16 U.S.C. § 824p Siting of interstate electric transmission facilities

+115 −6817 of 22 shown
More for 16 U.S.C. § 824p
Read § 824p
22 changes the bill asks for here, 17 carried out
  1. Carried out:

    Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (a) and inserting the following:(a) Definitions.— In this section: (1) Affected landowner.— The term “affected landowner” includes each owner of a property interest in affected property, including— (A) the Federal Government; (B) a State or local government; and (C) each owner noted in the most recent county …

  2. Carried out:

    in the matter preceding paragraph (1), by striking Except and all that follows through finds that and inserting Except as provided in subsections (d)(1) and (i), the Commission shall, after notice and an opportunity for hearing, including a public comment period of at least 45 days, issue one or more permits to individual or joint applicants for the construction or modification of electric transmission facilities necessary in the national interest if the Commission finds that;

  3. Carried out:

    in subparagraph (A)(i), by inserting or modification after siting; and

  4. Carried out:

    in the matter preceding clause (i), by inserting or modification after siting; and

  5. Not carried out:

    in clause (i), by striking the later of in the matter preceding subclause (I) and all that follows through the semicolon at the end of subclause (II) and inserting the date on which the application was filed with the State commission or other entity;; and

    “the later of” isn't in § 824p(b)(1)(C)(i)(II) in the Code as we have it. The law may have changed since the bill was drafted.

    Technical detail“the later of” not found in /us/usc/t16/s824p/b/1/C/i/II
  6. Carried out:

    by striking paragraphs (2) through (6) and inserting the following:(2) the proposed facilities will be used for the transmission of electric energy in interstate commerce (including transmission from the outer Continental Shelf to a State) or foreign commerce; (3) the proposed construction or modification is consistent with the public interest; …

  7. Carried out:

    Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (d) and inserting the following:(d) State siting and consultation.— (1) Preservation of State siting authority.— The Commission shall have no authority to issue a permit under subsection (b) for the construction or modification of an electric transmission facility within a State except as provided in paragraph …

  8. Carried out:

    Section 216(e)(3) of the Federal Power Act (16 U.S.C. 824p(e)(3)) is amended by striking shall conform and all that follows through the period at the end and inserting shall be in accordance with rule 71.1 of the Federal Rules of Civil Procedure..

  9. Carried out:

    Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (f) and inserting the following:(f) Cost allocation.— (1) Transmission tariffs.— For the purposes of this section and except as provided in paragraph (2), any transmitting utility that owns, controls, or operates electric transmission facilities that the Commission finds to be consistent with the findings …

  10. Carried out:

    in paragraph (1), by adding at the end the following:(C) The term “Federal authorization” includes a certification under section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341) from a certifying authority (as defined in subsection (h) of that section) and any other permit, license, concurrence, or approval of a …

  11. Not carried out:

    in paragraph (2), by striking the period at the end and inserting the following:(A) the Commission shall act as the lead agency in the case of facilities permitted under subsection (b) or section 225; and (B) the Department of the Interior shall act as the lead agency in the case of facilities located on a lease, easement, or right-of-way granted by the …

    We can't read how this instruction is worded yet, so it isn't shown in the text.

    Technical detailno-pattern: striking the period at the end and inserting the following: QCONTENT;
  12. Carried out:

    in each of paragraphs (3), (4)(B), (4)(C), (5)(B), (6)(A), (7)(A), (7)(B)(i), (8)(A)(i), and (9), by striking Secretary each place it appears and inserting lead agency;

  13. Carried out:

    in paragraph (4)(A), by striking As head of the lead agency, the Secretary and inserting The lead agency;

  14. Carried out:

    in paragraph (5)(A), by striking As lead agency head, the Secretary and inserting The lead agency;

  15. Not carried out:

    in subparagraph (A), by striking 18 months after the date of enactment of this section and inserting 18 months after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026; and

    “18 months after the date of enactment of this section” isn't in § 824p(h)(7)(A) in the Code as we have it. The law may have changed since the bill was drafted.

