Title 42 · The Public Health and Welfare

Changes to 42 U.S.C. § 15942

S. 5653 · Bipartisan American Affordability and Jobs Act of 2026 ·

In committee · step 2 of 5

Sections are cited like “7 U.S.C. § 2012”: 7 of the , 2012.

42 U.S.C. § 15942 NEPA review

+19 −8Shown
More for 42 U.S.C. § 15942
Read § 15942
8 changes the bill asks for here, 8 carried out
  1. Carried out:

    by striking subsection (a) and inserting the following:(a) NEPA Review.— Action by the Secretary of the Interior in managing public land, or the Secretary of Agriculture in managing National Forest System land, with respect to an activity described in subsection (b) shall not be considered a major Federal action under the National …

  2. Carried out:

    in paragraph (2), by striking or gas and inserting , gas, or geothermal;

  3. Carried out:

    in paragraph (3), by striking or gas and inserting , gas, or geothermal;

  4. Carried out:

    by striking NEPA each place it appears and inserting the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.);

  5. Carried out:

    in paragraph (4), by striking 5 and inserting 10;

  6. Carried out:

    by redesignating paragraph (5) as paragraph (6); and

  7. Carried out:

    by inserting after paragraph (4) the following:(5) For the purposes of geothermal, placement of an electric transmission or distribution line of not more than 20 miles in length in an approved right-of-way corridor, so long as the corridor was approved within 10 years prior to the date of placement of the transmission or distribution line.; and

  8. Carried out:

    by adding at the end the following:(c) Effect.— (1) In general.— Nothing in this section affects the requirement for a drilling permit for the conduct of any activity described in subsection (b) pursuant to— (A) the Mineral Leasing Act (30 U.S.C. 181 et seq.); or (B) the Geothermal Steam Act of 1970 (30 U.S.C. …

§ 15942(a)–(c)

§ 15942. NEPA review

(a) NEPA [struck: review][inserted: Review.—] Action by the Secretary of the Interior in managing [struck: the ]public [struck: lands][inserted: land], or the Secretary of Agriculture in managing National Forest System [struck: Lands][inserted: land], with respect to [struck: any][inserted: an] [struck: of][inserted: activity] [struck: the activities ]described in subsection (b) shall [inserted: not ]be [struck: subject][inserted: considered] [struck: to ]a [struck: rebuttable][inserted: major] [struck: presumption][inserted: Federal] [struck: that][inserted: action] [struck: the use of a categorical exclusion ]under the National Environmental Policy Act of 1969 [struck: [][inserted: (]42 U.S.C. 4321 et seq.[struck: ] (NEPA]) [struck: would apply ]if the activity is conducted pursuant to the Mineral Leasing Act [struck: [][inserted: (]30 U.S.C. 181 et seq.[struck: ]][inserted: )] [inserted: or the Geothermal Steam Act of 1970 (30 U.S.C. 1001 et seq.) ]for the purpose of exploration or development of oil[inserted: ,] [inserted: gas, ]or [struck: gas][inserted: geothermal resources].

(b) Activities described The activities referred to in subsection (a) are the following:

(1) Individual surface disturbances of less than 5 acres so long as the total surface disturbance on the lease is not greater than 150 acres and site-specific analysis in a document prepared pursuant to [struck: NEPA][inserted: the] [inserted: National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) ]has been previously completed.

(2) Drilling an oil[inserted: ,] [inserted: gas, ]or [struck: gas][inserted: geothermal] well at a location or well pad site at which drilling has occurred previously within 5 years prior to the date of spudding the well.

(3) Drilling an oil[inserted: ,] [inserted: gas, ]or [struck: gas][inserted: geothermal] well within a developed field for which an approved land use plan or any environmental document prepared pursuant to [struck: NEPA][inserted: the] [inserted: National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) ]analyzed such drilling as a reasonably foreseeable activity, so long as such plan or document was approved within 5 years prior to the date of spudding the well.

(4) Placement of a pipeline in an approved right-of-way corridor, so long as the corridor was approved within [struck: 5][inserted: 10] years prior to the date of placement of the pipeline.

(5) [inserted: For the purposes of geothermal, placement of an electric transmission or distribution line of not more than 20 miles in length in an approved right-of-way corridor, so long as the corridor was approved within 10 years prior to the date of placement of the transmission or distribution line.]

[struck: (5)] [inserted: (6)] Maintenance of a minor activity, other than any construction or major renovation or a building or facility.

(c) [inserted: Effect.—]

(1) [inserted: In general.—] [inserted: Nothing in this section affects the requirement for a drilling permit for the conduct of any activity described in subsection (b) pursuant to—]

(A) [inserted: the Mineral Leasing Act (30 U.S.C. 181 et seq.); or]

(B) [inserted: the Geothermal Steam Act of 1970 (30 U.S.C. 1001 et seq.).]

(2) [inserted: Requirements.—] [inserted: Notwithstanding section 17(p)(2)(A) of the Mineral Leasing Act (30 U.S.C. 226(p)(2)(A)) or subsection (h)(2)(A)(i) of section 4 of the Geothermal Steam Act of 1970 (30 U.S.C. 1003), activities described in subsection (b) that require a drilling permit under the Mineral Leasing Act (30 U.S.C. 1001 et seq.) or a geothermal drilling permit under the Geothermal Steam Act of 1970 (30 U.S.C. 1001 et seq.) shall not have any requirements under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).]