Changes to the Code
S. 514 · MERP Clarifications Act of 2025 · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
In committee · step 2 of 5
42 U.S.C. § 7436 Methane emissions and waste reduction incentive program for petroleum and natural gas systems
5 changes the bill asks for here, 5 carried out
- Carried out:
in subsection (f), by adding at the end the following:
(8) Exemption for small upstream producers.— (A) In general.— The Administrator may not, pursuant to any requirement under this section, impose a reporting requirement or a charge under this section on an applicable facility described in subparagraph (B). (B) Applicable …
- Carried out:
by striking subsection (g) and inserting the following:
(g) Period.— The Administrator may not impose or collect the charge under subsection (c) until January 1 of the first calendar year that begins after the date on which the Administrator submits to the Committee on Environment and Public Works of the Senate and the Committee on …
- Carried out:
by redesignating subsection (i) as subsection (k);
- Carried out:
by inserting after subsection (h) the following:
(i) Public comment period.— Except as provided in section 2(c) of the MERP Clarifications Act of 2025, any proposed regulation, rule, guidance, or directive with respect to the implementation of this section from the Administrator, the Executive Office of the President, or …
- Carried out:
by adding at the end the following:
(l) Sunset.— (1) Termination of effectiveness.— The authority provided under this section terminates on December 31, 2034. (2) Continued imposition of waste charge.— (A) In general.— If this section is not reauthorized by December 31, 2034, the Administrator shall immediately …
§ 7436(f)–(l)
Start of § 7436 to (f)(6)(A)(ii) unchanged ·
(B) Resumption of charge If the conditions in clause (i) or (ii) of subparagraph (A) cease to apply after the Administrator has made the determination in that subparagraph, the applicable facility will again be subject to the charge under subsection (c) beginning in the first calendar year in which the conditions in either clause (i) or (ii) of that subparagraph are no longer met.
(7) Plugged wells Charges shall not be imposed with respect to the emissions rate from any well that has been permanently shut-in and plugged in the previous year in accordance with all applicable closure requirements, as determined by the Administrator.
(8) [inserted: Exemption for small upstream producers.—]
(A) [inserted: In general.—] [inserted: The Administrator may not, pursuant to any requirement under this section, impose a reporting requirement or a charge under this section on an applicable facility described in subparagraph (B).]
(B) [inserted: Applicable facilities described.—] [inserted: An applicable facility referred to in subparagraphs (A), (C), and (D) is an applicable facility that, as of August 16, 2022—]
(i) [inserted: was generating less than 25,000 metric tons of carbon dioxide equivalent of greenhouse gases emitted per year; and]
(ii) [inserted: had 2,500 or fewer full-time employees.]
(C) [inserted: No requirement to demonstrate.—] [inserted: The Administrator may not impose a requirement that an applicable facility described in subparagraph (B) demonstrate to the Administrator that the applicable facility meets the requirements described in that subparagraph.]
(D) [inserted: Notification.—]
(i) [inserted: Notice to facility.—] [inserted: Not later than 60 days after the date of enactment of this paragraph, the Administrator shall provide written notice to each applicable facility described in subparagraph (B) that the applicable facility is not subject to the reporting requirements or charges imposed under this section.]
(ii) [inserted: Publication.—] [inserted: The Administrator shall communicate publicly (including through press releases and messages on the website of the Environmental Protection Agency) that the applicable facilities described in subparagraph (B) are not subject to the reporting requirements or charges imposed under this section.]
(9) [inserted: Exemption for certain producers.—] [inserted: Notwithstanding any other requirement of this section, the Administrator may not impose a charge under this section on an applicable facility during any period in which the applicable facility—]
(A) [inserted: complies with subpart OOOOb and OOOOc, as applicable, of part 60 of title 40, Code of Federal Regulations (or successor regulations); and]
(B) [inserted: is located in a State in compliance with the applicable State implementation plan required under subpart OOOOc of that part (or successor regulations).]
(g) Period[inserted: .—] [inserted: The Administrator may not impose or collect the charge under subsection (c) until January 1 of the first calendar year that begins after the date on which the Administrator submits to the Committee on Environment and Public Works of the Senate and the Committee on Energy and Commerce of the House of Representatives a written notice that each of the following requirements has been met for a period of not less than 1 year before that January 1:]
(1) [inserted: The grants authorized under subsections (a) and (b) have been fully disbursed to all eligible recipients.]
(2) [inserted: The revisions to subpart W of part 98 of title 40, Code of Federal Regulations, that are required under this section—]
(A) [inserted: ensure the use of emissions factors that have been validated by the Administrator and posted to the website of the Administrator; and]
(B) [inserted: have been finalized.]
[struck: The charge under subsection (c) shall be imposed and collected beginning with respect to emissions reported for calendar year 2034 and for each year thereafter.]
(h) Reporting Not later than 2 years after August 16, 2022, the Administrator shall revise the requirements of subpart W of part 98 of title 40, Code of Federal Regulations, to ensure the reporting under such subpart, and calculation of charges under subsections (e) and (f) of this section, are based on empirical data, including data collected pursuant to subsection (a)(4), accurately reflect the total methane emissions and waste emissions from the applicable facilities, and allow owners and operators of applicable facilities to submit empirical emissions data, in a manner to be prescribed by the Administrator, to demonstrate the extent to which a charge under subsection (c) is owed.
(i) [inserted: Public comment period.—] [inserted: Except as provided in section 2(c) of the MERP Clarifications Act of 2025, any proposed regulation, rule, guidance, or directive with respect to the implementation of this section from the Administrator, the Executive Office of the President, or another Federal agency shall, consistent with subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the “Administrative Procedure Act”), be subject to a period of public comment of not less than 90 days.]
(j) [inserted: Dispute resolution procedure.—] [inserted: Not later than 60 days after the date of enactment of this subsection, the Administrator shall, consistent with subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the “Administrative Procedure Act”), propose a rule establishing an expedited process for an applicable facility to appeal or dispute the amount of a charge imposed under this section that is separate and apart from any other such process under this Act.]
[struck: (i)] [inserted: (k)] Definition of greenhouse gas In this section, the term “greenhouse gas” means the air pollutants carbon dioxide, hydrofluorocarbons, methane, nitrous oxide, perfluorocarbons, and sulfur hexafluoride.
(l) [inserted: Sunset.—]
(1) [inserted: Termination of effectiveness.—] [inserted: The authority provided under this section terminates on December 31, 2034.]
(2) [inserted: Continued imposition of waste charge.—]
(A) [inserted: In general.—] [inserted: If this section is not reauthorized by December 31, 2034, the Administrator shall immediately cease all activities with respect to the imposition of the charge under this section.]
(B) [inserted: Enforcement.—]
(i) [inserted: In general.—] [inserted: If the Administrator or the head of any other applicable Federal agency carries out any authority under this section after the date described in subparagraph (A), a party that suffers likely harm from the carrying out of that authority may seek financial compensation from the Federal Government in the appropriate Federal district court.]
(ii) [inserted: Expedited relief.—] [inserted: A Federal district court shall expedite the consideration of an action described in clause (i) brought by the owner of an applicable facility with 2,500 or fewer full-time employees.]
(3) [inserted: Rescission.—] [inserted: On December 31, 2034, there is rescinded the unobligated balance of amounts made available under subsections (a) and (b) as of that date.]