40 U.S.C. § 3143 · 40, 3143 of the

§ 3143. Termination of work on failure to pay agreed wages

Every contract within the scope of this subchapter shall contain a provision that if the contracting officer finds that any laborer or mechanic employed by the contractor or any subcontractor directly on the site of the work covered by the contract has been or is being paid a rate of wages less than the rate of wages required by the contract to be paid, the Federal Government by written notice to the contractor may terminate the contractor’s right to proceed with the work or the part of the work as to which there has been a failure to pay the required wages. The Government may have the work completed, by contract or otherwise, and the contractor and the contractor’s sureties shall be liable to the Government for any excess costs the Government incurs.

Where this text comes from

The public laws () that wrote and changed it, and where each is printed in the Statutes at Large ().

(Pub. L. 107–217, Aug. 21, 2002, 116 Stat. 1151.)

Notes (1)

Historical and Revision Notes

RevisedSection Source (U.S. Code) Source (Statutes at Large)

3143 40:276a–1. Mar. 3, 1931, ch. 411, § 2, 46 Stat. 1494; Aug. 30, 1935, ch. 825, 49 Stat. 1012.

The words “The Government may have the work completed” are substituted for “and to prosecute the work to completion . . . thereby” for clarity.

Would change this section

No bill we know of would change this section.

Versions

Each is an official edition of the Code (a ), up to date through the named.

  • Through Public Law 119-138, Current