    Technical detail“18 months after the date of enactment of this section” not found in /us/usc/t16/s824p/h/7/A
  16. Not carried out:

    in subparagraph (B)(i), by striking 1 year after the date of enactment of this section and inserting 18 months after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026; and

    “1 year after the date of enactment of this section” isn't in § 824p(h)(7)(B)(i) in the Code as we have it. The law may have changed since the bill was drafted.

    Technical detail“1 year after the date of enactment of this section” not found in /us/usc/t16/s824p/h/7/B/i
  17. Carried out:

    by adding at the end the following:(10) Any order or action of a Federal agency or State administrative agency acting pursuant to Federal law to issue, condition, or deny a Federal authorization shall be subject to judicial review in the same courts in which an order of the Commission is subject to judicial …

  18. Carried out:

    in paragraph (3), by striking , including facilities in national interest electric transmission corridors; and

  19. Carried out:

    in subparagraph (A), by striking ; and and inserting a period;

  20. Carried out:

    by striking subparagraph (B); and

  21. Not carried out:

    by striking in disagreement in the matter preceding subparagraph (A) and all that follows through (A) the in subparagraph (A) and inserting unable to reach an agreement on an application seeking approval by the.

    We can't read how this instruction is worded yet, so it isn't shown in the text.

    Technical detailno-pattern: striking QTEXT in the matter preceding subparagraph (X) and all that follows through QTEXT in subparagraph (X) and inserting QTEXT.
  22. Carried out:

    Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (k) and inserting the following:(k) Jurisdiction.— (1) ERCOT.— This section shall not apply within the area referred to in section 212(k)(2)(A). (2) Other utilities.— (A) In general.— For the purposes of this section, the Commission shall have jurisdiction over all transmitting utilities, including …

§ 824p(a)–(b)

§ 824p. Siting of interstate electric transmission facilities

(a) [struck: Designation of national interest electric transmission corridors][inserted: Definitions.—] [inserted: In this section:]

(1) [inserted: Affected landowner.—] [inserted: The term “affected landowner” includes each owner of a property interest in affected property, including—]

(A) [inserted: the Federal Government;]

(B) [inserted: a State or local government; and]

(C) [inserted: each owner noted in the most recent county or city tax record as receiving the relevant tax notice with respect to that interest.]

[struck: Not later than 1 year after August 8, 2005, and every 3 years thereafter, the Secretary of Energy (referred to in this section as the “Secretary”), in consultation with affected States and Indian Tribes, shall conduct a study of electric transmission capacity constraints and congestion.]

(2) [inserted: Affected property.—] [struck: Not][inserted: The] [struck: less][inserted: term] [struck: frequently than once every 3 years, the Secretary, after considering alternatives and recommendations from interested parties (including an opportunity for comment from ][inserted: “]affected [struck: States][inserted: property”] [struck: and][inserted: means] [struck: Indian][inserted: any] [struck: Tribes),][inserted: land] [struck: shall issue a report, based on the study under paragraph (1) ]or other [struck: information relating to electric transmission capacity constraints and congestion, which may designate as a national interest electric transmission corridor any geographic area that][inserted: property]—

(A) [inserted: that is or will be crossed by the energy transmission facility proposed to be constructed or modified under the applicable permit under subsection (b);]

(B) [inserted: that is or will be used as a facility site with respect to the energy transmission facility proposed to be constructed or modified under the applicable permit under subsection (b);]

(C) [inserted: that abuts any boundary of an existing right-of-way or other facility site that—]

(i) [inserted: is owned by an electric utility; and]

(ii) [inserted: is located not more than 500 feet from the energy transmission facility to be constructed or modified under the applicable permit under subsection (b);]

(D) [inserted: that abuts the boundary of a proposed facility site for the energy transmission facility to be constructed or modified under the applicable permit under subsection (b);]

(E) [inserted: that is crossed by, or abuts any boundary of, an existing or proposed right-of-way that—]

(i) [inserted: will be used for the energy transmission facility to be constructed or modified under the applicable permit under subsection (b); and]

(ii) [inserted: is located not more than 500 feet from the proposed location of that energy transmission facility; or]

(F) [inserted: on which a residence is located not more than 500 feet from the boundary of any right-of-way for that energy transmission facility.]

[struck: (i)] [struck: 1 is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or]

[struck: (ii)] [struck: 2 is expected to experience such energy transmission capacity constraints or congestion.]

