Federal Power Act § 224 Ensuring data centers pay their fair share New section

+32 −0Shown
More for Federal Power Act § 224
Every bill that would add § 224
1 change the bill asks for here, 1 carried out
  1. Carried out:

    The Federal Power Act is amended by inserting after section 223 (16 U.S.C. 824w) the following:224. Ensuring data centers pay their fair share (a) Authority.— (1) In general.— Notwithstanding subsection (a) and subsection (b)(1) of section 201, and subject to subsection (d), the Commission shall, beginning on the date that is 90 days after the date of enactment of this section, have the sole authority to approve rates and charges for the retail sale of electric energy from a covered electric utility to a data center. (2) Just and reasonable requirement.— All rates and charges approved by the Commission pursuant to paragraph (1) shall be just and reasonable, and not unduly discriminatory or preferential. If the Commission finds, after a hearing held upon its own motion or upon complaint, that any rate or charge approved by the Commission is unjust or unreasonable, or unduly discriminatory or preferential, the Commission shall fix a new rate or charge that is just and reasonable and not unduly discriminatory or preferential. (b) Full allocation of costs.— Any rate or charge approved pursuant to subsection (a) shall include— (1) the full costs of constructing, upgrading, and expanding any transmission or distribution facility to facilitate the interconnection of data centers to the bulk-power system; (2) the full costs of constructing, upgrading, and expanding any transmission or distribution facility to ensure the reliability of the bulk-power system during periods of increasing demand for electric energy from data centers; and (3) the full costs of constructing, upgrading, and expanding any generating facility to facilitate the reliability of the bulk-power system during periods of increasing demand for electric energy from data centers. (c) Prohibition on cost-shifting.— No covered electric utility may shift the costs described in paragraphs (1) through (3) of subsection (b) onto their retail rates or charges for any customer other than a data center. (d) Inapplicability.— This section shall not apply within the area referred to in section 212(k)(2)(A). (e) Definitions.— In this section: (1) Commission.— The term Commission means the Federal Energy Regulatory Commission. (2) Covered electric utility.— The term covered electric utility means a person that sells electric energy, except— (A) an electric cooperative described in section 201(f); (B) an electric utility that is owned or operated by a State or political subdivision thereof; (C) the Tennessee Valley Authority; and (D) each Federal power marketing administration..

§ 224(a)–(e)

WhereMarkThe Code nowMarkAs the bill would leave it
§ 224. [inserted: Ensuring data centers pay their fair share]
(a)(a) [inserted: Authority.—]
(a)(1)(1) [inserted: In general.—]
[inserted: Notwithstanding subsection (a) and subsection (b)(1) of section 201, and subject to subsection (d), the Commission shall, beginning on the date that is 90 days after the date of enactment of this section, have the sole authority to approve rates and charges for the retail sale of electric energy from a covered electric utility to a data center.]
(a)(2)(2) [inserted: Just and reasonable requirement.—]
[inserted: All rates and charges approved by the Commission pursuant to paragraph (1) shall be just and reasonable, and not unduly discriminatory or preferential. If the Commission finds, after a hearing held upon its own motion or upon complaint, that any rate or charge approved by the Commission is unjust or unreasonable, or unduly discriminatory or preferential, the Commission shall fix a new rate or charge that is just and reasonable and not unduly discriminatory or preferential.]
(b)(b) [inserted: Full allocation of costs.—]
[inserted: Any rate or charge approved pursuant to subsection (a) shall include—]
(b)(1)(1) [inserted: ]
[inserted: the full costs of constructing, upgrading, and expanding any transmission or distribution facility to facilitate the interconnection of data centers to the bulk-power system;]
(b)(2)(2) [inserted: ]
[inserted: the full costs of constructing, upgrading, and expanding any transmission or distribution facility to ensure the reliability of the bulk-power system during periods of increasing demand for electric energy from data centers; and]
(b)(3)(3) [inserted: ]
[inserted: the full costs of constructing, upgrading, and expanding any generating facility to facilitate the reliability of the bulk-power system during periods of increasing demand for electric energy from data centers.]
(c)(c) [inserted: Prohibition on cost-shifting.—]
[inserted: No covered electric utility may shift the costs described in paragraphs (1) through (3) of subsection (b) onto their retail rates or charges for any customer other than a data center.]
(d)(d) [inserted: Inapplicability.—]
[inserted: This section shall not apply within the area referred to in section 212(k)(2)(A).]
(e)(e) [inserted: Definitions.—]
[inserted: In this section:]
(e)(1)(1) [inserted: Commission.—]
[inserted: The term “Commission” means the Federal Energy Regulatory Commission.]
(e)(2)(2) [inserted: Covered electric utility.—]
[inserted: The term “covered electric utility” means a person that sells electric energy, except—]
(e)(2)(A)(A) [inserted: ]
[inserted: an electric cooperative described in section 201(f);]
(e)(2)(B)(B) [inserted: ]
[inserted: an electric utility that is owned or operated by a State or political subdivision thereof;]
(e)(2)(C)(C) [inserted: ]
[inserted: the Tennessee Valley Authority; and]
(e)(2)(D)(D) [inserted: ]
[inserted: each Federal power marketing administration.]