15 U.S.C. § 717f Construction, extension, or abandonment of facilities
1 change the bill asks for here, 1 carried out
- Carried out:
Section 7 of the Natural Gas Act (15 U.S.C. 717f) is amended by adding at the end the following:
(i) Covered pipeline activities.— (1) Definitions.— In this subsection: (A) Covered activity.— The term “covered activity” means any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation, looping, compression, capacity-enhancement …
§ 717f(g)–(i)
Start of § 717f to (f)(2) unchanged ·
(g) Certificate of public convenience and necessity for service of area already being served Nothing contained in this section shall be construed as a limitation upon the power of the Commission to grant certificates of public convenience and necessity for service of an area already being served by another natural-gas company.
(h) Right of eminent domain for construction of pipelines, etc. When any holder of a certificate of public convenience and necessity cannot acquire by contract, or is unable to agree with the owner of property to the compensation to be paid for, the necessary right-of-way to construct, operate, and maintain a pipe line or pipe lines for the transportation of natural gas, and the necessary land or other property, in addition to right-of-way, for the location of compressor stations, pressure apparatus, or other stations or equipment necessary to the proper operation of such pipe line or pipe lines, it may acquire the same by the exercise of the right of eminent domain in the district court of the United States for the district in which such property may be located, or in the State courts. The practice and procedure in any action or proceeding for that purpose in the district court of the United States shall conform as nearly as may be with the practice and procedure in similar action or proceeding in the courts of the State where the property is situated: Provided, That the United States district courts shall only have jurisdiction of cases when the amount claimed by the owner of the property to be condemned exceeds $3,000.
(i) [inserted: Covered pipeline activities.—]
(1) [inserted: Definitions.—] [inserted: In this subsection:]
(A) [inserted: Covered activity.—] [inserted: The term “covered activity” means any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation, looping, compression, capacity-enhancement project, or addition to a covered facility.]
(B) [inserted: Covered area.—] [inserted: The term “covered area” means—]
(i) [inserted: an existing right-of-way; and]
(ii) [inserted: the footprint of original construction previously authorized and environmentally reviewed under this Act, together with any minimum additional area adjacent to an existing right-of-way that is necessary to complete a covered activity.]
(C) [inserted: Covered facility.—] [inserted: The term “covered facility” means an existing interstate natural gas pipeline or associated infrastructure, including a compressor station, meter station, regulator station, valve site, launcher, receiver, storage-related facility, or similar facility located within a covered area.]
(2) [inserted: Environmental review.—] [inserted: A covered activity and any Federal agency action authorizing that covered activity—]
(A) [inserted: shall not be considered a major Federal action under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) if the covered activity remains within a covered area; and]
(B) [inserted: shall not be considered an undertaking for purposes of section 306108 of title 54, United States Code, if the covered activity remains within a covered area.]
(3) [inserted: Rule of construction.—] [inserted: Nothing in this subsection affects the applicability of any requirement under—]
(A) [inserted: the Federal Water Pollution Control Act (33 U.S.C. 1251 et seq.) (commonly known as the “Clean Water Act”);]
(B) [inserted: the Clean Air Act (42 U.S.C. 7401 et seq.); or]
(C) [inserted: any other applicable Federal law not expressly addressed by this subsection.]
15 U.S.C. § 4659 Additional authorities
1 change the bill asks for here, 1 carried out
- Carried out:
Section 9909(c)(1) of the William M. (Mac) Thornberry National Defense Authorization Act for Fiscal Year 2021 (15 U.S.C. 4659(c)(1)) is amended by striking
section 111 of NEPA (42 U.S.C. 4336e)
and insertingsection 3 of NEPA
.
§ 4659(b)–(d)
Start of § 4659 to (a)(7) unchanged ·
(b) Requirement Any funds received from a payment made by a person or entity pursuant to subsection (a)(3) shall be credited to and merged with the account from which support to the person or entity was made1
(c) Lead Federal agency and cooperating agencies
(1) Definition In this subsection, the term “lead agency” has the meaning given the term in section [struck: 111][inserted: 3] of NEPA[struck: (42 U].[struck: S.C. 4336e).]
(2) Option to serve as lead agency With respect to a covered activity that is a major Federal action under NEPA, and with respect to which the Department of Commerce is authorized or required by law to issue an authorization or take action for or relating to that covered activity, the Department of Commerce shall have the first right to serve as the lead agency with respect to that covered activity under NEPA.
(d) Categorical exclusions
Rest of § 4659 unchanged ·
16 U.S.C. § 796 Definitions
1 change the bill asks for here, 1 carried out
- Carried out:
Section 3 of the Federal Power Act (16 U.S.C. 796) is amended by adding at the end the following:
(30) Qualifying behind-the-meter distributed energy system facility; qualifying BTM DES facility.— The term “qualifying behind-the-meter distributed energy system facility” or “qualifying BTM DES facility” means a facility that— (A) is an energy storage system (including a …
§ 796(28)–(31)
Start of § 796 to (28)(A) unchanged ·
(B) to ensure nondiscriminatory access to the facilities.3
(29) Transmission organization.— The term “Transmission Organization” means a Regional Transmission Organization, Independent System Operator, independent transmission provider, or other transmission organization finally approved by the Commission for the operation of transmission facilities.
(30) [inserted: Qualifying behind-the-meter distributed energy system facility; qualifying BTM DES facility.—] [inserted: The term “qualifying behind-the-meter distributed energy system facility” or “qualifying BTM DES facility” means a facility that—]
(A) [inserted: is an energy storage system (including a battery energy storage system), a fuel cell system, a generator, or other resource—]
(i) [inserted: that can be brought online within 15 minutes of being called on for deployment; and]
(ii) [inserted: the output of which can be dispatched and adjusted at the signal of the system operator;]
(B) [inserted: is located behind the meter of a retail customer of a distribution utility (as defined in section 217(a));]
(C) [inserted: has a rated capacity of not less than 5 kilowatts; and]
(D) [inserted: maintains metering and telemetry capabilities that—]
(i) [inserted: are sufficient to dispatch the facility, account for withdrawals from and injections to the grid, and communicate all relevant operational data from the facility; and]
(ii) [inserted: are not required to include equipment owned or installed by the distribution utility (as so defined), and may include the use of device-level equipment, including inverters.]
(31) [inserted: Qualifying behind-the-meter distributed energy system aggregation; qualifying BTM DES aggregation.—] [inserted: The term “qualifying behind-the-meter distributed energy system aggregation” or “qualifying BTM DES aggregation” means an aggregation of 2 or more qualifying BTM DES facilities—]
(A) [inserted: with a combined capacity of not less than 100 kilowatts; and]
(B) [inserted: that maintains aggregation-level metering and telemetry capabilities sufficient to facilitate the dispatch and market settlement of the aggregation.]
16 U.S.C. § 803 Conditions of license generally
2 changes the bill asks for here, 2 carried out
- Carried out:
Section 10(b) of the Federal Power Act (16 U.S.C. 803(b)) is amended by adding at the end the following: Except as previously provided in this subsection, the Commission shall require prior approval of a
substantial alteration or addition
to project works or to project operations consisting of any significant modification of the project works or operation of the project that is not in conformity with the project plans previously approved by the Commission. The Commission shall not require approval of any alteration or addition as determined pursuant to regulations promulgated under section 2233(c) of the Bipartisan American Affordability and Jobs Act of 2026 or any temporary variance to the project operations necessitated by circumstances beyond the reasonable control of the licensee, including extreme weather, natural disasters, equipment failures, or other unforeseen circumstances.. - Carried out:
Section 10(c) of the Federal Power Act (16 U.S.C. 803(c)) is amended by inserting after the first sentence the following:
The Commission shall not require approval or an amendment to a project license for any routine maintenance, repair, or replacement of any portion of a project works necessary to maintain the project works in accordance with this subsection.
.
§ 803(a)–(e)
Start of § 803 to (a)(2)(C) unchanged ·
(3) Upon receipt of an application for a license, the Commission shall solicit recommendations from the agencies and Indian tribes identified in subparagraphs (A) and (B) of paragraph (2) for proposed terms and conditions for the Commission’s consideration for inclusion in the license.