(3) [inserted: Commission.—] [struck: Not][inserted: The] [struck: less][inserted: term] [struck: frequently][inserted: “Commission”] [struck: than][inserted: means] [struck: once every 3 years, ]the [struck: Secretary,][inserted: Federal] [struck: in][inserted: Energy] [struck: conducting][inserted: Regulatory] [struck: the study under paragraph (1) and issuing the report under paragraph (2), shall consult with any appropriate regional entity referred to in section 824o of this title][inserted: Commission].

(4) [inserted: Improved reliability.—] [inserted: The term “improved reliability” has the meaning given the term in section 225(a).]

(5) [inserted: Landowner input.—] [inserted: The term “landowner input” means input received—]

(A) [inserted: by the Commission;]

(B) [inserted: from affected landowners, such as farmers and ranchers, in the path of the proposed construction or modification of an electric transmission facility; and]

(C) [inserted: pursuant to notification provided to, and consultation with, those affected landowners, farmers, and ranchers by the Commission.]

(6) [inserted: Secretary.—] [inserted: The term “Secretary” means the Secretary of Energy.]

[struck: In determining whether to designate a national interest electric transmission corridor under paragraph (2), the Secretary may consider whether—]

[struck: (A)] [struck: the economic vitality and development of the corridor, or the end markets served by the corridor, may be constrained by lack of adequate or reasonably priced electricity;]

[struck: (B)]

[struck: (i)] [struck: economic growth in the corridor, or the end markets served by the corridor, may be jeopardized by reliance on limited sources of energy; and]

[struck: (ii)] [struck: a diversification of supply is warranted;]

[struck: (C)] [struck: the energy independence or energy security of the United States would be served by the designation;]

[struck: (D)] [struck: the designation would be in the interest of national energy policy;]

[struck: (E)] [struck: the designation would enhance national defense and homeland security;]

[struck: (F)] [struck: the designation would enhance the ability of facilities that generate or transmit firm or intermittent energy to connect to the electric grid;]

[struck: (G)] [struck: the designation—]

[struck: (i)] [struck: maximizes existing rights-of-way; and]

[struck: (ii)] [struck: avoids and minimizes, to the maximum extent practicable, and offsets to the extent appropriate and practicable, sensitive environmental areas and cultural heritage sites; and]

[struck: (H)] [struck: the designation would result in a reduction in the cost to purchase electric energy for consumers.]

(b) Construction permit Except as provided in [struck: subsection][inserted: subsections] ([inserted: d)(1) and (]i), the Commission [struck: may][inserted: shall], after notice and an opportunity for hearing, [inserted: including a public comment period of at least 45 days, ]issue one or more permits [inserted: to individual or joint applicants ]for the construction or modification of electric transmission facilities [inserted: necessary ]in [struck: a][inserted: the] national interest [struck: electric transmission corridor designated by the Secretary under subsection (a) ]if the Commission finds that—

(1)

(A) a State in which the transmission facilities are to be constructed or modified does not have authority to—

(i) approve the siting [inserted: or modification ]of the facilities; or

(ii) consider the interstate benefits or interregional benefits expected to be achieved by the proposed construction or modification of transmission facilities in the State;

(B) the applicant for a permit is a transmitting utility under this chapter but does not qualify to apply for a permit or siting approval for the proposed project in a State because the applicant does not serve end-use customers in the State; or

(C) a State commission or other entity that has authority to approve the siting [inserted: or modification ]of the facilities—

(i) has not made a determination on an application seeking approval pursuant to applicable law by the date that is 1 year after the later of—

(I) the date on which the application was filed; and

§ 824p(b)–(c)

(b)(1)(C)(i)(II)–(ii) unchanged ·

(iii) has denied an application seeking approval pursuant to applicable law;

(2) the [inserted: proposed ]facilities [struck: to be authorized by the permit ]will be used for the transmission of electric energy in interstate commerce[inserted: (including transmission from the outer Continental Shelf to a State) or foreign commerce];

(3) the proposed construction or modification is consistent with the public interest;

