Skip to content
The People's CodeSearch
Menu

Title 42 · The Public Health and Welfare

Changes to 42 U.S.C. § 7502

S. 5363 · New Source Review Permitting Improvement Act ·

In committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

42 U.S.C. § 7502 Nonattainment plan provisions in general

+8 −0Shown
More for 42 U.S.C. § 7502
Read § 7502
1 change the bill asks for here, 1 carried out
  1. Carried out:

    Section 172(c)(5) of the Clean Air Act (42 U.S.C. 7502(c)(5)) is amended by adding at the end the following:(A) may be costly; (B) may significantly alter the site; (C) is permanent in nature; or (D) is to accommodate an installation to an emissions unit. The construction for which a permit is required under this paragraph is construction that involves physical construction of the …

§ 7502(c)Nonattainment plan provisions(4)–(7)

Start of § 7502 to (c)(3) unchanged ·

(4) Identification and quantification Such plan provisions shall expressly identify and quantify the emissions, if any, of any such pollutant or pollutants which will be allowed, in accordance with section 7503(a)(1)(B) of this title, from the construction and operation of major new or modified stationary sources in each such area. The plan shall demonstrate to the satisfaction of the Administrator that the emissions quantified for this purpose will be consistent with the achievement of reasonable further progress and will not interfere with attainment of the applicable national ambient air quality standard by the applicable attainment date.

(5) Permits for new and modified major stationary sources Such plan provisions shall require permits for the construction and operation of new or modified major stationary sources anywhere in the nonattainment area, in accordance with section 7503 of this title.

(A) [inserted: may be costly;]

(B) [inserted: may significantly alter the site;]

(C) [inserted: is permanent in nature; or]

(D) [inserted: is to accommodate an installation to an emissions unit.]

(6) Other measures Such plan provisions shall include enforceable emission limitations, and such other control measures, means or techniques (including economic incentives such as fees, marketable permits, and auctions of emission rights), as well as schedules and timetables for compliance, as may be necessary or appropriate to provide for attainment of such standard in such area by the applicable attainment date specified in this part.

(7) Compliance with section 7410(a)(2) Such plan provisions shall also meet the applicable provisions of section 7410(a)(2) of this title.

Rest of § 7502 unchanged ·

Step through the changes