(b) Alterations in project works That except when emergency shall require for the protection of navigation, life, health, or property, no substantial alteration or addition not in conformity with the approved plans shall be made to any dam or other project works constructed hereunder of an installed capacity in excess of two thousand horsepower without the prior approval of the Commission; and any emergency alteration or addition so made shall thereafter be subject to such modification and change as the Commission may direct.[inserted: Except as previously provided in this subsection, the Commission shall require prior approval of a “substantial alteration or addition” to project works or to project operations consisting of any significant modification of the project works or operation of the project that is not in conformity with the project plans previously approved by the Commission. The Commission shall not require approval of any alteration or addition as determined pursuant to regulations promulgated under section 2233(c) of the Bipartisan American Affordability and Jobs Act of 2026 or any temporary variance to the project operations necessitated by circumstances beyond the reasonable control of the licensee, including extreme weather, natural disasters, equipment failures, or other unforeseen circumstances.]
(c) Maintenance and repair of project works; liability of licensee for damages That the licensee shall maintain the project works in a condition of repair adequate for the purposes of navigation and for the efficient operation of said works in the development and transmission of power, shall make all necessary renewals and replacements, shall establish and maintain adequate depreciation reserves for such purposes, shall so maintain, and operate said works as not to impair navigation, and shall conform to such rules and regulations as the Commission may from time to time prescribe for the protection of life, health, and property. [inserted: The Commission shall not require approval or an amendment to a project license for any routine maintenance, repair, or replacement of any portion of a project works necessary to maintain the project works in accordance with this subsection. ]Each licensee hereunder shall be liable for all damages occasioned to the property of others by the construction, maintenance, or operation of the project works or of the works appurtenant or accessory thereto, constructed under the license and in no event shall the United States be liable therefor.
(d) Amortization reserves That after the first twenty years of operation, out of surplus earned thereafter, if any, accumulated in excess of a specified reasonable rate of return upon the net investment of a licensee in any project or projects under license, the licensee shall establish and maintain amortization reserves, which reserves shall, in the discretion of the Commission, be held until the termination of the license or be applied from time to time in reduction of the net investment. Such specified rate of return and the proportion of such surplus earnings to be paid into and held in such reserves shall be set forth in the license. For any new license issued under section 808 of this title, the amortization reserves under this subsection shall be maintained on and after the effective date of such new license.
(e) Annual charges payable by licensees; maximum rates; application; review and report to Congress
Rest of § 803 unchanged ·
Federal Power Act § 37 Licensing of micro hydrokinetic energy projects New section
1 change the bill asks for here, 1 carried out
- Carried out:
Part I of the Federal Power Act (16 U.S.C. 792 et seq.) is amended by adding at the end the following:37. Licensing of micro hydrokinetic energy projects (a) Definition of micro hydrokinetic energy project.— In this section, the term
micro hydrokinetic energy project
— (1) means a project that— (A) has an installed capacity of not more than 5 megawatts; and (B) converts to electric energy the hydrokinetic energy from a generator driven by a turbine from— (i) waves, tides, or currents in oceans, estuaries, or tidal areas; or (ii) free flowing water in rivers, lakes, streams, or man-made channels; and (2) does not include a project that impounds water to generate electricity. (b) Authorization.— The Commission may issue a license in accordance with this section for a term of not less than 10, and not more than 20, years for the construction, operation, and maintenance of project works for a micro hydrokinetic energy project. (c) Expedited licensing process.— (1) Notification of intent.— (A) Filing of notification.— An applicant for a license under this section shall commence the licensing process by filing a notification of intent with the Commission. (B) Existing license deadline.— Notwithstanding section 15(b)(1), an applicant for a license under this section shall file a notification of intent under subparagraph (A) not later than 2 years before the expiration of an existing license, if applicable. (2) Filing of application.— (A) In general.— Except as provided in subparagraph (B), an applicant for a license under this section shall submit to the Commission an application not later than 1 year after the date on which the applicant files a notification of intent under paragraph (1). (B) Existing license deadline.— Notwithstanding section 15(c)(1), an applicant for a license under this section shall file an application with the Commission not later than 1 year before the date of expiration of the term of an existing license, if applicable. (3) Deadline for issuance.— The Commission shall take final action on an application for a license under this section not later than 1 year after the date on which the application is filed under paragraph (2). (4) Schedule for final action.— To the extent reasonably practicable, the Commission and any applicable conditioning or permitting agencies shall establish, with respect to each micro hydrokinetic energy project that is the subject of a notification of intent to apply for a license under this section, a joint schedule that permits the timely completion of decisions required to be made with respect to, and the timely issuance of, authorizations required under Federal law by the Commission and the conditioning or permitting agencies, subject to the requirement that any joint schedule established under this paragraph shall comply with the deadline for final action established under paragraph (3). (d) Regulations.— (1) In general.— Not later than 180 days after the date of enactment of this section, the Commission shall promulgate regulations to implement this section in a manner that expedites the deployment of micro hydrokinetic energy projects while ensuring the safe operation of the micro hydrokinetic energy project in compliance with applicable Federal and State laws. (2) Inclusion.— The regulations promulgated under paragraph (1) shall provide for the use of 1 or more categorical exclusions, including allowing for extraordinary circumstances under which the categorical exclusion shall not be available, under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for low disturbance activities necessary for micro hydrokinetic energy projects. (e) Report to congress.— The Commission shall submit to Congress a report describing the impacts of the micro hydrokinetic energy projects licensed under this section on the environment, the economy, and the reliability and affordability of electricity not later than the earlier of— (1) the date that is 5 years after the date of enactment of this section; and (2) the date on which the first 50 micro hydrokinetic energy projects licensed under this section have been operational for not less than 1 year. (f) Savings clause.— Nothing in this section affects any authority of the Commission, at the election of an applicant, to license the construction, operation, and maintenance of project works for a micro hydrokinetic energy project under any other provision of this part..
§ 37(a)–(f)
§ 37. [inserted: Licensing of micro hydrokinetic energy projects]
(a) [inserted: Definition of micro hydrokinetic energy project.—] [inserted: In this section, the term “micro hydrokinetic energy project”—]
(1) [inserted: means a project that—]
(A) [inserted: has an installed capacity of not more than 5 megawatts; and]
(B) [inserted: converts to electric energy the hydrokinetic energy from a generator driven by a turbine from—]
(i) [inserted: waves, tides, or currents in oceans, estuaries, or tidal areas; or]
(ii) [inserted: free flowing water in rivers, lakes, streams, or man-made channels; and]
(2) [inserted: does not include a project that impounds water to generate electricity.]
(b) [inserted: Authorization.—] [inserted: The Commission may issue a license in accordance with this section for a term of not less than 10, and not more than 20, years for the construction, operation, and maintenance of project works for a micro hydrokinetic energy project.]
(c) [inserted: Expedited licensing process.—]
(1) [inserted: Notification of intent.—]
(A) [inserted: Filing of notification.—] [inserted: An applicant for a license under this section shall commence the licensing process by filing a notification of intent with the Commission.]
(B) [inserted: Existing license deadline.—] [inserted: Notwithstanding section 15(b)(1), an applicant for a license under this section shall file a notification of intent under subparagraph (A) not later than 2 years before the expiration of an existing license, if applicable.]
(2) [inserted: Filing of application.—]
(A) [inserted: In general.—] [inserted: Except as provided in subparagraph (B), an applicant for a license under this section shall submit to the Commission an application not later than 1 year after the date on which the applicant files a notification of intent under paragraph (1).]
(B) [inserted: Existing license deadline.—] [inserted: Notwithstanding section 15(c)(1), an applicant for a license under this section shall file an application with the Commission not later than 1 year before the date of expiration of the term of an existing license, if applicable.]
(3) [inserted: Deadline for issuance.—] [inserted: The Commission shall take final action on an application for a license under this section not later than 1 year after the date on which the application is filed under paragraph (2).]
(4) [inserted: Schedule for final action.—] [inserted: To the extent reasonably practicable, the Commission and any applicable conditioning or permitting agencies shall establish, with respect to each micro hydrokinetic energy project that is the subject of a notification of intent to apply for a license under this section, a joint schedule that permits the timely completion of decisions required to be made with respect to, and the timely issuance of, authorizations required under Federal law by the Commission and the conditioning or permitting agencies, subject to the requirement that any joint schedule established under this paragraph shall comply with the deadline for final action established under paragraph (3).]
(d) [inserted: Regulations.—]
(1) [inserted: In general.—] [inserted: Not later than 180 days after the date of enactment of this section, the Commission shall promulgate regulations to implement this section in a manner that expedites the deployment of micro hydrokinetic energy projects while ensuring the safe operation of the micro hydrokinetic energy project in compliance with applicable Federal and State laws.]