(4) the proposed construction or modification will [struck: significantly][inserted: protect] [struck: reduce][inserted: or] [struck: transmission][inserted: benefit] [struck: congestion][inserted: consumers] [struck: in interstate commerce ]and [struck: protects][inserted: provide] [struck: or][inserted: improved] [struck: benefits consumers][inserted: reliability];

(5) the [struck: proposed][inserted: electric] [struck: construction][inserted: transmission] [inserted: facilities are capable of transmitting electric energy at a voltage of not less than 230 kilovolts ]or[inserted: ,] [struck: modification][inserted: in] [struck: is][inserted: the] [struck: consistent][inserted: case] [struck: with][inserted: of] [struck: sound][inserted: facilities] [struck: national][inserted: that] [struck: energy][inserted: include] [struck: policy][inserted: advanced] [struck: and][inserted: transmission] [struck: will][inserted: conductors] [struck: enhance][inserted: (including] [struck: energy][inserted: superconductors),] [struck: independence][inserted: as defined by the Commission, voltages determined to be appropriate by the Commission]; and

(6) [inserted: if applicable, ]the proposed modification [inserted: (including reconductoring) ]will maximize, to the extent reasonable and economical, the transmission capabilities of existing towers[inserted: ,] [inserted: structures, ]or [struck: structures][inserted: rights-of-way].

(c) Permit applications

(1) Permit applications under subsection (b) shall be made in writing to the Commission.

§ 824p(c)–(h)

(c)(2) unchanged ·

(B) the information to be contained in the application; and

(C) the manner of service of notice of the permit application on interested persons.

(d) [struck: Comments][inserted: State siting and consultation.—]

(1) [inserted: Preservation of State siting authority.—] [inserted: The Commission shall have no authority to issue a permit under subsection (b) for the construction or modification of an electric transmission facility within a State except as provided in paragraph (1) of that subsection.]

(2) [inserted: Consultation.—] [inserted: In any proceeding before the Commission under subsection (b), the Commission shall afford each State in which a transmission facility covered by the permit is or will be located, each affected Federal agency and Indian Tribe, private property owners, and other interested persons, a reasonable opportunity to present their views and recommendations with respect to the need for and impact of a facility covered by the permit.]

(3) [inserted: Landowner input.—] [inserted: In authorizing the construction or modification of an electric transmission facility under subsection (b), the Commission shall take into account landowner input.]

(4) [inserted: State record.—] [inserted: In any proceeding before the Commission under subsection (b), each State in which a transmission facility covered by the permit is or will be located may file with the Commission, and the Commission shall consider, any part of the State record, if applicable, that the State finds to be relevant to the determination of the Commission.]

(5) [inserted: Pre-filing processes.—] [inserted: Any Commission-related pre-filing processes relating to an application submitted under subsection (c) may commence before, but shall commence no later than, an application is submitted to the applicable State commission or other entity that has authority to approve the siting of the applicable facility.]

(6) [inserted: Simultaneous processing.—] [inserted: In the case of transmission facilities that are capable of transmitting electric energy at a voltage of not less than 345 kilovolts, an application under subsection (c) shall be submitted to the Commission simultaneously with, or any time after, the submission of an application to the applicable State commission or other entity that has authority to approve the siting of the applicable facility, and the Commission shall commence a proceeding under subsection (b).]

(7) [inserted: Limitations.—] [inserted: Simultaneous processing under paragraph (6) is subject to the condition that the Commission shall not issue a permit under subsection (b) unless the Commission first makes a finding described in subparagraph (A), (B), or (C) of subsection (b)(1) with respect to the applicable electric transmission facility.]

[struck: In any proceeding before the Commission under subsection (b), the Commission shall afford each State in which a transmission facility covered by the permit is or will be located, each affected Federal agency and Indian tribe, private property owners, and other interested persons, a reasonable opportunity to present their views and recommendations with respect to the need for and impact of a facility covered by the permit.]

(e) Rights-of-way

(1) In the case of a permit under subsection (b) for electric transmission facilities to be located on property other than property owned by the United States or a State, if the permit holder cannot acquire by contract, or is unable to agree with the owner of the property to the compensation to be paid for, the necessary right-of-way to construct or modify, and operate and maintain, the transmission facilities and, in the determination of the Commission, the permit holder has made good faith efforts to engage with landowners and other stakeholders early in the applicable permitting process, the permit holder may acquire the right-of-way by the exercise of the right of eminent domain in the district court of the United States for the district in which the property concerned is located, or in the appropriate court of the State in which the property is located.

