the Secretary shall—]
(i) [inserted: issue the permit, if the requirements under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and other applicable law have been completed within such timeframe; or]
(ii) [inserted: defer the decision on the permit and provide to the applicant a notice—]
(I) [inserted: that specifies any steps that the applicant could take for the permit to be issued; and]
(II) [inserted: that includes a list of actions that need to be taken by the agency to comply with applicable law, together with timelines and deadlines for taking such actions, which shall not exceed the deadlines specified in section 107(g) of the National Environmental Policy Act of 1969 (42 U.S.C. 4336a(g)).]
(B) [inserted: Deadline for deferred decisions.—] [inserted: If the Secretary defers a decision on a permit under subparagraph (A)(ii), the Secretary shall issue a decision on the permit not later than 10 days after the applicant takes any steps specified pursuant to subparagraph (A)(ii)(I) and the agency takes the actions listed pursuant to subparagraph (A)(ii)(II) in accordance with any applicable timelines and deadlines.]