(2) [inserted: Inclusion.—] [inserted: The regulations promulgated under paragraph (1) shall provide for the use of 1 or more categorical exclusions, including allowing for extraordinary circumstances under which the categorical exclusion shall not be available, under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for low disturbance activities necessary for micro hydrokinetic energy projects.]
(e) [inserted: Report to congress.—] [inserted: The Commission shall submit to Congress a report describing the impacts of the micro hydrokinetic energy projects licensed under this section on the environment, the economy, and the reliability and affordability of electricity not later than the earlier of—]
(1) [inserted: the date that is 5 years after the date of enactment of this section; and]
(2) [inserted: the date on which the first 50 micro hydrokinetic energy projects licensed under this section have been operational for not less than 1 year.]
(f) [inserted: Savings clause.—] [inserted: Nothing in this section affects any authority of the Commission, at the election of an applicant, to license the construction, operation, and maintenance of project works for a micro hydrokinetic energy project under any other provision of this part.]
16 U.S.C. § 824 Declaration of policy; application of subchapter
5 changes the bill asks for here, 2 carried out
- Carried out:
Section 201 of the Federal Power Act (16 U.S.C. 824) is amended by adding at the end the following:
(h) Qualifying BTM DES facilities and aggregations.— The designation of a facility as a qualifying BTM DES facility or an aggregation of 2 or more facilities as a qualifying BTM DES aggregation does not, of itself, subject any of the following to the jurisdiction of the …
- Not carried out:
in the first sentence, by striking
and 222
and inserting222, 225, 226, 226A, 227, 228, 229, 230, 231, 232, and 233
; and“and 222” isn't in § 824(b)(2) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“and 222” not found in /us/usc/t16/s824/b/2 - Not carried out:
in the second sentence, by striking
or 222
and inserting222, 225, 226, 226A, 227, 228, 229, 230, 231, 232, or 233
; and“or 222” isn't in § 824(b)(2) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“or 222” not found in /us/usc/t16/s824/b/2 - Carried out:
by striking
206(f),
; and - Not carried out:
by striking
or 222
and inserting222, 225, 226, 226A, 227, 228, 229, 230, 231, 232, or 233
.“or 222” isn't in § 824(e) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“or 222” not found in /us/usc/t16/s824/e
§ 824(d)–(g)
Start of § 824 to (c) unchanged ·
(d) “Sale of electric energy at wholesale” defined The term “sale of electric energy at wholesale” when used in this subchapter, means a sale of electric energy to any person for resale.
(e) “Public utility” defined The term “public utility” when used in this subchapter and subchapter III of this chapter means any person who owns or operates facilities subject to the jurisdiction of the Commission under this subchapter (other than facilities subject to such jurisdiction solely by reason of section 824e(e), [struck: 824e(f), ]824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, or 824v of this title).
(f) United States, State, political subdivision of a State, or agency or instrumentality thereof exempt No provision in this subchapter shall apply to, or be deemed to include, the United States, a State or any political subdivision of a State, an electric cooperative that receives financing under the Rural Electrification Act of 1936 (7 U.S.C. 901 et seq.) or that sells less than 4,000,000 megawatt hours of electricity per year, or any agency, authority, or instrumentality of any one or more of the foregoing, or any corporation which is wholly owned, directly or indirectly, by any one or more of the foregoing, or any officer, agent, or employee of any of the foregoing acting as such in the course of his official duty, unless such provision makes specific reference thereto.
(g) Books and records
§ 824(g)–(h)
(g)(1)–(4) unchanged ·
(B) in any way limit rights to obtain records and other information under Federal law, contracts, or otherwise.
(5) As used in this subsection the terms “affiliate”, “associate company”, “electric utility company”, “holding company”, “subsidiary company”, and “exempt wholesale generator” shall have the same meaning as when used in the Public Utility Holding Company Act of 2005 [42 U.S.C. 16451 et seq.].
(h) [inserted: Qualifying BTM DES facilities and aggregations.—] [inserted: The designation of a facility as a qualifying BTM DES facility or an aggregation of 2 or more facilities as a qualifying BTM DES aggregation does not, of itself, subject any of the following to the jurisdiction of the Commission:]
(1) [inserted: The facility or aggregation.]
(2) [inserted: The retail electric service provided to or for the facility or aggregation.]
(3) [inserted: The distribution service on which the facility or aggregation relies.]
16 U.S.C. § 824p Siting of interstate electric transmission facilities
22 changes the bill asks for here, 17 carried out
- Carried out:
Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (a) and inserting the following:
(a) Definitions.— In this section: (1) Affected landowner.— The term “affected landowner” includes each owner of a property interest in affected property, including— (A) the Federal Government; (B) a State or local government; and (C) each owner noted in the most recent county …
- Carried out:
in the matter preceding paragraph (1), by striking
Except
and all that follows throughfinds that
and insertingExcept as provided in subsections (d)(1) and (i), the Commission shall, after notice and an opportunity for hearing, including a public comment period of at least 45 days, issue one or more permits to individual or joint applicants for the construction or modification of electric transmission facilities necessary in the national interest if the Commission finds that
; - Carried out:
in subparagraph (A)(i), by inserting
or modification
aftersiting
; and - Carried out:
in the matter preceding clause (i), by inserting
or modification
aftersiting
; and - Not carried out:
in clause (i), by striking
the later of
in the matter preceding subclause (I) and all that follows through the semicolon at the end of subclause (II) and insertingthe date on which the application was filed with the State commission or other entity;
; and“the later of” isn't in § 824p(b)(1)(C)(i)(II) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“the later of” not found in /us/usc/t16/s824p/b/1/C/i/II - Carried out:
by striking paragraphs (2) through (6) and inserting the following:
(2) the proposed facilities will be used for the transmission of electric energy in interstate commerce (including transmission from the outer Continental Shelf to a State) or foreign commerce; (3) the proposed construction or modification is consistent with the public interest; …
- Carried out:
Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (d) and inserting the following:
(d) State siting and consultation.— (1) Preservation of State siting authority.— The Commission shall have no authority to issue a permit under subsection (b) for the construction or modification of an electric transmission facility within a State except as provided in paragraph …
- Carried out:
Section 216(e)(3) of the Federal Power Act (16 U.S.C. 824p(e)(3)) is amended by striking
shall conform
and all that follows through the period at the end and insertingshall be in accordance with rule 71.1 of the Federal Rules of Civil Procedure.
. - Carried out:
Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (f) and inserting the following:
(f) Cost allocation.— (1) Transmission tariffs.— For the purposes of this section and except as provided in paragraph (2), any transmitting utility that owns, controls, or operates electric transmission facilities that the Commission finds to be consistent with the findings …
- Carried out:
in paragraph (1), by adding at the end the following:
(C) The term “Federal authorization” includes a certification under section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341) from a certifying authority (as defined in subsection (h) of that section) and any other permit, license, concurrence, or approval of a …
- Not carried out:
in paragraph (2), by striking the period at the end and inserting the following:
(A) the Commission shall act as the lead agency in the case of facilities permitted under subsection (b) or section 225; and (B) the Department of the Interior shall act as the lead agency in the case of facilities located on a lease, easement, or right-of-way granted by the …
We can't read how this instruction is worded yet, so it isn't shown in the text.
Technical detail
no-pattern: striking the period at the end and inserting the following: QCONTENT; - Carried out:
in each of paragraphs (3), (4)(B), (4)(C), (5)(B), (6)(A), (7)(A), (7)(B)(i), (8)(A)(i), and (9), by striking
Secretary
each place it appears and insertinglead agency
; - Carried out:
in paragraph (4)(A), by striking
As head of the lead agency, the Secretary
and insertingThe lead agency
; - Carried out:
in paragraph (5)(A), by striking
As lead agency head, the Secretary
and insertingThe lead agency
; - Not carried out:
in subparagraph (A), by striking
18 months after the date of enactment of this section
and inserting18 months after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026
; and“18 months after the date of enactment of this section” isn't in § 824p(h)(7)(A) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“18 months after the date of enactment of this section” not found in /us/usc/t16/s824p/h/7/A - Not carried out:
in subparagraph (B)(i), by striking
1 year after the date of enactment of this section
and inserting18 months after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026
; and“1 year after the date of enactment of this section” isn't in § 824p(h)(7)(B)(i) in the Code as we have it. The law may have changed since the bill was drafted.