(2) Any right-of-way acquired under paragraph (1) shall be used exclusively for the construction or modification of electric transmission facilities within a reasonable period of time after the acquisition.

(3) The practice and procedure in any action or proceeding under this subsection in the district court of the United States shall [struck: conform][inserted: be] [struck: as nearly as practicable to the practice and procedure ]in [struck: a][inserted: accordance] [struck: similar][inserted: with] [struck: action][inserted: rule] [struck: or][inserted: 71.1] [struck: proceeding in the courts ]of the [struck: State][inserted: Federal] [struck: in][inserted: Rules] [struck: which][inserted: of] [struck: the][inserted: Civil] [struck: property is located][inserted: Procedure].

(4) Nothing in this subsection shall be construed to authorize the use of eminent domain to acquire a right-of-way for any purpose other than the construction, modification, operation, or maintenance of electric transmission facilities and related facilities. The right-of-way cannot be used for any other purpose, and the right-of-way shall terminate upon the termination of the use for which the right-of-way was acquired.

(f) [struck: Compensation][inserted: Cost allocation.—]

(1) [inserted: Transmission tariffs.—] [struck: Any][inserted: For] [struck: right-][inserted: the purposes ]of[struck: -way] [struck: acquired][inserted: this] [struck: pursuant][inserted: section] [inserted: and except as provided in paragraph (2), any transmitting utility that owns, controls, or operates electric transmission facilities that the Commission finds ]to [inserted: be consistent with the findings under paragraphs (2) through (5) and, if applicable, (6) of ]subsection ([struck: e][inserted: b]) shall [struck: be][inserted: file] [struck: considered ]a [struck: taking][inserted: tariff] [inserted: or tariff revision with the Commission pursuant to section 205 and the regulations ]of [struck: private][inserted: the] [struck: property][inserted: Commission] [struck: for][inserted: allocating] [struck: which][inserted: the] [struck: just][inserted: costs] [struck: compensation][inserted: of] [struck: is][inserted: the] [struck: due][inserted: new or modified transmission facilities].

(2) [inserted: Exception.—] [struck: Just][inserted: In] [struck: compensation][inserted: the] [struck: shall][inserted: case] [struck: be][inserted: of] an [struck: amount][inserted: exempt] [struck: equal][inserted: transmitting] [struck: to][inserted: utility] [struck: the][inserted: (as] [struck: fair][inserted: defined] [struck: market][inserted: in] [struck: value][inserted: section] [inserted: 225]([struck: including][inserted: a))] [struck: applicable][inserted: that] [struck: severance][inserted: owns,] [struck: damages][inserted: controls, or operates electric transmission facilities described in paragraph (1])[inserted: ,] [struck: of][inserted: the] [inserted: Commission, notwithstanding section 211A(c), shall require ]the [struck: property][inserted: exempt] [struck: taken][inserted: transmitting] [struck: on][inserted: utility] [inserted: to provide transmission services over such facilities pursuant to section 211A and ]the [struck: date][inserted: regulations] of the [struck: exercise][inserted: Commission] [inserted: allocating the costs ]of [struck: eminent][inserted: the] [struck: domain][inserted: new] [struck: authority][inserted: or modified transmission facilities].

(3) [inserted: Transmission benefits.—] [inserted: The Commission shall require that tariffs or tariff revisions filed under this section are just and reasonable and allocate the costs of providing service to customers that benefit, in accordance with the cost-causation principle and at least roughly commensurate with the benefits, including through—]

(A) [inserted: improved reliability;]

(B) [inserted: reduced congestion;]

(C) [inserted: reduced power losses;]

(D) [inserted: greater carrying capacity that delivers improved reliability or reductions in the cost of delivered power;]

(E) [inserted: reduced operating reserve requirements; and]

(F) [inserted: improved access to generation that achieves reductions in the cost of delivered power.]

