Title 30 · Mineral Lands and MiningEnergy
Changes to 30 U.S.C. § 1003
S. 5653 · Bipartisan American Affordability and Jobs Act of 2026 · Introduced The text as a member of Congress first filed it. Most bills never get further than this.
In committee · step 2 of 5
30 U.S.C. § 1003 Leasing procedures
4 changes the bill asks for here, 4 carried out
- Carried out:
in paragraph (2), by striking
2 years
and insertingyear
; and - Carried out:
by adding at the end the following:
(5) Replacement sales.— If a lease sale under paragraph (1) for a year is cancelled or delayed, the Secretary shall conduct a replacement sale during the same year..
- Carried out:
Section 4 of the Geothermal Steam Act of 1970 (30 U.S.C. 1003) is amended by adding at the end the following:
(h) Deadlines for consideration of geothermal drilling permits.— (1) Notice.— Not later than 30 days after the date on which the Secretary receives an application for any geothermal drilling permit, the Secretary shall— (A) provide written notice to the applicant that the …
- Carried out:
Section 4 of the Geothermal Steam Act of 1970 (30 U.S.C. 1003) (as amended by section 2223(b)) is amended by adding at the end the following:
(i) Effect of pending civil actions on processing applications relating to geothermal leasing.— (1) Definition of authorization.— In this subsection, the term “authorization” means any license, permit, approval, finding, determination, or other administrative decision issued by …
§ 1003(b)–(d)
Start of § 1003 to (b) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (b)(1) | (1) In general | (1) In general | ||
| Except as otherwise specifically provided by this chapter, all land to be leased that is not subject to leasing under subsection (c) shall be leased as provided in this subsection to the highest responsible qualified bidder, as determined by the Secretary. | Except as otherwise specifically provided by this chapter, all land to be leased that is not subject to leasing under subsection (c) shall be leased as provided in this subsection to the highest responsible qualified bidder, as determined by the Secretary. | |||
| (b)(2) | (2) Competitive lease sales | (2) Competitive lease sales | ||
| The Secretary shall hold a competitive lease sale at least once every | The Secretary shall hold a competitive lease sale at least once every [inserted: year] for land in a State that has nominations pending under subsection (a) if the land is otherwise available for leasing. | |||
| (b)(3) | (3) Lands subject to mining claims | (3) Lands subject to mining claims | ||
| Lands that are subject to a mining claim for which a plan of operations has been approved by the relevant Federal land management agency may be available for noncompetitive leasing under this section to the mining claim holder. | Lands that are subject to a mining claim for which a plan of operations has been approved by the relevant Federal land management agency may be available for noncompetitive leasing under this section to the mining claim holder. | |||
| (b)(4) | (4) Land subject to oil and gas lease | (4) Land subject to oil and gas lease | ||
| Land under an oil and gas lease issued pursuant to the Mineral Leasing Act (30 U.S.C. 181 et seq.) or the Mineral Leasing Act for Acquired Lands (30 U.S.C. 351 et seq.) that is subject to an approved application for permit to drill and from which oil and gas production is occurring may be available for noncompetitive leasing under subsection (c) by the holder of the oil and gas lease— | Land under an oil and gas lease issued pursuant to the Mineral Leasing Act (30 U.S.C. 181 et seq.) or the Mineral Leasing Act for Acquired Lands (30 U.S.C. 351 et seq.) that is subject to an approved application for permit to drill and from which oil and gas production is occurring may be available for noncompetitive leasing under subsection (c) by the holder of the oil and gas lease— | |||
| (b)(4)(A) | (A) | (A) | ||
| on a determination that geothermal energy will be produced from a well producing or capable of producing oil and gas; and | on a determination that geothermal energy will be produced from a well producing or capable of producing oil and gas; and | |||
| (b)(4)(B) | (B) | (B) | ||
| to provide for the coproduction of geothermal energy with oil and gas. | to provide for the coproduction of geothermal energy with oil and gas. | |||
| (b)(5) | (5) [inserted: Replacement sales.—] | |||
| [inserted: If a lease sale under paragraph (1) for a year is cancelled or delayed, the Secretary shall conduct a replacement sale during the same year.] | ||||
| (c) | (c) Noncompetitive leasing | (c) Noncompetitive leasing | ||
| The Secretary shall make available for a period of 2 years for noncompetitive leasing any tract for which a competitive lease sale is held, but for which the Secretary does not receive any bids in a competitive lease sale. | The Secretary shall make available for a period of 2 years for noncompetitive leasing any tract for which a competitive lease sale is held, but for which the Secretary does not receive any bids in a competitive lease sale. | |||
| (d) | (d) Pending lease applications | (d) Pending lease applications | ||