Technical detail
“1 year after the date of enactment of this section” not found in /us/usc/t16/s824p/h/7/B/i - Carried out:
by adding at the end the following:
(10) Any order or action of a Federal agency or State administrative agency acting pursuant to Federal law to issue, condition, or deny a Federal authorization shall be subject to judicial review in the same courts in which an order of the Commission is subject to judicial …
- Carried out:
in paragraph (3), by striking
, including facilities in national interest electric transmission corridors
; and - Carried out:
in subparagraph (A), by striking
; and
and inserting a period; - Carried out:
by striking subparagraph (B); and
- Not carried out:
by striking
in disagreement
in the matter preceding subparagraph (A) and all that follows through(A) the
in subparagraph (A) and insertingunable to reach an agreement on an application seeking approval by the
.We can't read how this instruction is worded yet, so it isn't shown in the text.
Technical detail
no-pattern: striking QTEXT in the matter preceding subparagraph (X) and all that follows through QTEXT in subparagraph (X) and inserting QTEXT. - Carried out:
Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (k) and inserting the following:
(k) Jurisdiction.— (1) ERCOT.— This section shall not apply within the area referred to in section 212(k)(2)(A). (2) Other utilities.— (A) In general.— For the purposes of this section, the Commission shall have jurisdiction over all transmitting utilities, including …
§ 824p(a)–(b)
§ 824p. Siting of interstate electric transmission facilities
(a) [struck: Designation of national interest electric transmission corridors][inserted: Definitions.—] [inserted: In this section:]
(1) [inserted: Affected landowner.—] [inserted: The term “affected landowner” includes each owner of a property interest in affected property, including—]
(A) [inserted: the Federal Government;]
(B) [inserted: a State or local government; and]
(C) [inserted: each owner noted in the most recent county or city tax record as receiving the relevant tax notice with respect to that interest.]
[struck: Not later than 1 year after August 8, 2005, and every 3 years thereafter, the Secretary of Energy (referred to in this section as the “Secretary”), in consultation with affected States and Indian Tribes, shall conduct a study of electric transmission capacity constraints and congestion.]
(2) [inserted: Affected property.—] [struck: Not][inserted: The] [struck: less][inserted: term] [struck: frequently than once every 3 years, the Secretary, after considering alternatives and recommendations from interested parties (including an opportunity for comment from ][inserted: “]affected [struck: States][inserted: property”] [struck: and][inserted: means] [struck: Indian][inserted: any] [struck: Tribes),][inserted: land] [struck: shall issue a report, based on the study under paragraph (1) ]or other [struck: information relating to electric transmission capacity constraints and congestion, which may designate as a national interest electric transmission corridor any geographic area that][inserted: property]—
(A) [inserted: that is or will be crossed by the energy transmission facility proposed to be constructed or modified under the applicable permit under subsection (b);]
(B) [inserted: that is or will be used as a facility site with respect to the energy transmission facility proposed to be constructed or modified under the applicable permit under subsection (b);]
(C) [inserted: that abuts any boundary of an existing right-of-way or other facility site that—]
(i) [inserted: is owned by an electric utility; and]
(ii) [inserted: is located not more than 500 feet from the energy transmission facility to be constructed or modified under the applicable permit under subsection (b);]
(D) [inserted: that abuts the boundary of a proposed facility site for the energy transmission facility to be constructed or modified under the applicable permit under subsection (b);]
(E) [inserted: that is crossed by, or abuts any boundary of, an existing or proposed right-of-way that—]
(i) [inserted: will be used for the energy transmission facility to be constructed or modified under the applicable permit under subsection (b); and]
(ii) [inserted: is located not more than 500 feet from the proposed location of that energy transmission facility; or]
(F) [inserted: on which a residence is located not more than 500 feet from the boundary of any right-of-way for that energy transmission facility.]
[struck: (i)] [struck: 1 is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or]
[struck: (ii)] [struck: 2 is expected to experience such energy transmission capacity constraints or congestion.]
(3) [inserted: Commission.—] [struck: Not][inserted: The] [struck: less][inserted: term] [struck: frequently][inserted: “Commission”] [struck: than][inserted: means] [struck: once every 3 years, ]the [struck: Secretary,][inserted: Federal] [struck: in][inserted: Energy] [struck: conducting][inserted: Regulatory] [struck: the study under paragraph (1) and issuing the report under paragraph (2), shall consult with any appropriate regional entity referred to in section 824o of this title][inserted: Commission].
(4) [inserted: Improved reliability.—] [inserted: The term “improved reliability” has the meaning given the term in section 225(a).]
(5) [inserted: Landowner input.—] [inserted: The term “landowner input” means input received—]
(A) [inserted: by the Commission;]
(B) [inserted: from affected landowners, such as farmers and ranchers, in the path of the proposed construction or modification of an electric transmission facility; and]
(C) [inserted: pursuant to notification provided to, and consultation with, those affected landowners, farmers, and ranchers by the Commission.]
(6) [inserted: Secretary.—] [inserted: The term “Secretary” means the Secretary of Energy.]
[struck: In determining whether to designate a national interest electric transmission corridor under paragraph (2), the Secretary may consider whether—]
[struck: (A)] [struck: the economic vitality and development of the corridor, or the end markets served by the corridor, may be constrained by lack of adequate or reasonably priced electricity;]
[struck: (B)]
[struck: (i)] [struck: economic growth in the corridor, or the end markets served by the corridor, may be jeopardized by reliance on limited sources of energy; and]
[struck: (ii)] [struck: a diversification of supply is warranted;]
[struck: (C)] [struck: the energy independence or energy security of the United States would be served by the designation;]
[struck: (D)] [struck: the designation would be in the interest of national energy policy;]
[struck: (E)] [struck: the designation would enhance national defense and homeland security;]
[struck: (F)] [struck: the designation would enhance the ability of facilities that generate or transmit firm or intermittent energy to connect to the electric grid;]
[struck: (G)] [struck: the designation—]
[struck: (i)] [struck: maximizes existing rights-of-way; and]
[struck: (ii)] [struck: avoids and minimizes, to the maximum extent practicable, and offsets to the extent appropriate and practicable, sensitive environmental areas and cultural heritage sites; and]
[struck: (H)] [struck: the designation would result in a reduction in the cost to purchase electric energy for consumers.]
(b) Construction permit Except as provided in [struck: subsection][inserted: subsections] ([inserted: d)(1) and (]i), the Commission [struck: may][inserted: shall], after notice and an opportunity for hearing, [inserted: including a public comment period of at least 45 days, ]issue one or more permits [inserted: to individual or joint applicants ]for the construction or modification of electric transmission facilities [inserted: necessary ]in [struck: a][inserted: the] national interest [struck: electric transmission corridor designated by the Secretary under subsection (a) ]if the Commission finds that—
(1)
(A) a State in which the transmission facilities are to be constructed or modified does not have authority to—
(i) approve the siting [inserted: or modification ]of the facilities; or
(ii) consider the interstate benefits or interregional benefits expected to be achieved by the proposed construction or modification of transmission facilities in the State;
(B) the applicant for a permit is a transmitting utility under this chapter but does not qualify to apply for a permit or siting approval for the proposed project in a State because the applicant does not serve end-use customers in the State; or
(C) a State commission or other entity that has authority to approve the siting [inserted: or modification ]of the facilities—
(i) has not made a determination on an application seeking approval pursuant to applicable law by the date that is 1 year after the later of—
(I) the date on which the application was filed; and
§ 824p(b)–(c)
(b)(1)(C)(i)(II)–(ii) unchanged ·
(iii) has denied an application seeking approval pursuant to applicable law;
(2) the [inserted: proposed ]facilities [struck: to be authorized by the permit ]will be used for the transmission of electric energy in interstate commerce[inserted: (including transmission from the outer Continental Shelf to a State) or foreign commerce];
(3) the proposed construction or modification is consistent with the public interest;
(4) the proposed construction or modification will [struck: significantly][inserted: protect] [struck: reduce][inserted: or] [struck: transmission][inserted: benefit] [struck: congestion][inserted: consumers] [struck: in interstate commerce ]and [struck: protects][inserted: provide] [struck: or][inserted: improved] [struck: benefits consumers][inserted: reliability];
(5) the [struck: proposed][inserted: electric] [struck: construction][inserted: transmission] [inserted: facilities are capable of transmitting electric energy at a voltage of not less than 230 kilovolts ]or[inserted: ,] [struck: modification][inserted: in] [struck: is][inserted: the] [struck: consistent][inserted: case] [struck: with][inserted: of] [struck: sound][inserted: facilities] [struck: national][inserted: that] [struck: energy][inserted: include] [struck: policy][inserted: advanced] [struck: and][inserted: transmission] [struck: will][inserted: conductors] [struck: enhance][inserted: (including] [struck: energy][inserted: superconductors),] [struck: independence][inserted: as defined by the Commission, voltages determined to be appropriate by the Commission]; and
(6) [inserted: if applicable, ]the proposed modification [inserted: (including reconductoring) ]will maximize, to the extent reasonable and economical, the transmission capabilities of existing towers[inserted: ,] [inserted: structures, ]or [struck: structures][inserted: rights-of-way].