(4) [inserted: Ratepayer protection.—] [inserted: Customers that receive no benefit, or benefits that are trivial in relation to the costs sought to be allocated, from electric transmission facilities constructed or modified under this section shall not be involuntarily allocated any of the costs of those transmission facilities, provided, however, that nothing in this section shall prevent a transmitting utility from recovering such costs through voluntary agreement with its customers.]

(g) State law Nothing in this section precludes any person from constructing or modifying any transmission facility in accordance with State law.

(h) Coordination of Federal authorizations for transmission facilities

(1) In this subsection:

(A) The term “Federal authorization” means any authorization required under Federal law in order to site a transmission facility.

(B) The term “Federal authorization” includes such permits, special use authorizations, certifications, opinions, or other approvals as may be required under Federal law in order to site a transmission facility.

(C) [inserted: The term “Federal authorization” includes a certification under section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341) from a certifying authority (as defined in subsection (h) of that section) and any other permit, license, concurrence, or approval of a State administrative agency required under Federal law, other than the Coastal Zone Management Act of 1972 (16 U.S.C. 1451 et seq.), in order to site a transmission facility.]

(2) The Department of Energy shall act as the lead agency for purposes of coordinating all applicable Federal authorizations and related environmental reviews of the facility.

(3) To the maximum extent practicable under applicable Federal law, the [struck: Secretary][inserted: lead] [inserted: agency ]shall coordinate the Federal authorization and review process under this subsection with any Indian tribes, multistate entities, and State agencies that are responsible for conducting any separate permitting and environmental reviews of the facility, to ensure timely and efficient review and permit decisions.

(4)

(A) [struck: As][inserted: The] [struck: head of the ]lead agency, [struck: the Secretary, ]in consultation with agencies responsible for Federal authorizations and, as appropriate, with Indian tribes, multistate entities, and State agencies that are willing to coordinate their own separate permitting and environmental reviews with the Federal authorization and environmental reviews, shall establish prompt and binding intermediate milestones and ultimate deadlines for the review of, and Federal authorization decisions relating to, the proposed facility.

(B) The [struck: Secretary][inserted: lead] [inserted: agency ]shall ensure that, once an application has been submitted with such data as the [struck: Secretary][inserted: lead] [inserted: agency ]considers necessary, all permit decisions and related environmental reviews under all applicable Federal laws shall be completed—

(i) within 1 year; or

(ii) if a requirement of another provision of Federal law does not permit compliance with clause (i), as soon thereafter as is practicable.

(C) The [struck: Secretary][inserted: lead] [inserted: agency ]shall provide an expeditious pre-application mechanism for prospective applicants to confer with the agencies involved to have each such agency determine and communicate to the prospective applicant not later than 60 days after the prospective applicant submits a request for such information concerning—

(i) the likelihood of approval for a potential facility; and

(ii) key issues of concern to the agencies and public.

(5)

(A) [struck: As][inserted: The] lead agency[struck: head], [struck: the Secretary, ]in consultation with the affected agencies, shall prepare a single environmental review document, which shall be used as the basis for all decisions on the proposed project under Federal law.

(B) The [struck: Secretary][inserted: lead] [inserted: agency ]and the heads of other agencies shall streamline the review and permitting of transmission within corridors designated under section 503 of the Federal Land Policy and Management Act (43 U.S.C. 1763) by fully taking into account prior analyses and decisions relating to the corridors.

(C) The document shall include consideration by the relevant agencies of any applicable criteria or other matters as required under applicable law.

(6)

(A) If any agency has denied a Federal authorization required for a transmission facility, or has failed to act by the deadline established by the [struck: Secretary][inserted: lead] [inserted: agency ]pursuant to this section for deciding whether to issue the authorization, the applicant or any State in which the facility would be located may file an appeal with the President, who shall, in consultation with the affected agency, review the denial or failure to take action on the pending application.

(B) Based on the overall record and in consultation with the affected agency, the President may—

(i) issue the necessary authorization with any appropriate conditions; or

§ 824p(h)–(i)

(h)(6)(B)(ii)–(D)(iv) unchanged ·

(v) the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1701 et seq.).