§ 1003(g)–(i)
(d)(1)–(g) unchanged
| Where | Mark | The Code now | Mark | As the bill would leave it |
|---|---|---|---|---|
| (g)(1) | (1) In general | (1) In general | ||
| Subject to paragraph (2), a geothermal lease for the direct use of geothermal resources shall cover not more than the quantity of acreage determined by the Secretary to be reasonably necessary for the proposed use. | Subject to paragraph (2), a geothermal lease for the direct use of geothermal resources shall cover not more than the quantity of acreage determined by the Secretary to be reasonably necessary for the proposed use. | |||
| (g)(2) | (2) Limitations | (2) Limitations | ||
| The quantity of acreage covered by the lease shall not exceed the limitations established under section 1006 of this title. | The quantity of acreage covered by the lease shall not exceed the limitations established under section 1006 of this title. | |||
| (h) | (h) [inserted: Deadlines for consideration of geothermal drilling permits.—] | |||
| (h)(1) | (1) [inserted: Notice.—] | |||
| [inserted: Not later than 30 days after the date on which the Secretary receives an application for any geothermal drilling permit, the Secretary shall—] | ||||
| (h)(1)(A) | (A) [inserted: ] | |||
| [inserted: provide written notice to the applicant that the application is complete; or] | ||||
| (h)(1)(B) | (B) [inserted: ] | |||
| [inserted: notify the applicant that information is missing and specify any information that is required to be submitted for the application to be complete.] | ||||
| (h)(2) | (2) [inserted: Issuance or deferral.—] | |||
| (h)(2)(A) | (A) [inserted: In general.—] | |||
| [inserted: Not later than 30 days after the Secretary has provided written notice to an applicant for a geothermal drilling permit that the application for such permit is complete pursuant to paragraph (1)(A), the Secretary shall—] | ||||
| (h)(2)(A)(i) | (i) [inserted: ] | |||
| [inserted: issue the permit, if the requirements under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and other applicable law have been completed within the timeframe; or] | ||||
| (h)(2)(A)(ii) | (ii) [inserted: ] | |||
| [inserted: defer the decision on the permit and provide to the applicant a notice—] | ||||
| (h)(2)(A)(ii)(I) | (I) [inserted: ] | |||
| [inserted: that specifies any steps that the applicant could take for the permit to be issued; and] | ||||
| (h)(2)(A)(ii)(II) | (II) [inserted: ] | |||
| [inserted: that includes a list of actions that need to be taken by the agency to comply with applicable law, together with timelines and deadlines for taking those actions, which shall not exceed the deadlines specified in section 107(g) of the National Environmental Policy Act of 1969 (42 U.S.C. 4336a(g)).] | ||||
| (h)(2)(B) | (B) [inserted: Deadline for deferred decisions.—] | |||
| [inserted: If the Secretary defers a decision on a permit under subparagraph (A)(ii), the Secretary shall issue a decision on the permit not later than 10 days after—] | ||||
| (h)(2)(B)(i) | (i) [inserted: ] | |||
| [inserted: the applicant takes any steps specified under subparagraph (A)(ii)(I); and] | ||||
| (h)(2)(B)(ii) | (ii) [inserted: ] | |||
| [inserted: the agency takes the actions described in subparagraph (A)(ii)(II) in accordance with any applicable timelines and deadlines.] | ||||
| (i) | (i) [inserted: Effect of pending civil actions on processing applications relating to geothermal leasing.—] | |||
| (i)(1) | (1) [inserted: Definition of authorization.—] | |||
| [inserted: In this subsection, the term “authorization” means any license, permit, approval, finding, determination, or other administrative decision issued by a Federal agency, or any interagency consultation, that is required or authorized under Federal law (including regulations) in order to site, construct, reconstruct, or commence operation of a geothermal project administered by a Federal agency.] | ||||
| (i)(2) | (2) [inserted: Requirement to process applications.—] | |||
| [inserted: Notwithstanding any pending civil action that affects an application for a geothermal drilling permit, sundry notice, notice to proceed, right-of-way, or any other authorization under a valid existing geothermal lease, the Secretary shall, unless a Federal court vacates or provides injunctive relief for the applicable geothermal lease, geothermal drilling permit, sundry notice, notice to proceed, right-of-way, or other authorization, approve and issue, or deny, each such application not later than 60 days after completing all requirements under applicable Federal laws (including regulations), including the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.), the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.), and division A of subtitle III of title 54, United States Code.] | ||||
| (i)(3) | (3) [inserted: No new authority for Federal courts.—] | |||
| [inserted: Nothing in this subsection modifies any existing authority of a Federal court to vacate or provide injunctive relief for a geothermal lease, geothermal drilling permit, sundry notice, notice to proceed, right-of-way, or other authorization.] | ||||