(c) Permit applications
(1) Permit applications under subsection (b) shall be made in writing to the Commission.
§ 824p(c)–(h)
(c)(2) unchanged ·
(B) the information to be contained in the application; and
(C) the manner of service of notice of the permit application on interested persons.
(d) [struck: Comments][inserted: State siting and consultation.—]
(1) [inserted: Preservation of State siting authority.—] [inserted: The Commission shall have no authority to issue a permit under subsection (b) for the construction or modification of an electric transmission facility within a State except as provided in paragraph (1) of that subsection.]
(2) [inserted: Consultation.—] [inserted: In any proceeding before the Commission under subsection (b), the Commission shall afford each State in which a transmission facility covered by the permit is or will be located, each affected Federal agency and Indian Tribe, private property owners, and other interested persons, a reasonable opportunity to present their views and recommendations with respect to the need for and impact of a facility covered by the permit.]
(3) [inserted: Landowner input.—] [inserted: In authorizing the construction or modification of an electric transmission facility under subsection (b), the Commission shall take into account landowner input.]
(4) [inserted: State record.—] [inserted: In any proceeding before the Commission under subsection (b), each State in which a transmission facility covered by the permit is or will be located may file with the Commission, and the Commission shall consider, any part of the State record, if applicable, that the State finds to be relevant to the determination of the Commission.]
(5) [inserted: Pre-filing processes.—] [inserted: Any Commission-related pre-filing processes relating to an application submitted under subsection (c) may commence before, but shall commence no later than, an application is submitted to the applicable State commission or other entity that has authority to approve the siting of the applicable facility.]
(6) [inserted: Simultaneous processing.—] [inserted: In the case of transmission facilities that are capable of transmitting electric energy at a voltage of not less than 345 kilovolts, an application under subsection (c) shall be submitted to the Commission simultaneously with, or any time after, the submission of an application to the applicable State commission or other entity that has authority to approve the siting of the applicable facility, and the Commission shall commence a proceeding under subsection (b).]
(7) [inserted: Limitations.—] [inserted: Simultaneous processing under paragraph (6) is subject to the condition that the Commission shall not issue a permit under subsection (b) unless the Commission first makes a finding described in subparagraph (A), (B), or (C) of subsection (b)(1) with respect to the applicable electric transmission facility.]
[struck: In any proceeding before the Commission under subsection (b), the Commission shall afford each State in which a transmission facility covered by the permit is or will be located, each affected Federal agency and Indian tribe, private property owners, and other interested persons, a reasonable opportunity to present their views and recommendations with respect to the need for and impact of a facility covered by the permit.]
(e) Rights-of-way
(1) In the case of a permit under subsection (b) for electric transmission facilities to be located on property other than property owned by the United States or a State, if the permit holder cannot acquire by contract, or is unable to agree with the owner of the property to the compensation to be paid for, the necessary right-of-way to construct or modify, and operate and maintain, the transmission facilities and, in the determination of the Commission, the permit holder has made good faith efforts to engage with landowners and other stakeholders early in the applicable permitting process, the permit holder may acquire the right-of-way by the exercise of the right of eminent domain in the district court of the United States for the district in which the property concerned is located, or in the appropriate court of the State in which the property is located.
(2) Any right-of-way acquired under paragraph (1) shall be used exclusively for the construction or modification of electric transmission facilities within a reasonable period of time after the acquisition.
(3) The practice and procedure in any action or proceeding under this subsection in the district court of the United States shall [struck: conform][inserted: be] [struck: as nearly as practicable to the practice and procedure ]in [struck: a][inserted: accordance] [struck: similar][inserted: with] [struck: action][inserted: rule] [struck: or][inserted: 71.1] [struck: proceeding in the courts ]of the [struck: State][inserted: Federal] [struck: in][inserted: Rules] [struck: which][inserted: of] [struck: the][inserted: Civil] [struck: property is located][inserted: Procedure].
(4) Nothing in this subsection shall be construed to authorize the use of eminent domain to acquire a right-of-way for any purpose other than the construction, modification, operation, or maintenance of electric transmission facilities and related facilities. The right-of-way cannot be used for any other purpose, and the right-of-way shall terminate upon the termination of the use for which the right-of-way was acquired.
(f) [struck: Compensation][inserted: Cost allocation.—]
(1) [inserted: Transmission tariffs.—] [struck: Any][inserted: For] [struck: right-][inserted: the purposes ]of[struck: -way] [struck: acquired][inserted: this] [struck: pursuant][inserted: section] [inserted: and except as provided in paragraph (2), any transmitting utility that owns, controls, or operates electric transmission facilities that the Commission finds ]to [inserted: be consistent with the findings under paragraphs (2) through (5) and, if applicable, (6) of ]subsection ([struck: e][inserted: b]) shall [struck: be][inserted: file] [struck: considered ]a [struck: taking][inserted: tariff] [inserted: or tariff revision with the Commission pursuant to section 205 and the regulations ]of [struck: private][inserted: the] [struck: property][inserted: Commission] [struck: for][inserted: allocating] [struck: which][inserted: the] [struck: just][inserted: costs] [struck: compensation][inserted: of] [struck: is][inserted: the] [struck: due][inserted: new or modified transmission facilities].
(2) [inserted: Exception.—] [struck: Just][inserted: In] [struck: compensation][inserted: the] [struck: shall][inserted: case] [struck: be][inserted: of] an [struck: amount][inserted: exempt] [struck: equal][inserted: transmitting] [struck: to][inserted: utility] [struck: the][inserted: (as] [struck: fair][inserted: defined] [struck: market][inserted: in] [struck: value][inserted: section] [inserted: 225]([struck: including][inserted: a))] [struck: applicable][inserted: that] [struck: severance][inserted: owns,] [struck: damages][inserted: controls, or operates electric transmission facilities described in paragraph (1])[inserted: ,] [struck: of][inserted: the] [inserted: Commission, notwithstanding section 211A(c), shall require ]the [struck: property][inserted: exempt] [struck: taken][inserted: transmitting] [struck: on][inserted: utility] [inserted: to provide transmission services over such facilities pursuant to section 211A and ]the [struck: date][inserted: regulations] of the [struck: exercise][inserted: Commission] [inserted: allocating the costs ]of [struck: eminent][inserted: the] [struck: domain][inserted: new] [struck: authority][inserted: or modified transmission facilities].
(3) [inserted: Transmission benefits.—] [inserted: The Commission shall require that tariffs or tariff revisions filed under this section are just and reasonable and allocate the costs of providing service to customers that benefit, in accordance with the cost-causation principle and at least roughly commensurate with the benefits, including through—]
(A) [inserted: improved reliability;]
(B) [inserted: reduced congestion;]
(C) [inserted: reduced power losses;]
(D) [inserted: greater carrying capacity that delivers improved reliability or reductions in the cost of delivered power;]
(E) [inserted: reduced operating reserve requirements; and]
(F) [inserted: improved access to generation that achieves reductions in the cost of delivered power.]
(4) [inserted: Ratepayer protection.—] [inserted: Customers that receive no benefit, or benefits that are trivial in relation to the costs sought to be allocated, from electric transmission facilities constructed or modified under this section shall not be involuntarily allocated any of the costs of those transmission facilities, provided, however, that nothing in this section shall prevent a transmitting utility from recovering such costs through voluntary agreement with its customers.]
(g) State law Nothing in this section precludes any person from constructing or modifying any transmission facility in accordance with State law.
(h) Coordination of Federal authorizations for transmission facilities
(1) In this subsection:
(A) The term “Federal authorization” means any authorization required under Federal law in order to site a transmission facility.