(7)

(A) Not later than 18 months after August 8, 2005, the [struck: Secretary][inserted: lead] [inserted: agency ]shall issue any regulations necessary to implement this subsection.

(B)

(i) Not later than 1 year after August 8, 2005, the [struck: Secretary][inserted: lead] [inserted: agency ]and the heads of all Federal agencies with authority to issue Federal authorizations shall enter into a memorandum of understanding to ensure the timely and coordinated review and permitting of electricity transmission facilities.

(ii) Interested Indian tribes, multistate entities, and State agencies may enter the memorandum of understanding.

(C) The head of each Federal agency with authority to issue a Federal authorization shall designate a senior official responsible for, and dedicate sufficient other staff and resources to ensure, full implementation of the regulations and memorandum required under this paragraph.

(8)

(A) Each Federal land use authorization for an electricity transmission facility shall be issued—

(i) for a duration, as determined by the [struck: Secretary][inserted: lead agency], commensurate with the anticipated use of the facility; and

(ii) with appropriate authority to manage the right-of-way for reliability and environmental protection.

(B) On the expiration of the authorization (including an authorization issued before August 8, 2005), the authorization shall be reviewed for renewal taking fully into account reliance on such electricity infrastructure, recognizing the importance of the authorization for public health, safety, and economic welfare and as a legitimate use of Federal land.

(9) In exercising the responsibilities under this section, the [struck: Secretary][inserted: lead] [inserted: agency ]shall consult regularly with—

(A) the Federal Energy Regulatory Commission;

(B) electric reliability organizations (including related regional entities) approved by the Commission; and

(C) Transmission Organizations approved by the Commission.

(10) [inserted: Any order or action of a Federal agency or State administrative agency acting pursuant to Federal law to issue, condition, or deny a Federal authorization shall be subject to judicial review in the same courts in which an order of the Commission is subject to judicial review under section 313, and a court shall have jurisdiction over the action in accordance with the third sentence of subsection (b) of that section, the courts described in that section having original and exclusive jurisdiction over such actions.]

(i) Interstate compacts

(1) The consent of Congress is given for three or more contiguous States to enter into an interstate compact, subject to approval by Congress, establishing regional transmission siting agencies to—

§ 824p(i)–(k)

(i)(1)(A)–(B) unchanged ·

(2) The Secretary shall provide technical assistance to regional transmission siting agencies established under this subsection.

(3) The regional transmission siting agencies shall have the authority to review, certify, and permit siting of transmission facilities[struck: ,] [struck: including facilities in national interest electric transmission corridors ](other than facilities on property owned by the United States).

(4) The Commission shall have no authority to issue a permit for the construction or modification of an electric transmission facility within a State that is a party to a compact, unless the Secretary determines that the members of the compact are in disagreement after the later of—

(A) the date that is 1 year after the date on which the relevant application for the facility was filed[struck: ; and][inserted: .]

[struck: (B)] [struck: the date that is 1 year after the date on which the relevant national interest electric transmission corridor was designated by the Secretary under subsection (a).]

(j) Relationship to other laws

(1) Except as specifically provided, nothing in this section affects any requirement of an environmental law of the United States, including the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).

(2) Subsection (h)(6) shall not apply to any unit of the National Park System, the National Wildlife Refuge System, the National Wild and Scenic Rivers System, the National Trails System, the National Wilderness Preservation System, or a National Monument.

(k) [struck: ERCOT][inserted: Jurisdiction.—]

(1) [inserted: ERCOT.—] [inserted: This section shall not apply within the area referred to in section 212(k)(2)(A).]

(2) [inserted: Other utilities.—]

(A) [inserted: In general.—] [inserted: For the purposes of this section, the Commission shall have jurisdiction over all transmitting utilities, including transmitting utilities described in section 201(f), but excluding any ERCOT utility (as defined in section 212(k)(2)(B)) and any exempt transmitting utility that does not voluntarily subject itself to Commission jurisdiction for the purposes of this section.]

(B) [inserted: Clarification.—] [inserted: Being subject to Commission jurisdiction for the purposes of this section shall not make an entity described in section 201(f) a public utility for the purposes of section 201(e).]

[struck: This section shall not apply within the area referred to in section 824k(k)(2)(A) of this title.]