§ 4707. Remission of liquidated damages

When a contract made on behalf of the Federal Government by the head of a Federal agency, or by an authorized officer of the agency, includes a provision for liquidated damages for delay, the Secretary of the Treasury on recommendation of the head of the agency may remit any part of the damages as the Secretary of the Treasury believes is just and equitable.

Where this text comes from

The public laws () that wrote and changed it, and where each is printed in the Statutes at Large ().

(Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3799.)

Notes (1)

Historical and Revision Notes

RevisedSection Source (U.S. Code) Source (Statutes at Large)

4707 41:256a. Sept. 5, 1950, ch. 849, § 10(a), 64 Stat. 591; Pub. L. 104–316, title II, § 202(u), Oct. 19, 1996, 110 Stat. 3845.

Would change this section

No bill we know of would change this section.

Versions

Each is an official edition of the Code (a ), up to date through the named.

  • Through Public Law 119-138, Current