(B) The term “Federal authorization” includes such permits, special use authorizations, certifications, opinions, or other approvals as may be required under Federal law in order to site a transmission facility.
(C) [inserted: The term “Federal authorization” includes a certification under section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341) from a certifying authority (as defined in subsection (h) of that section) and any other permit, license, concurrence, or approval of a State administrative agency required under Federal law, other than the Coastal Zone Management Act of 1972 (16 U.S.C. 1451 et seq.), in order to site a transmission facility.]
(2) The Department of Energy shall act as the lead agency for purposes of coordinating all applicable Federal authorizations and related environmental reviews of the facility.
(3) To the maximum extent practicable under applicable Federal law, the [struck: Secretary][inserted: lead] [inserted: agency ]shall coordinate the Federal authorization and review process under this subsection with any Indian tribes, multistate entities, and State agencies that are responsible for conducting any separate permitting and environmental reviews of the facility, to ensure timely and efficient review and permit decisions.
(4)
(A) [struck: As][inserted: The] [struck: head of the ]lead agency, [struck: the Secretary, ]in consultation with agencies responsible for Federal authorizations and, as appropriate, with Indian tribes, multistate entities, and State agencies that are willing to coordinate their own separate permitting and environmental reviews with the Federal authorization and environmental reviews, shall establish prompt and binding intermediate milestones and ultimate deadlines for the review of, and Federal authorization decisions relating to, the proposed facility.
(B) The [struck: Secretary][inserted: lead] [inserted: agency ]shall ensure that, once an application has been submitted with such data as the [struck: Secretary][inserted: lead] [inserted: agency ]considers necessary, all permit decisions and related environmental reviews under all applicable Federal laws shall be completed—
(i) within 1 year; or
(ii) if a requirement of another provision of Federal law does not permit compliance with clause (i), as soon thereafter as is practicable.
(C) The [struck: Secretary][inserted: lead] [inserted: agency ]shall provide an expeditious pre-application mechanism for prospective applicants to confer with the agencies involved to have each such agency determine and communicate to the prospective applicant not later than 60 days after the prospective applicant submits a request for such information concerning—
(i) the likelihood of approval for a potential facility; and
(ii) key issues of concern to the agencies and public.
(5)
(A) [struck: As][inserted: The] lead agency[struck: head], [struck: the Secretary, ]in consultation with the affected agencies, shall prepare a single environmental review document, which shall be used as the basis for all decisions on the proposed project under Federal law.
(B) The [struck: Secretary][inserted: lead] [inserted: agency ]and the heads of other agencies shall streamline the review and permitting of transmission within corridors designated under section 503 of the Federal Land Policy and Management Act (43 U.S.C. 1763) by fully taking into account prior analyses and decisions relating to the corridors.
(C) The document shall include consideration by the relevant agencies of any applicable criteria or other matters as required under applicable law.
(6)
(A) If any agency has denied a Federal authorization required for a transmission facility, or has failed to act by the deadline established by the [struck: Secretary][inserted: lead] [inserted: agency ]pursuant to this section for deciding whether to issue the authorization, the applicant or any State in which the facility would be located may file an appeal with the President, who shall, in consultation with the affected agency, review the denial or failure to take action on the pending application.
(B) Based on the overall record and in consultation with the affected agency, the President may—
(i) issue the necessary authorization with any appropriate conditions; or
§ 824p(h)–(i)
(h)(6)(B)(ii)–(D)(iv) unchanged ·
(v) the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1701 et seq.).
(7)
(A) Not later than 18 months after August 8, 2005, the [struck: Secretary][inserted: lead] [inserted: agency ]shall issue any regulations necessary to implement this subsection.
(B)
(i) Not later than 1 year after August 8, 2005, the [struck: Secretary][inserted: lead] [inserted: agency ]and the heads of all Federal agencies with authority to issue Federal authorizations shall enter into a memorandum of understanding to ensure the timely and coordinated review and permitting of electricity transmission facilities.
(ii) Interested Indian tribes, multistate entities, and State agencies may enter the memorandum of understanding.
(C) The head of each Federal agency with authority to issue a Federal authorization shall designate a senior official responsible for, and dedicate sufficient other staff and resources to ensure, full implementation of the regulations and memorandum required under this paragraph.
(8)
(A) Each Federal land use authorization for an electricity transmission facility shall be issued—
(i) for a duration, as determined by the [struck: Secretary][inserted: lead agency], commensurate with the anticipated use of the facility; and
(ii) with appropriate authority to manage the right-of-way for reliability and environmental protection.
(B) On the expiration of the authorization (including an authorization issued before August 8, 2005), the authorization shall be reviewed for renewal taking fully into account reliance on such electricity infrastructure, recognizing the importance of the authorization for public health, safety, and economic welfare and as a legitimate use of Federal land.
(9) In exercising the responsibilities under this section, the [struck: Secretary][inserted: lead] [inserted: agency ]shall consult regularly with—
(A) the Federal Energy Regulatory Commission;
(B) electric reliability organizations (including related regional entities) approved by the Commission; and
(C) Transmission Organizations approved by the Commission.
(10) [inserted: Any order or action of a Federal agency or State administrative agency acting pursuant to Federal law to issue, condition, or deny a Federal authorization shall be subject to judicial review in the same courts in which an order of the Commission is subject to judicial review under section 313, and a court shall have jurisdiction over the action in accordance with the third sentence of subsection (b) of that section, the courts described in that section having original and exclusive jurisdiction over such actions.]
(i) Interstate compacts
(1) The consent of Congress is given for three or more contiguous States to enter into an interstate compact, subject to approval by Congress, establishing regional transmission siting agencies to—
§ 824p(i)–(k)
(i)(1)(A)–(B) unchanged ·
(2) The Secretary shall provide technical assistance to regional transmission siting agencies established under this subsection.
(3) The regional transmission siting agencies shall have the authority to review, certify, and permit siting of transmission facilities[struck: ,] [struck: including facilities in national interest electric transmission corridors ](other than facilities on property owned by the United States).
(4) The Commission shall have no authority to issue a permit for the construction or modification of an electric transmission facility within a State that is a party to a compact, unless the Secretary determines that the members of the compact are in disagreement after the later of—
(A) the date that is 1 year after the date on which the relevant application for the facility was filed[struck: ; and][inserted: .]
[struck: (B)] [struck: the date that is 1 year after the date on which the relevant national interest electric transmission corridor was designated by the Secretary under subsection (a).]
(j) Relationship to other laws
(1) Except as specifically provided, nothing in this section affects any requirement of an environmental law of the United States, including the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
(2) Subsection (h)(6) shall not apply to any unit of the National Park System, the National Wildlife Refuge System, the National Wild and Scenic Rivers System, the National Trails System, the National Wilderness Preservation System, or a National Monument.
(k) [struck: ERCOT][inserted: Jurisdiction.—]
(1) [inserted: ERCOT.—] [inserted: This section shall not apply within the area referred to in section 212(k)(2)(A).]
(2) [inserted: Other utilities.—]
(A) [inserted: In general.—] [inserted: For the purposes of this section, the Commission shall have jurisdiction over all transmitting utilities, including transmitting utilities described in section 201(f), but excluding any ERCOT utility (as defined in section 212(k)(2)(B)) and any exempt transmitting utility that does not voluntarily subject itself to Commission jurisdiction for the purposes of this section.]
(B) [inserted: Clarification.—] [inserted: Being subject to Commission jurisdiction for the purposes of this section shall not make an entity described in section 201(f) a public utility for the purposes of section 201(e).]
[struck: This section shall not apply within the area referred to in section 824k(k)(2)(A) of this title.]
