Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

42 U.S.C. § 2243 Licensing of uranium enrichment facilities

+14 −810 of 11 shown
More for 42 U.S.C. § 2243
Read § 2243Only this section
11 changes the bill asks for here, 10 carried out
  1. Carried out:

    in paragraph (1), by striking construction and; and

  2. Carried out:

    by striking the hearing on; and

  3. Carried out:

    by striking construction and;

  4. Carried out:

    by striking The Commission shall conduct a single adjudicatory hearing on the record and inserting In accordance with section 189 a.(1)(A), the Commission shall grant a hearing;

  5. Carried out:

    by striking construction and; and

  6. Not carried out:

    by inserting on the request of any person whose interest may be affected by the operation of the uranium enrichment facility and shall admit that person as a party to the proceeding after and 63;

    “and 63” isn't in § 2243(b)(1) in the Code as we have it. The law may have changed since the bill was drafted.

    Technical detail“and 63” not found in /us/usc/t42/s2243/b/1
  7. Carried out:

    by striking paragraph (2);

  8. Carried out:

    by redesignating paragraph (3) as paragraph (2); and

  9. Carried out:

    in paragraph (2) (as so redesignated), in the paragraph heading, by striking Single proceeding and inserting No further action required;

  10. Carried out:

    in subsection (c), by striking construction and; and

  11. Carried out:

    by adding at the end the following:(g) Pre-license construction.— Nothing in this section prohibits the construction of a uranium enrichment facility prior to issuance of a license authorizing operation of that facility under sections 53 and 63, subject to the conditions that the construction— (1) commences after …

§ 2243(a)–(d)

§ 2243. Licensing of uranium enrichment facilities

(a) Environmental impact statement

(1) Major Federal action The issuance of a license under sections 2073 and 2093 of this title for the [struck: construction and ]operation of any uranium enrichment facility shall be considered a major Federal action significantly affecting the quality of the human environment for purposes of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).

(2) Timing An environmental impact statement prepared under paragraph (1) shall be prepared before the [struck: hearing on the ]issuance of a license for the [struck: construction and ]operation of a uranium enrichment facility is completed.

(b) Adjudicatory hearing

(1) In general [struck: The][inserted: In] [struck: Commission][inserted: accordance] [struck: shall][inserted: with] [struck: conduct][inserted: section] [inserted: 189 ]a[inserted: .(1)(A),] [struck: single][inserted: the] [struck: adjudicatory][inserted: Commission] [struck: hearing][inserted: shall] [struck: on][inserted: grant] [struck: the][inserted: a] [struck: record][inserted: hearing] with regard to the licensing of the [struck: construction and ]operation of a uranium enrichment facility under sections 2073 and 2093 of this title.

[struck: (2)] [struck: Timing] [struck: Such hearing shall be completed and a decision issued before the issuance of a license for such construction and operation.]

[struck: (3)] [inserted: (2)] [struck: Single][inserted: No] [struck: proceeding][inserted: further action required] No further Commission licensing action shall be required to authorize operation.

(c) Inspection and operation Prior to commencement of operation of a uranium enrichment facility licensed hereunder, the Commission shall verify through inspection that the facility has been constructed in accordance with the requirements of the license for [struck: construction and ]operation. The Commission shall publish notice of the inspection results in the Federal Register.

(d) Insurance and decommissioning

(1) The Commission shall require, as a condition of the issuance of a license under sections 2073 and 2093 of this title for a uranium enrichment facility, that the licensee have and maintain liability insurance of such type and in such amounts as the Commission judges appropriate to cover liability claims arising out of any occurrence within the United States, causing, within or outside the United States, bodily injury, sickness, disease, or death, or loss of or damage to property, or loss of use of property, arising out of or resulting from the radioactive, toxic, explosive, or other hazardous properties of chemical compounds containing source or special nuclear material.

§ 2243(f)–(g)

(d)(2)–(f)(2) unchanged ·

(A) the common defense and security of the United States; or

(B) the maintenance of a reliable and economical domestic source of enrichment services.

(g) [inserted: Pre-license construction.—] [inserted: Nothing in this section prohibits the construction of a uranium enrichment facility prior to issuance of a license authorizing operation of that facility under sections 53 and 63, subject to the conditions that the construction—]

(1) [inserted: commences after the date on which the Commission dockets the application;]

(2) [inserted: complies with all applicable Federal laws and regulations; and]

(3) [inserted: is entirely at the risk of the applicant.]