Federal Power Act § 216A Grid capacity expansion in existing rights-of-way New section
1 change the bill asks for here, 1 carried out
- Carried out:
The Federal Power Act is amended by inserting after section 216 (16 U.S.C. 824p) the following:216A. Grid capacity expansion in existing rights-of-way (a) Definitions.— In this section: (1) Applicable electrical standard.— The term
applicable electrical standard
includes— (A) a reliability standard (as defined in section 215(a)); and (B) an applicable standard of the National Electrical Safety Code published by the Institute of Electrical and Electronics Engineers Standards Association. (2) Covered area.— The termcovered area
means an area— (A) within an existing right-of-way; or (B) within the minimum additional area adjacent to an existing right-of-way that is necessary— (i) to comply with applicable electrical standards; or (ii) to complete an activity described in subsection (b). (3) Covered facility.— The termcovered facility
means an existing electric transmission or distribution facility or associated infrastructure (including an electrical substation) that is located within a covered area. (b) Exemptions.— (1) In general.— Activities to maintain or increase the capacity of the electric grid within a covered area, and any Federal agency action authorizing such activities— (A) are a category of actions designated as being categorically excluded from the preparation of an environmental assessment or an environmental impact statement under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and (B) shall not be considered to be— (i) a major Federal action for purposes of that Act; or (ii) an undertaking for purposes of section 306108 of title 54, United States Code. (2) Inclusions.— The activities described in paragraph (1) include— (A) any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation of, or addition to, a covered facility, including— (i) reconductoring; (ii) an increase in operating voltage; (iii) a circuit addition or adjustment; and (iv) installation of advanced transmission technologies (as defined in section 1223(a) of the Energy Policy Act of 2005 (42 U.S.C. 16422(a))); (B) any minimum widening of an existing right-of-way associated with an activity described in subparagraph (A) that— (i) is necessary to comply with applicable electrical standards; or (ii) remains within a covered area; (C) an addition of energy storage at or near a covered facility; and (D) the addition of a parallel circuit within an existing right-of-way..
§ 216A(a)–(b)
§ 216A. [inserted: Grid capacity expansion in existing rights-of-way]
(a) [inserted: Definitions.—] [inserted: In this section:]
(1) [inserted: Applicable electrical standard.—] [inserted: The term “applicable electrical standard” includes—]
(A) [inserted: a reliability standard (as defined in section 215(a)); and]
(B) [inserted: an applicable standard of the National Electrical Safety Code published by the Institute of Electrical and Electronics Engineers Standards Association.]
(2) [inserted: Covered area.—] [inserted: The term “covered area” means an area—]
(A) [inserted: within an existing right-of-way; or]
(B) [inserted: within the minimum additional area adjacent to an existing right-of-way that is necessary—]
(i) [inserted: to comply with applicable electrical standards; or]
(ii) [inserted: to complete an activity described in subsection (b).]
(3) [inserted: Covered facility.—] [inserted: The term “covered facility” means an existing electric transmission or distribution facility or associated infrastructure (including an electrical substation) that is located within a covered area.]
(b) [inserted: Exemptions.—]
(1) [inserted: In general.—] [inserted: Activities to maintain or increase the capacity of the electric grid within a covered area, and any Federal agency action authorizing such activities—]
(A) [inserted: are a category of actions designated as being categorically excluded from the preparation of an environmental assessment or an environmental impact statement under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and]
(B) [inserted: shall not be considered to be—]
(i) [inserted: a major Federal action for purposes of that Act; or]
(ii) [inserted: an undertaking for purposes of section 306108 of title 54, United States Code.]
(2) [inserted: Inclusions.—] [inserted: The activities described in paragraph (1) include—]
(A) [inserted: any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation of, or addition to, a covered facility, including—]
(i) [inserted: reconductoring;]
(ii) [inserted: an increase in operating voltage;]
(iii) [inserted: a circuit addition or adjustment; and]
(iv) [inserted: installation of advanced transmission technologies (as defined in section 1223(a) of the Energy Policy Act of 2005 (42 U.S.C. 16422(a)));]
(B) [inserted: any minimum widening of an existing right-of-way associated with an activity described in subparagraph (A) that—]
(i) [inserted: is necessary to comply with applicable electrical standards; or]
(ii) [inserted: remains within a covered area;]
(C) [inserted: an addition of energy storage at or near a covered facility; and]
(D) [inserted: the addition of a parallel circuit within an existing right-of-way.]
16 U.S.C. § 824s Transmission infrastructure investment
3 changes the bill asks for here, 3 carried out
- Carried out:
in subparagraph (A), by striking
and
after the semicolon at the end;
- Carried out:
in subparagraph (B), by striking the period at the end and inserting
; and
; and - Carried out:
by adding at the end the following:
(C) all prudently incurred costs associated with payments to jurisdictions impacted by electric transmission facilities developed pursuant to section 216 or 225..
§ 824s(b)–(d)
Start of § 824s to (b)(3) unchanged ·
(4) allow recovery of—
(A) all prudently incurred costs necessary to comply with mandatory reliability standards issued pursuant to section 824o of this title;[struck: and]
(B) all prudently incurred costs related to transmission infrastructure development pursuant to section 824p of this title[struck: .][inserted: ; and]
(C) [inserted: all prudently incurred costs associated with payments to jurisdictions impacted by electric transmission facilities developed pursuant to section 216 or 225.]
(c) Incentives In the rule issued under this section, the Commission shall, to the extent within its jurisdiction, provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization. The Commission shall ensure that any costs recoverable pursuant to this subsection may be recovered by such utility through the transmission rates charged by such utility or through the transmission rates charged by the Transmission Organization that provides transmission service to such utility.
(d) Just and reasonable rates All rates approved under the rules adopted pursuant to this section, including any revisions to the rules, are subject to the requirements of sections 824d and 824e of this title that all rates, charges, terms, and conditions be just and reasonable and not unduly discriminatory or preferential.
Federal Power Act § 224 Transmission study New section
1 change the bill asks for here, 1 carried out
- Carried out:
Part II of the Federal Power Act (16 U.S.C. 824 et seq.) is amended by adding at the end the following:224. Transmission study (a) In general.— Not later than 1 year after the date of enactment of this section and every 3 years thereafter, the Secretary of Energy (referred to in this section as the
Secretary
), in consultation with affected States and Indian Tribes, shall conduct a study of electric transmission capacity constraints and congestion. (b) Report.— (1) In general.— Not less frequently than once every 3 years, the Secretary shall issue a report based on the study under subsection (a) or other information relating to electric transmission capacity constraints and congestion. (2) Opportunity for comment.— Before issuing a report under paragraph (1), the Secretary shall— (A) provide an opportunity for comment to affected States and Indian Tribes; and (B) take into consideration any comments received under subparagraph (A) in preparing the report. (3) Identification of areas with capacity constraints and congestion.— After considering alternatives and recommendations from interested parties (including any comments received from affected States and Indian Tribes), the Secretary may identify in a report issued under paragraph (1) any geographic area that— (A) is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or (B) is expected to experience such energy transmission capacity constraints or congestion. (c) Consultation.— Not less frequently than once every 3 years, the Secretary, in conducting the study under subsection (a) and issuing the report under subsection (b), shall consult with affected transmission planning regions (as defined in section 225(a)) and any appropriate regional entity referred to in section 215. (d) Alaska.— The Secretary— (1) shall, in consultation with the State of Alaska and affected Indian Tribes, consider any intrastate transmission capacity constraints and congestion within the State of Alaska in the study under subsection (a); and (2) in issuing the report under subsection (b), may, subject to the approval of the Regulatory Commission of Alaska, identify any geographic area in the State of Alaska that— (A) is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or (B) is expected to experience such energy transmission capacity constraints or congestion. 225. Planning for transmission facilities that enhance grid reliability, affordability, and resilience (a) Definitions.— In this section: (1) Commission.— The termCommission
means the Federal Energy Regulatory Commission. (2) ERO.— The termERO
has the meaning given the term in section 215(a). (3) Exempt transmitting utility.— The termexempt transmitting utility
means a transmitting utility that is— (A) a State or any political subdivision of a State; or (B) an electric cooperative that sells less than 4,000,000 megawatt hours of electricity per year. (4) Improved reliability.— The termimproved reliability
means that, on balance, considering each of the matters described in subparagraphs (A) through (D), reliability is improved in a material manner that benefits customers through at least one of the following: (A) Facilitating compliance with a mandatory standard for reliability approved by the Commission under section 215. (B) A reduction in expected unserved energy, loss of load hours, or loss of load probability (as defined by the ERO). (C) Facilitating compliance with a tariff requirement or process for resource adequacy on file with the Commission. (D) Any other similar material improvement, including a reduction in correlated outage risk. (5) Interregional transmission facility.— The terminterregional transmission facility
means a transmission facility that— (A) is located within 2 or more neighboring transmission planning regions; or (B) significantly impacts the ability of 1 or more transmission planning regions to transmit electric energy among neighboring transmission planning regions. (6) Regional transmission facility.— The termregional transmission facility
means a transmission facility that— (A) is located within 1 transmission planning region; and (B) is not an interregional transmission facility. (7) Transmission planning region.— (A) In general.— The termtransmission planning region
— (i) when used in a geographical sense, means a region for which the Commission determines that electric transmission planning is appropriate, such as a region established in accordance with Order No. 1000 of the Commission, entitledTransmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities
(76 Fed. Reg. 49842 (August 11, 2011)); and (ii) when used in a corporate sense, means the Transmission Organization or other entity responsible for planning or operating electric transmission facilities within a region described in clause (i). (B) Exclusion.— The termtransmission planning region
does not include the Electric Reliability Council of Texas or the region served by members of the Electric Reliability Council of Texas. (b) Jurisdiction.— (1) ERCOT.— This section shall not apply within the area referred to in section 212(k)(2)(A). (2) Other utilities.— (A) In general.— For the purposes of this section, the Commission shall have jurisdiction over all transmitting utilities, including transmitting utilities described in section 201(f), but excluding any ERCOT utility (as defined in section 212(k)(2)(B)) and any exempt transmitting utility that does not voluntarily subject itself to Commission jurisdiction for the purposes of this section. (B) Clarification.— Being subject to Commission jurisdiction for the purposes of this section shall not make an entity described in section 201(f) a public utility for the purposes of section 201(e). (c) Rulemaking requirement.— Not later than 180 days after the date of enactment of this section, the Commission shall, consistent with the requirements of this section, by rule— (1) require each transmission planning region to establish a process for planning for regional transmission facilities in accordance with this section; (2) require neighboring transmission planning regions to jointly establish a process for planning interregional transmission facilities in accordance with this section; (3) require each transmission planning region to submit to the Commission for approval— (A) a regional transmission planning process; and (B) a joint interregional transmission planning process with each of its neighboring transmission planning regions, which requirement may, at the discretion of the transmission planning region, be satisfied through the submission of— (i) a separate joint interregional transmission planning process with each of its neighboring transmission planning regions; or (ii) 1 or more joint interregional transmission planning processes, any of which may be submitted with any 1 or more of its neighboring transmission planning regions; and (4) establish rate treatments for regional and interregional transmission planning and cost allocation. (d) Transmission planning process elements.— The Commission shall require, within the rule under subsection (c), that regional and joint interregional transmission planning processes contain the following elements: (1) Compatibility.— A common set of input assumptions and models, on a consistent timeline, that— (A) allow for the joint identification and selection of specific interregional transmission facilities, and individual identification and selection of specific regional transmission facilities, by transmission planning regions, for construction or modification, including through the use of advanced transmission conductors (including superconductors) and reconductoring; (B) consider, to the extent reasonable and economical, modifications that maximize the transmission capabilities of existing towers, structures, or rights-of-way; and (C) consider interactions with existing regional, interregional, and supplemental transmission plans and planning processes. (2) Transmission benefits.— A common set of benefits for regional and interregional transmission planning and cost allocation, including— (A) improved reliability; (B) reduced congestion; (C) reduced power losses; (D) greater carrying capacity that delivers improved reliability or reductions in the cost of delivered power; (E) reduced operating reserve requirements; and (F) improved access to generation that achieves reductions in the cost of delivered power. (3) Selection criteria.— Criteria governing the selection by transmission planning regions, for construction or modification, of regional and interregional transmission facilities that— (A) provide improved reliability; (B) protect or benefit consumers; and (C) are consistent with the public interest. (e) Deadline; updates.— The regional and joint interregional transmission planning processes required to be submitted to the Commission pursuant to the rule under subsection (c) shall be— (1) submitted to the Commission not later than 2 years after the date of enactment of this section; and (2) updated not less frequently than once every 4 years. (f) Commission review.— The Commission shall— (1) review each regional and joint interregional transmission planning process submitted pursuant to the rule under subsection (c); and (2) approve the regional or joint interregional transmission planning process if the Commission finds that the process— (A) meets the requirements of subsection (d); (B) allocates costs in accordance with subsection (g); (C) ensures that all rates, charges, terms, and conditions will be just and reasonable and not unduly discriminatory or preferential; and (D) is consistent with the public interest. (g) Cost allocation.— (1) Transmission tariffs.— For the purposes of this section and except as provided in paragraph (2), any transmitting utility that owns, controls, or operates electric transmission facilities constructed or modified as a result of this section shall file a tariff or tariff revision with the Commission pursuant to section 205 and the regulations of the Commission allocating the costs of the new or modified transmission facilities. (2) Exception.— In the case of an exempt transmitting utility that owns, controls, or operates electric transmission facilities described in paragraph (1), the Commission, notwithstanding section 211A(c), shall require the exempt transmitting utility to provide transmission services over such facilities pursuant to section 211A and the regulations of the Commission allocating the costs of the new or modified transmission facilities. (3) Requirement.— The Commission shall require that tariffs or tariff revisions filed under this section are just and reasonable and allocate the costs of providing service to customers that benefit, in accordance with the cost-causation principle and at least roughly commensurate with the benefits, including through the benefits described in subsection (d)(2). (4) Ratepayer protection.— Customers that receive no benefit, or benefits that are trivial in relation to the costs sought to be allocated, from electric transmission facilities constructed or modified under this section shall not be involuntarily allocated any of the costs of those transmission facilities. (h) Compliance.— Compliance with a Commission order or rulemaking effective as of the date of enactment of this section, including orders published in the Federal Register on April 28, 2025, December 6, 2024, and June 11, 2024, shall constitute compliance with the regional transmission planning and cost allocation requirements of this section. (i) Construction permit.— For the purposes of obtaining a construction permit under section 216(b), a project that is selected by 1 or more transmission planning regions pursuant to a regional or joint interregional transmission plan in accordance with this section shall be considered to satisfy paragraphs (2) through (5) and, if applicable, (6) of that section. (j) Failure To submit planning process.— In the event that neighboring transmission planning regions (in the case of an interregional planning process) or a single planning region (in the case of a regional planning process) fails to submit to the Commission a regional or joint interregional transmission planning process, as applicable, under this section, the Commission shall, as the Commission determines to be appropriate, grant a request to extend the time for submission of the planning process for not more than 6 months after the deadline the Commission requires for compliance with the rule under subsection (c). (k) NEPA.— For purposes of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.)— (1) any approval of a regional or joint interregional transmission planning process under subsection (f) shall not be considered a major Federal action; and (2) any permit granted under section 216(b) for a project that is selected by transmission planning regions pursuant to a joint interregional transmission plan shall be considered a major Federal action..
§ 224(a)–(d)
§ 224. [inserted: Transmission study]
(a) [inserted: In general.—] [inserted: Not later than 1 year after the date of enactment of this section and every 3 years thereafter, the Secretary of Energy (referred to in this section as the “Secretary”), in consultation with affected States and Indian Tribes, shall conduct a study of electric transmission capacity constraints and congestion.]
(b) [inserted: Report.—]
(1) [inserted: In general.—] [inserted: Not less frequently than once every 3 years, the Secretary shall issue a report based on the study under subsection (a) or other information relating to electric transmission capacity constraints and congestion.]
(2) [inserted: Opportunity for comment.—] [inserted: Before issuing a report under paragraph (1), the Secretary shall—]
(A) [inserted: provide an opportunity for comment to affected States and Indian Tribes; and]
(B) [inserted: take into consideration any comments received under subparagraph (A) in preparing the report.]
(3) [inserted: Identification of areas with capacity constraints and congestion.—] [inserted: After considering alternatives and recommendations from interested parties (including any comments received from affected States and Indian Tribes), the Secretary may identify in a report issued under paragraph (1) any geographic area that—]
(A) [inserted: is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or]
(B) [inserted: is expected to experience such energy transmission capacity constraints or congestion.]
(c) [inserted: Consultation.—] [inserted: Not less frequently than once every 3 years, the Secretary, in conducting the study under subsection (a) and issuing the report under subsection (b), shall consult with affected transmission planning regions (as defined in section 225(a)) and any appropriate regional entity referred to in section 215.]
(d) [inserted: Alaska.—] [inserted: The Secretary—]
(1) [inserted: shall, in consultation with the State of Alaska and affected Indian Tribes, consider any intrastate transmission capacity constraints and congestion within the State of Alaska in the study under subsection (a); and]
(2) [inserted: in issuing the report under subsection (b), may, subject to the approval of the Regulatory Commission of Alaska, identify any geographic area in the State of Alaska that—]
(A) [inserted: is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or]
(B) [inserted: is expected to experience such energy transmission capacity constraints or congestion.]